ABC Wastewater Treatment Class II: Preliminary and Primary Treatment

ABC Wastewater Treatment Class II · Work through your exam, one topic at a time.

All guide sections

Preliminary and Primary Treatment

Core concepts

Preliminary treatment protects downstream equipment: bar screens and comminutors remove large solids, grit channels or vortex grit units remove sand and eggshell material that would abrade pumps and clog digesters. Know grit removal design (velocity control so organics stay in flow while dense grit settles) and why grit belongs in a landfill, not a digester.

Primary clarification is gravity settling of settleable solids. Key vocabulary: detention time, surface overflow rate (hydraulic loading, gpd/ft²), weir loading rate, and solids loading rate. Typical primary detention is roughly 1.5–2.5 hours; surface overflow rates commonly run 600–1,200 gpd/ft² at average flow. Removal expectations: about 50–65% suspended solids and 25–40% BOD.

Operational indicators: sludge blanket depth, sludge hopper draw schedule, scum removal, and the clarifier's hydraulic profile. Short-circuiting, density currents, and wind-driven currents cause poor settling. Septic conditions (rising H2S, black odorous sludge, gas bubbles) mean sludge is too old - increase wasting/draw frequency.

Traps

Questions confuse surface overflow rate with weir loading rate, or ask what happens when flow increases (overflow rate rises, detention time falls, removal efficiency drops). Another trap: assuming more grit in the digester is harmless - it accumulates and reduces digester volume. Watch for "increase recycle to fix a septic primary clarifier" - that is a secondary-treatment answer.

Worked example / rule of thumb

A 60-ft-diameter clarifier handles 1.5 MGD. Area = 0.785 × 60² = 2,827 ft². Overflow rate = 1,500,000 ÷ 2,827 ≈ 531 gpd/ft². Rule of thumb: if calculated rate exceeds design, expect solids carryover and short detention - check flow equalization or splitting to other units before blaming the sludge collector.