Pricing a Contract With a Number That Will Not Sit Still

ACCA SBL · Put your knowledge to work in context.

All case studies

Pricing a Contract With a Number That Will Not Sit Still

Meridian Rail Components is bidding to supply brake assemblies to a state operator over four years. The tender is fixed-price. Finance has built a model: 18,000 units at $2,400 each, contribution margin 22%, giving a positive NPV of $1.9m at a 9% discount rate. Three assumptions are shaky. Steel is 38% of unit cost and the supplier has signalled index-linked pricing from year two; the current model holds steel flat. The customer requires a 5% performance bond and payment 90 days after acceptance, while Meridian's own suppliers are paid at 30 days. The production line needs $6m of tooling, half of which is only usable for this customer's specification. A competitor has publicly stated it will bid aggressively to win the reference. The bid must be lodged in ten days.

1. Identify the commercial and financial risks in this bid and explain how each should change the appraisal, not just the narrative around it.

Read the worked answer

1. Steel indexation (the biggest number) Steel is 38% of unit cost; if prices rise 10% in year two and the model holds flat, contribution is overstated by roughly 3.8 percentage points of cost - on 18,000 units at $2,400 that is material to a $1.9m NPV. Appraisal change: model steel as an indexed input with a sensitivity range (e.g. +5%/+10%/+15%), and either price an escalation clause into the bid or hold a contingency. A fixed-price bid with floating input cost is a short option sold to the customer.

2. Working capital 90-day receipts against 30-day payments creates a 60-day funding gap on roughly $43.2m annual revenue, i.e. several million of working capital. Appraisal change: the NPV must include the working capital build and release; a model showing only margin and capex overstates value.

3. Bond and tooling The 5% performance bond is a real cost (fee or capital tied up) and a contingent liability. The $3m of customer-specific tooling has no alternative use, so its recovery depends entirely on winning and retaining the contract: treat it as a sunk-if-lost cost and test the downside where the contract is terminated early.

4. Competitive dynamics A rival bidding for reference will compress price. Appraisal change: run the bid at lower margin to find the walk-away price; a positive NPV at current assumptions is not evidence the bid is winnable.

5. Contract term risk Four-year fixed price with indexed costs and no volume guarantee transfers input and volume risk to Meridian.

2. Recommend the bid strategy the board should approve, including the price position and the conditions attached.

Read the worked answer

Recommended strategy: bid, but conditionally and at a lower margin than the model assumes.

Price position

  • Re-run the model with indexed steel and working capital; expect NPV to fall substantially. Set the bid price so that NPV remains positive at the +10% steel scenario. If it does not, the contract is not worth winning at any price the customer will accept.
  • Establish a walk-away price before negotiations and have the board approve it, so the bid team cannot be talked down under time pressure.

Conditions to attach to the bid

  1. A steel escalation clause (index-linked) or a shorter price-firm period with renegotiation.
  2. Milestone payments or a reduced payment term; if the customer insists on 90 days, price the financing cost in.
  3. A minimum volume commitment or take-or-pay element to protect the $3m specific tooling.
  4. Clarify termination compensation for the non-recoverable tooling.

Strategic considerations

  • The reference value of a state operator contract may justify a thinner margin, but that value should be quantified, not assumed. If the reference is worth, say, $X of future business, the board can consciously accept a lower NPV - but it should record that as a strategic investment decision, not disguise it as a profitable bid.
  • Do not chase the aggressive competitor blindly; a loss-making four-year contract consumes capacity that could serve other customers.

Governance Approve in principle subject to the revised model and a delegated authority for the final price within a defined band. Ten days is enough for a sensitivity run; it is not enough to renegotiate the customer's payment terms, so the bid should carry the conditions as qualifications.