ACMSO ACMS: Production Planning and Scheduling

ACMSO ACMS · Work through your exam, one topic at a time.

All guide sections

Production Planning and Scheduling

Core concepts

Production planning decides what and how much to make; scheduling decides when and in what order. Candidates should understand demand forecasting, capacity planning, master production scheduling, material requirements planning (MRP), and shop-floor scheduling rules. Key vocabulary includes lead time, work-in-process, bottleneck, changeover, and safety stock.

What to know cold

  • MRP logic: requirements explode from the master schedule through the bill of materials, offset by lead times.
  • Capacity: rough-cut versus detailed; the bottleneck constrains throughput.
  • Scheduling rules: earliest due date, shortest processing time, first-come-first-served; each trades due-date performance against efficiency.
  • Lean concepts: takt time, pull systems, setup reduction.
  • Lot sizing: larger lots reduce changeover cost but raise inventory and lead time.

Traps in questions

A frequent trap is optimizing a non-bottleneck resource - local efficiency at a non-bottleneck does not raise throughput and can increase WIP. Another is confusing lead time with processing time; queue time often dominates. Questions may also test whether adding capacity everywhere helps - it does not if the bottleneck remains.

Rule of thumb

Throughput is set by the bottleneck. Apply improvement and scheduling focus there first; protect it with buffers and reduce its changeover time. A useful check: system output cannot exceed bottleneck output regardless of upstream capacity.

Worked example

A line runs 100 units/hour at the bottleneck but a downstream station runs 120/hour. Raising the downstream station to 150/hour changes nothing; raising the bottleneck to 110/hour raises system output to 110/hour, provided upstream supply keeps pace.