Post-acquisition consolidation of issue type and workflow schemes

ACP-420 · Put your knowledge to work in context.

All case studies

Post-acquisition consolidation of issue type and workflow schemes

Northwind acquired a supplier and now runs support (SUP) and engineering (ENG) as separate company-managed projects on one Jira Cloud site. SUP: 21,000 issues, issue types Bug, Task and Sub-task, workflow with Open, Waiting for Customer, Resolved, Closed. ENG: 9,400 issues, issue types Story, Bug, Epic, Task and Sub-task, Scrum board with two active sprints, workflow with Backlog, In Progress, In Review, Done. SUP uses a Kanban board. Leadership wants one issue type scheme and one workflow scheme across both projects so a single filter and dashboard can report cycle time. Two shared filters owned by the support manager feed a weekly report. 'Customer' is required on SUP's create screen only. Sub-tasks are used in both.

1. Design the consolidated issue type scheme. What can and cannot be done by editing schemes, and what must happen first?

Read the worked answer

The union is easy; deletion is the trap. Issue types are global objects - a scheme merely selects them. So confirm first that SUP's Bug and ENG's Bug are the same object and not two near-duplicates created by an admin years ago (names like 'Bug ' or 'Defect'). Duplicates are the only thing here that would force a real migration.

Build one new scheme: Epic, Story, Bug, Task, Sub-task. Then:

  1. Adding a type is safe - assign both projects to the new scheme and SUP simply gains Story/Epic.
  2. Removing a type is not - Jira refuses to remove an issue type from a scheme while issues of that type exist in a project using the scheme. Because you only add, no migration is needed. Do not try to standardise by deleting.
  3. Set the default issue type deliberately - it drives the Create button and API/portal fallbacks. Task is the safest shared default; leaving it as Story would have support agents creating stories.
  4. Before assigning, confirm every included type is on each project's create screen and has a workflow in the workflow scheme. Missing either produces 'issue type is not valid' or 'no workflow associated' errors at create time, which read like permissions bugs.
  5. Sub-tasks: keep one sub-task type. Multiple sub-task types across projects quietly break boards, filters and hierarchy reports.
  6. 'Customer is required on SUP only' survives the consolidation - required-ness is a field-configuration property, and each project keeps its own field configuration scheme.

2. Now the workflows. Compare the consolidation options and recommend one, including how you execute the switch.

Read the worked answer

The goal is comparable reporting, not identical workflows.

  • Option A - one shared workflow with the union of statuses. Cheapest to maintain, but it creates illegal paths: an ENG story can be moved to 'Waiting for Customer', and every ENG board must map a status its team never uses. Every future change requires cross-team coordination.
  • Option B - one workflow scheme, two workflows, mapped by issue type. Workflow schemes map issue type → workflow, so a single scheme can hold SUP's workflow for Task/Sub-task and ENG's for Story/Epic, still satisfying 'one workflow scheme'. Caveat: Bug can map to only one workflow per scheme - pick which project's process governs bugs.

Recommendation: B, plus standardise status categories rather than status names. Report with statusCategory = Done and statusCategory = In Progress and both teams' data aggregates regardless of whether they call the terminal state Resolved, Closed or Done.

Execution: use the workflow scheme switch/migration, mapping every old status to a target status and choosing to save a backup. Statuses with no mapping lose their status (history survives in the changelog, the current status does not). Map the done-category statuses to done-category targets so boards keep counting them as complete. Do it in a change window: the switch triggers re-indexing and can briefly hide issues from boards and filters.

3. What must you inspect on the support manager's two shared filters and the dashboards before and after the switch?

Read the worked answer
  • Ownership. A filter is owned by a person; if the support manager leaves the site, both boards and the weekly report break. Move ownership to a shared service account and share the filter with a group or project role, not with the owner alone.
  • Scope. Rewrite project = SUP deliberately - extend to both projects only if the report is meant to be cross-project. Do not accidentally let the ENG Scrum board pick up SUP issues.
  • Status-name JQL. Any clause naming Resolved, Closed or Waiting for Customer silently changes meaning after the switch. Replace with statusCategory/resolution-based clauses.
  • Gadget permissions. Filters and dashboards have independent sharing. A gadget renders blank or errors for viewers who can see the dashboard but not the filter, so share filters to the same audience as the dashboard.
  • Subscriptions if the weekly report is emailed - recreate them after changing ownership.