PEC EPE Chemical study materials
PEC EPE Chemical study resources

PEC EPE Chemical: Process Design, Simulation and Economics

PEC EPE Chemical · Work through your exam, one topic at a time.

All guide sections

Process Design, Simulation and Economics

What the exam tests

Flowsheet synthesis and pinch analysis, equipment sizing, capital and operating cost estimation, profitability measures (NPV, IRR, payback) and simulation practice - convergence, tear streams and property-package selection.

Core rules

  • Six-tenths rule: C₂ = C₁(S₂/S₁)^n with n ≈ 0.6; escalate with a cost index, C_now = C_then(I_now/I_then).
  • Lang factors: installed cost ≈ f_L × purchased equipment cost, with f_L around 3–5 depending on plant type.
  • Working capital is typically 10–20% of fixed capital and must be included in total capital investment.
  • Depreciation is non-cash; tax applies to revenue minus operating cost minus depreciation.
  • NPV = ΣCF_t/(1+i)^t; IRR is the rate where NPV = 0; accept projects with positive NPV at the hurdle rate.
  • Pinch analysis sets minimum hot and cold utility targets; never transfer heat across the pinch.

Worked example

A 100 t/d unit cost USD 500,000 when the CEPCI was 600; the index is now 780 and the new capacity is 400 t/d. Scaled cost = 500,000 × (400/100)^0.6 = 500,000 × 4^0.6 = 500,000 × 2.297 = 1,148,000. Indexed cost = 1,148,000 × (780/600) = 1,493,000. That is a screening-grade estimate (roughly ±30%) suitable for concept selection, not for a funding decision.

Traps

  • Inverting the capacity ratio in the six-tenths rule.
  • Forgetting escalation, or double counting contingency on top of an already-installed cost.
  • Comparing projects of different lives without an equivalent annual cost basis.
  • Selecting a property package that cannot represent the chemistry (ideal gas for an associating polar system).
  • Recycle loops that fail to converge because tear-stream estimates are inconsistent with the overall balance.