Sanitary Sewer Overflow During Wet-Weather Infiltration

TX Water/Wastewater Operator · Put your knowledge to work in context.

All case studies

Sanitary Sewer Overflow During Wet-Weather Infiltration

A 12-inch vitrified clay gravity sewer carries dry-weather flow of 0.9 MGD to a treatment plant. During a 3-inch rain event, flow at the plant influent jumps to 4.5 MGD within six hours, and a manhole upstream of a 10-inch downstream segment surcharges and overflows into a storm ditch that discharges to a creek. The plant's headworks has a 4.0 MGD peak hydraulic capacity; above that, excess flow backs up the interceptor. The collection system has 40-year-old clay pipe with known root intrusion and offset joints; a smoke test last year flagged 22 defects. The state requires reporting of sanitary sewer overflows (SSOs) to the agency within 24 hours, with public notice if the overflow reaches waters of the state. The overflow was observed at 2:15 a.m. by a night operator.

1. Walk through the immediate response from the moment the overflow is observed, including notification and documentation.

Read the worked answer

Immediate response sequence:

  1. Stop or contain the overflow. Deploy pumps/vacuum trucks to relieve the surcharged manhole, or throttle upstream flow if possible. Place containment (sandbags, booms) at the ditch to limit reach to the creek.
  2. Protect public health. Post warning signs at the creek/ditch, notify downstream users, and sample the receiving water for bacteria (fecal coliform/E. coli) and other parameters per state protocol.
  3. Notify the agency within 24 hours (many states require immediate oral notice and written follow-up). Include location, estimated volume, duration, receiving water, and corrective actions.
  4. Public notice if the overflow reached waters of the state - required by the state's SSO rule; coordinate with the local health department.
  5. Document the time observed (2:15 a.m.), the weather, the estimated spill volume (estimate from manhole dimensions and duration, or metered pump records), photos, and the names of agencies notified.
  6. Clean up the affected area and disinfect where appropriate; dispose of contaminated material properly.

Do not wait for the 24-hour clock to expire - call as soon as the overflow is confirmed.

2. What root-cause analysis and capital/operational fixes would you pursue to prevent recurrence?

Read the worked answer

Root cause: wet-weather inflow/infiltration (I/I) overwhelming a system with known defects, plus a downstream 10-inch bottleneck and a plant headworks limited to 4.0 MGD.

Analysis:

  • Flow monitoring: compare dry-weather (0.9 MGD) to wet-weather (4.5 MGD) - a 5x jump indicates massive I/I. Use flow meters and rainfall data to quantify I/I by sub-basin.
  • CCTV and smoke testing to confirm the 22 flagged defects and find additional sources; root intrusion and offset joints are prime infiltration points.

Fixes:

  • Operational: increase inspection/cleaning frequency, root control (foaming or mechanical), and manhole rehabilitation (seal frames and covers).
  • Capital: line or replace the worst clay segments, seal joints, and rehabilitate manholes. Address the 10-inch downstream bottleneck (upsize or relieve).
  • Storage/peak shaving: add offline storage or a wet-weather equalization basin to shave peak flow to the plant's 4.0 MGD capacity.
  • Plant capacity: evaluate headworks expansion or high-rate treatment for wet weather.

Prioritize by cost-effectiveness and by the segments that overflow first; track post-rehab flow to verify I/I reduction.