The Lapsed Subcontractor: Statutory Employment in Construction

SC Property & Casualty · Put your knowledge to work in context.

All case studies

The Lapsed Subcontractor: Statutory Employment in Construction

Carolina Roofing & Exteriors subcontracted the framing on a 40-unit townhome project in Greenville to Vega Framing, a five-man crew. The subcontract required Vega to carry workers' compensation coverage and to indemnify Carolina. Vega's policy had lapsed for nonpayment three weeks before work began; Carolina's office manager filed the ACORD certificate and never verified it with the carrier. Vega's employee Luis fell 14 feet from a ladder, fracturing his wrist and pelvis. He will be off work 22 weeks. His average weekly wage is $780. Luis's attorney has filed a civil negligence suit against Carolina, and Carolina's CGL carrier has denied coverage. Luis had not elected to be excluded from coverage, and Vega has no assets.

1. Is Carolina liable for workers' compensation benefits to Luis? Is the CGL denial correct?

Read the worked answer

Yes, Carolina is liable. South Carolina's workers' compensation statute makes a contractor who subcontracts part of its work liable for the compensation owed to an employee of a subcontractor that failed to secure coverage. Carolina is the statutory employer, and statutory employment exists whether or not Carolina was negligent and whether or not it knew the policy had lapsed. A certificate of insurance is not coverage; it is a piece of paper, and the lapse predates the injury.

The CGL denial is correct for two independent reasons: the policy excludes obligations imposed by workers' compensation law, and it excludes bodily injury to an employee arising out of and in the course of employment. CGL is not a substitute for comp.

The practical lesson: certificates must be verified with the carrier at inception and at renewal, and uninsured-subcontractor exposure is a real, uninsured balance-sheet risk.

2. Compute the indemnity benefit and explain the waiting period.

Read the worked answer

Rate: two-thirds of the average weekly wage = 0.6667 × $780 = $520.00 per week, subject to the statutory maximum and minimum weekly benefit in effect for the injury year.

Waiting period: South Carolina pays nothing for the first seven days of disability, but if the incapacity lasts more than 14 days, compensation is paid from the date of injury - no seven-day deduction. Luis is out 22 weeks, so the exception applies.

Indemnity: 22 × $520 = $11,440, plus all causally related medical treatment furnished without a dollar cap.

After maximum medical improvement, a permanent partial rating to the wrist and pelvis would be evaluated separately on the scheduled-member and nonscheduled rules; it would be paid in addition to, not instead of, the temporary total disability computed above.

3. Luis has sued Carolina in tort. What happens to that suit, and what recourse does Carolina have?

Read the worked answer

The tort suit is barred. Once Carolina is a statutory employer, the exclusive remedy provision applies to it exactly as it applies to Vega. Luis's exclusive remedy against Carolina is the workers' compensation benefit - which is precisely why the comp claim must be accepted and paid promptly rather than fought.

Recourse: Carolina can pursue contractual indemnity against Vega under the subcontract, but Vega is judgment-proof, so the indemnity is worth very little. A claim against the producer who issued or filed an inaccurate certificate is possible but difficult and does not fund the claim. The realistic risk-transfer tools were: verify coverage directly with Vega's carrier, require Vega to name Carolina as an additional insured on Vega's comp policy where permitted, hold retainage, or buy a dedicated subcontractor-default product.

The exam-tested insight is that the exclusive remedy cuts both ways: it shields Carolina from a tort verdict but converts the exposure into an immediate, non-negotiable comp obligation.