ACT Mud Walls study materials
ACT Mud Walls study resources

ACT Mud Walls key terms

ACT Mud Walls · Get comfortable with the vocabulary.

Subsoil selection

Choosing the soil layer beneath the topsoil as wall material, rejecting organic-rich, mica-heavy or strongly expansive deposits and preferring gritty, well-graded soils that compact firmly and shrink little on drying.

Related: Topsoil stripping, Particle size distribution
Topsoil stripping

Removing the upper humus-bearing layer before digging wall material, because decaying plant matter weakens bonds, attracts termites and causes uneven shrinkage and cracking in the finished wall.

Related: Subsoil selection, Organic content check
Organic content check

A quick field or laboratory test, such as a bottle-shake or colour comparison, confirming that borrowed soil contains no decaying plant matter capable of weakening the wall.

Related: Topsoil stripping, Subsoil selection
Particle size distribution

The proportions of gravel, sand, silt and clay in a soil, found by sieving and sedimentation, which govern workability, compacted strength and shrinkage of an earth mix.

Related: Atterberg limits, Subsoil selection
Atterberg limits

The moisture contents marking the boundaries between solid, plastic and liquid behaviour in fine-grained soil, showing how much water a soil tolerates before it becomes unworkable.

Related: Plasticity index, Particle size distribution
Plasticity index

The gap between a soil's liquid limit and its plastic limit; a wide gap signals clay-rich material prone to swelling and shrinkage, which is less suitable for unstabilised walls.

Related: Atterberg limits, Lime stabilisation
Proctor compaction test

A standard laboratory test in which soil is compacted into a mould in layers with a fixed number of blows, relating dry density to moisture content and locating the optimum moisture content.

Related: Optimum moisture content, Dry density
Dry density

The mass of solid soil particles per unit volume of compacted material, the main measure of how thoroughly a wall mix has been densified on site.

Related: Proctor compaction test, Compaction
Binder content by mass

The weight of cement, lime or other stabiliser expressed as a percentage of the oven-dry weight of soil, the standard way of specifying and checking a mix.

Related: Cement stabilisation, Stabiliser
Cement stabilisation

Mixing a measured proportion of Portland cement into moist soil and compacting it before setting begins, giving a stronger, more water-resistant material for walls and foundations.

Related: Binder content by mass, Curing
Lime stabilisation

Adding hydrated or quicklime to clayey soil, where it flocculates the clay, lowers plasticity and slowly raises strength; it works poorly in clean sands.

Related: Plasticity index, Stabiliser
Stabiliser

A binder such as cement, lime, gypsum or bitumen added in small proportions to soil to raise strength and, especially, resistance to softening and erosion by water.

Related: Cement stabilisation, Lime stabilisation, Binder content by mass
Optimum moisture content

The water content at which a soil reaches its greatest dry density under a stated compaction effort; both drier and wetter mixes end up weaker and more porous.

Related: Proctor compaction test, Water content control, Drop test
Water content control

Measuring and adjusting the water in a batch, by drop test, hand squeeze or moisture meter, so the soil compacts densely without slumping or sticking to tools.

Related: Drop test, Optimum moisture content
Drop test

A field check in which a ball of mixed soil is dropped from about one metre; crumbling means too dry, flattening means too wet, and slight deformation suggests correct moisture.

Related: Water content control, Optimum moisture content
Shuttering

Temporary rigid panels of timber, plywood or steel that hold freshly placed earth in position and shape it until compaction is complete and the material can stand alone.

Related: Form release agent, Mould, Compaction
Form release agent

Oil, grease or thin clay slurry brushed on the inside faces of shuttering so earth does not stick and the form lifts away without tearing the wall face.

Related: Shuttering, Mould
Mould

A reusable box or frame, often with a removable base or lid, used to shape individual earth blocks or to form a repeated wall section in place.

Related: Shuttering, Form release agent
Course

A horizontal layer of earth or blocks of uniform thickness running along the wall, placed and compacted as one unit before the next layer begins.

Related: Lift thickness, Running bond
Lift thickness

The depth of a single layer of loose earth placed before compaction, kept small, commonly 100 to 150 millimetres, so the rammer densifies the full depth.

Related: Compaction, Tamping rammer, Course
Compaction

Densifying loose earth by repeated impact or pressure, driving out air voids and raising dry density, which increases strength and reduces later settlement and water absorption.

Related: Tamping rammer, Dry density, Lift thickness
Tamping rammer

A hand tool with a heavy flat or wedge-shaped head, used to strike earth in thin layers until each lift is fully dense before more material is added.

Related: Compaction, Lift thickness
Fibre reinforcement

Short natural fibres such as straw, sisal or coir mixed into earth, usually at one to three percent by volume, to restrain shrinkage cracking and add tensile toughness.

Related: Stabiliser, Render
Bonding

The grip and adhesion between successive layers of earth, or between earth and its foundation, obtained by roughening, moistening and compacting the surfaces where they meet.

Related: Keying, Running bond, Compaction
Running bond

A laying pattern where each course is offset by half a unit from the course below, so vertical joints never align and loads spread sideways through the wall.

Related: Course, Bonding
Keying

Scoring, stepping or indenting a surface so that the next layer of earth or applied render grips mechanically instead of relying on adhesion alone.

Related: Bonding, Render
Quoin

The corner section of a wall, built first and carefully plumbed and levelled, which sets the line, height and thickness for the courses running between corners.

Related: Course, Plumb bob
Lintel

A beam of timber, reinforced concrete or stone spanning a door or window opening, long enough to bear on the wall at both sides and stiff enough to carry the load above.

Related: Curing, Quoin
Curing

Keeping new earth or stabilised wall work damp and shaded for a set period so binder reactions finish and early shrinkage cracks are limited.

Related: Cement stabilisation, Render
Render

A protective coating of earth, lime or cement mortar trowelled onto a wall face to shed rain and bridge small cracks, applied in one or more coats.

Related: Keying, Curing, Erosion
Damp-proof course

A continuous water-resistant layer of bitumen membrane, slate or dense concrete built into the wall near ground level to stop moisture rising by capillary action.

Related: Coping, Toe drain, Erosion
Coping

A protective capping along the top of a wall that slopes to each side and projects slightly, shedding rainwater clear of the wall faces below.

Related: Damp-proof course, Erosion
Erosion

Progressive removal of wall or foundation material by rain splash, running water or wind, controlled by overhangs, plinths, drains, renders and ground vegetation.

Related: Splash apron, Coping, Render
Splash apron

A sloping impervious strip of concrete or stone laid on the ground around the wall base, deflecting falling rain away from the earth foundation.

Related: Toe drain, Erosion
Toe drain

A gravel-filled trench or perforated pipe at the foot of a wall that collects groundwater and carries it away, keeping the foundation soil dry and stable.

Related: Splash apron, Damp-proof course
Excavation shoring

Temporary boards, props or battered slopes supporting the sides of a borrow pit or trench so that soil cannot collapse onto workers below.

Related: Personal protective equipment
Personal protective equipment

Items worn by workers, such as dust masks, gloves, eye protection and safety boots, reducing exposure to silica dust, cuts and crushing injuries on site.

Related: Excavation shoring
Plumb bob

A weighted cord hung freely to define a true vertical, held beside a wall face at several heights to show whether the wall leans.

Related: Quoin, Straightedge
Straightedge

A long rigid bar held against a wall face or course to reveal high spots, hollows and twisting, so defects can be corrected while the material is still workable.

Related: Plumb bob, Render