Adobe Workfront PM Professional study materials
Adobe Workfront PM Professional study resources

Adobe Workfront PM Professional flashcards

Adobe Workfront PM Professional · Build recall with a focused review session.

33 cards. Read the term and the definition here. The deck at the top of this page is optional.

Request Queue
A project configured to accept incoming requests; requires the queue setting enabled and at least one queue topic to route submissions.
Queue Topic
A routing rule inside a request queue that determines which custom form fields appear and to whom the request is assigned.
Routing Rule
A rule that automatically selects a queue topic and default assignee based on criteria such as custom form answers at submission.
Convert Issue to Project
Action that creates a project from a request while keeping the original issue as a linked record for audit history.
Business Case
Intake artifact holding cost, risk, ROI, and alignment data used by the Portfolio Optimizer to rank and score projects.
Duration
The number of working days between a task's planned start and planned completion, excluding weekends and schedule exceptions.
Predecessor Types
Finish-Start, Start-Start, Finish-Finish, and Start-Finish relationships that control how task dates depend on other tasks.
Lag
A delay added to a predecessor relationship in days; negative lag, or lead, allows the successor to overlap the predecessor.
Milestone
A task with zero duration and zero planned hours, used to mark a significant date such as an approval or deliverable.
Critical Path
The longest chain of dependent tasks with zero float; any delay on this path delays the project completion date.
Constraint Type
A scheduling setting such as Must Start On or Start No Earlier Than that overrides dependency-driven date calculation for a task.
Duration Type
A task setting controlling whether changes in work, assignments, or dates affect duration; options include Calculated Assignment and Fixed Dates.
Commitment Date
A user-entered promise date for task completion that can differ from the system-calculated planned completion date.
Percent Complete Mode
A project setting determining whether project progress is derived from duration, effort, or manual entry across child tasks.
Updates Tab
The collaboration area on an object holding comments, mentions, approvals, and system change records that are reportable.
Bulk Task Edit
Selecting multiple tasks in a list and changing fields at once; triggers schedule recalculation when automatic recalc is enabled.
Resource Planner
A tool comparing planned hours by job role against available capacity across a date range and portfolio filter.
Workload Balancer
A view showing assigned work per user with over-allocation highlighted, including an unassigned backlog section for reassignment.
Available Hours
A user's capacity computed from schedule working hours, reduced by FTE percentage, time off, and schedule exceptions.
Scenario Planning
Saving alternative planned-hour allocations per job role in the Resource Planner to compare options before committing to a plan.
Over-allocation
A condition where a user's assigned hours exceed their available hours for a period, typically shown in red.
Text Mode Filter
Report filter syntax using field, operator, and value rows; an OR:1 prefix changes the default AND between rows to OR.
valueexpression
A text mode attribute that builds a calculated column from other fields, often combined with aggregation settings.
Prompt Filter
A runtime filter presented to report viewers that can be configured once and shared across multiple reports on a dashboard.
Dashboard Sections
Layout containers on a dashboard that hold reports; a dashboard supports up to 25 sections arranged in columns and rows.
Scheduled Delivery
A recurring email delivery of a report that runs with current data and the report's saved filter settings at send time.
Velocity
The number of story points a team completes per iteration, averaged over prior iterations and used to forecast future capacity.
Burndown Chart
A chart plotting remaining story points or hours per day across an iteration against the ideal line, revealing scope changes.
Iteration
A time-boxed work period belonging to one Agile team; iterations for the same team cannot overlap in dates.
Proof Automated Workflow
A proof workflow with stages and deadlines where each stage advances when its configured minimum decision count is reached.
Proof Decision Types
The responses available to proof recipients: Approved, Approved with changes, Changes required, and Not relevant.
Access Level
A user's maximum permission tier, such as Planner or Worker; object sharing can only narrow it, never exceed it.
Layout Template
Configuration controlling visible tabs, sections, and fields, assignable to users, groups, job roles, or set as default.