Buying Work: Overhead Recovery on a Thin-Margin Buildout
Riverbend Interiors LLC holds a Class B Virginia contractor license and closed last year at $520,000 in revenue. Fixed overhead - office rent, liability and workers' compensation insurance, two trucks, and the owner's salary - runs $138,000 a year. A repeat client invites Riverbend to bid a 14-week tenant buildout. The takeoff shows direct costs of $118,000: labor and burden, materials, a rented lift, and dumpsters. Competitors are pricing comparable work near $150,000, and the owner wants to "buy the work" to keep four carpenters busy through the winter. Terms are monthly billing, net 45, with 10 percent retainage released at final completion and punch-list sign-off. Without this job the crew would be roughly 60 percent utilized.
1. Calculate whether a $150,000 price recovers this job's share of overhead, and state the full-absorption break-even price.
Read the worked answer
Step 1 - Convert annual overhead to a job-length figure. Overhead per week = $138,000 ÷ 52 = $2,653.85 Overhead over 14 weeks = $2,653.85 × 14 = ≈ $37,154
Step 2 - Build the break-even price. Break-even = direct cost + overhead share = $118,000 + $37,154 = ≈ $155,154
Step 3 - Test the $150,000 bid.
- Planned contribution = $150,000 − $118,000 = $32,000 (21.3% of price)
- Overhead that must be recovered = $37,154 (24.8% of price)
- Shortfall = $37,154 − $32,000 = $5,154 under water
Conclusion. At $150,000 the job does not carry its own weight on a full-absorption basis; it is roughly $5,200 short before any overrun. A 5% direct-cost overrun (about $5,900) turns the shortfall into an $11,000 loss. Note the distinction the exam expects: cash break-even is $118,000 (overhead is being paid whether or not this job runs), while full-absorption break-even is about $155,154. Quoting the correct break-even depends on which question you are answering.
2. The owner argues that any price above direct cost "makes money." Evaluate that reasoning and recommend a bid position.
Read the worked answer
The owner is describing contribution margin, which is only half of the decision. A positive contribution is better than an idle crew if and only if several conditions hold:
- The overhead is genuinely unavoidable. If taking the job forces a second superintendent, overtime, or a larger insurance audit premium, those costs are incremental and belong in the direct cost column, not the overhead pool.
- No displacement. If a $210,000 job would arrive in week six and the crew is already committed, the $150,000 job has an opportunity cost that exceeds its contribution.
- No market-price damage. The client is a repeat customer. A deeply discounted number becomes the benchmark for the next negotiation.
- Risk is priced. A 14-week interior buildout with an unknown existing-condition profile carries real overrun exposure; the $5,154 shortfall is smaller than one bad discovery.
Recommended position: bid no lower than about $156,000, or hold $150,000 and issue a written alternates list (defer a portion of the ceiling grid, substitute a specified millwork package, exclude after-hours work). If the owner insists on buying work, put the decision in writing with the contribution analysis attached so the trade-off is documented rather than assumed. Do not bid below $150,000 to 'stay busy' - that is paying the client for the privilege of working.
3. Identify the cash-flow exposure created by the payment terms and name the specific contractual and billing steps that reduce it.
Read the worked answer
Size the exposure.
- Direct cost accrues at roughly $118,000 ÷ 14 = $8,429 per week.
- With monthly billing plus net 45, the first check lands near day 75. By then the company has incurred about $118,000 × (9 ÷ 14) ≈ $75,900 of cost and has collected nothing.
- Retainage of 10% on a $150,000 contract withholds $15,000 until final completion and punch sign-off - months after the last dollar of cost.
So the job is effectively financed by Riverbend's line of credit, and the retained $15,000 is an interest-free loan to the client. Two aggravating factors: retainage is typically calculated on every pay application including change orders, and a disputed punch item can hold the whole release.
Steps that reduce it:
- Bill monthly, in arrears, with the application submitted by a fixed date (e.g., the 25th) and a contractual payment date, not merely 'net 45.'
- Negotiate retainage down to 5% or provide for reduction to 5% once the job is 50% complete, and write the release trigger as 'final completion' rather than 'punch-list sign-off by owner.'
- Request a mobilization payment or materials deposit for the long-lead items.
- Submit lien waivers only in exchange for payment, and condition waivers on collected funds.
- If a payment goes 30 days past due, preserve mechanic's lien rights on the project rather than relying on leverage alone.