Question 1Request Intake and Project Initiation

Requests that people submit through a published request queue are stored on the project as which type of object?

  1. Requests (issues) Correct answer.
  2. Approval records
  3. Portfolio entries
  4. Planned tasks

Explanation

Submitting through a request queue creates a request (historically called an issue) on the project that owns the queue. Those records can then be triaged, assigned, resolved, or converted into projects.

Question 2Request Intake and Project Initiation

Which Workfront capability allows a project to accept submissions from users through a form-based intake process?

  1. A request queue Correct answer.
  2. A milestone path
  3. An approval process
  4. A routing rule

Explanation

Publishing a project as a request queue gives it a submission form that users can reach from the Requests area. Queue topics and custom forms shape what the requester sees and where the request goes.

Question 3Request Intake and Project Initiation

What is the purpose of a routing rule on a request queue?

  1. To control which access level can view the queue
  2. To send a request to a project, topic, or assignee based on the requester's answers Correct answer.
  3. To define the approval path a request follows after submission
  4. To set the planned duration applied to each new request

Explanation

Routing rules evaluate answers captured on the request form and automatically direct the submission to a chosen project, queue topic, or assignee. They reduce manual triage by acting on what the requester selected.

Question 4Request Intake and Project Initiation

A submitted request needs to become a full project with tasks and a plan. Which action should the project manager take?

  1. Convert it to a project, selecting a template if one is needed Correct answer.
  2. Change its status to Current
  3. Copy the request text into a new project manually
  4. Convert it to a task on the same project

Explanation

The convert action promotes the request into a real project and can apply a template so tasks, assignments, forms, and approvals are created automatically. Manually rebuilding the record loses the link between intake and delivery.

Question 5Request Intake and Project Initiation

Requesters must answer questions such as department and estimated budget when they submit. Which configuration makes those questions appear on the intake form?

  1. Naming the routing rules after the questions
  2. Attaching a custom form to the queue topic or queue details Correct answer.
  3. Adding the questions as tasks in the project plan
  4. Adding the questions to the project's milestone path

Explanation

The questions a requester sees come from the custom form attached to the queue topic or, when no topic is used, to the queue itself. Routing rules can then use those answers to direct the request.

Question 6Request Intake and Project Initiation

Which of the following is a valid setting for 'Who can add requests to this queue' in the queue details?

  1. Only the project sponsor
  2. Only users with a Plan license in the project's group
  3. Only the project owner
  4. Anyone Correct answer.

Explanation

The queue access setting offers choices such as Anyone, people with view access to the project, people in the project's group, or people in the project's company. 'Anyone' makes the queue open to all users who can reach the Requests area.

Question 7Request Intake and Project Initiation

What is the business case primarily used for during project initiation?

  1. Generating invoices for the client
  2. Storing the project baseline for later variance reports
  3. Justifying the request with expenses, risks, goals, and budgeted hours Correct answer.
  4. Recording time entries once work begins

Explanation

The business case gathers the justification data decision-makers need before work is committed, including expenses, risks, goal alignment, and budgeted resource hours. It can also be sent through an approval for review.

Question 8Request Intake and Project Initiation

A queue has many topics. What does a topic group do?

  1. It marks a topic as the default selection for the queue
  2. It organizes related queue topics under a single heading in the request dropdown Correct answer.
  3. It sends every request to one project regardless of the topic chosen
  4. It grants request access to a specific company

Explanation

Topic groups exist to keep a long list of queue topics manageable by nesting related topics under one heading. Requesters still pick an individual topic inside the group to submit.

Question 9Request Intake and Project Initiation

A queue topic has a default assignee configured. What is the effect when a request is submitted through that topic?

  1. The assignee is added to the resulting project's resource pool
  2. The request is automatically assigned to that user or team Correct answer.
  3. The assignee receives edit access to the queue details
  4. The assignee becomes the approver for the request

Explanation

A default assignee on the queue topic pre-fills the assigned-to field on new requests so the right person or team owns triage immediately. Approval responsibilities are set separately by an approval process.

Question 10Request Intake and Project Initiation

A user submits through a queue topic, but none of the intended questions appear on the form. Which configuration gap explains this?

  1. The project has an approval process attached to its status
  2. The project's milestone path was left empty
  3. The request queue was configured with more than one topic group
  4. No custom form was attached to the queue topic or the queue details Correct answer.

Explanation

The fields a requester completes come from the custom form attached to the selected queue topic or to the queue details. If neither has a form, the submission form shows no questions.

Question 11Request Intake and Project Initiation

Where are a project's request routing rules configured?

  1. In the project's business case
  2. In the project's queue details, in the Routing Rules section Correct answer.
  3. In the requester's user profile
  4. In the Setup area's approval processes

Explanation

Routing rules live with the queue setup on the project, in the Routing Rules area of the queue details. Each rule pairs a form answer with a destination such as a project, topic, or assignee.

Question 12Request Intake and Project Initiation

How can a project manager use the business case in an approval process?

  1. The business case can be sent for approval so decision-makers review it before work is committed Correct answer.
  2. The business case must be attached to a queue topic before it can be reviewed
  3. The business case locks the project plan so tasks cannot be added during review
  4. The business case approves the project automatically when the ROI is positive

Explanation

The business case can be submitted through an approval so managers see expenses, risks, and budgeted hours before committing the organization to the work. Approval decisions remain human decisions rather than automatic calculations.

Question 13Request Intake and Project Initiation

What does an alignment scorecard measure in the business case?

  1. How many requests each user has submitted
  2. How closely planned hours match actual hours logged
  3. How well the project supports the goals defined by the organization Correct answer.
  4. How many requests were converted in the previous quarter

Explanation

A scorecard asks a defined set of questions about organizational goals, and the answers produce the alignment score shown on the business case. That score helps compare dissimilar requests on a common basis.

Question 14Request Intake and Project Initiation

A project manager builds projects from a template that already contains custom forms and tasks for a common request type. What is the main benefit at initiation?

  1. The template removes the need for a request queue
  2. The template converts the project into a portfolio
  3. The forms are emailed to the requester automatically
  4. The template's forms and structure are reused in each new project, keeping intake data consistent Correct answer.

Explanation

Templates carry predefined tasks, assignments, custom forms, and approvals into every project created from them. Reusing a template for a frequent request type standardizes the plan and the data collected.

Question 15Request Intake and Project Initiation

Which conversion option keeps the original request in the system after it has been converted to a project?

  1. Resolve as task
  2. Copy issue assignee
  3. Include custom forms
  4. Keep original request Correct answer.

Explanation

Selecting the option to keep the original request preserves the intake record and ties it to the new project. Without it, the request is removed once the conversion succeeds.

Question 16Request Intake and Project Initiation

A submitted request shows as pending approval and no one is working on it. What is the explanation?

  1. An approval process is waiting for approver decisions before work can proceed Correct answer.
  2. The routing rule sent it to a project that is on hold
  3. The topic's default assignee has not accepted the request
  4. The request was converted and then closed

Explanation

When an approval process is attached to a request or its queue topic, the request stays in a pending approval state until approvers respond. Progress resumes only after the approval is granted.

Question 17Request Intake and Project Initiation

Requesters should choose between 'New Hire', 'Hardware', and 'Software' when they open the queue. How should this be configured?

  1. Create three queue topics on the published request queue Correct answer.
  2. Create three routing rules and no queue topics
  3. Create three approval processes
  4. Create three milestone paths

Explanation

Queue topics are the selectable options a requester sees on the submission form, so each category becomes its own topic. Each topic can then carry its own form, default assignee, and routing rules.

Question 18Request Intake and Project Initiation

Which field on a project associates it with a department so that group-level statuses, preferences, and reporting apply?

  1. The Group field Correct answer.
  2. The portfolio owner field
  3. The milestone path
  4. The queue topic

Explanation

The Group field links the project to an organizational unit, which governs available statuses, group-level preferences, and reporting scope. Group administrators also gain administrative rights over the project.

Question 19Request Intake and Project Initiation

Where in the business case can a project manager estimate hours by job role before the project is approved?

  1. Risks
  2. Resource Budgeting Correct answer.
  3. Goals
  4. Expenses

Explanation

The Resource Budgeting area of the business case lets the manager enter budgeted hours per job role so the request can be weighed against available capacity. Those hours can later inform resource planning if the project is approved.

Question 20Request Intake and Project Initiation

Users cannot find a request queue that the project manager believes is published. Which configuration issue would produce this result?

  1. The project has more than one custom form attached
  2. The queue has more than one topic group
  3. The project is in a status that does not equate with Current Correct answer.
  4. The project owner does not have a Plan license

Explanation

A request queue only accepts submissions while the project holding it is active, meaning its status equates with Current. If the project sits in a planning, on-hold, or closed status, the queue is unavailable to requesters.

Question 21Request Intake and Project Initiation

The PMO wants to compare business case scores across many requests against budget and capacity before choosing which to pursue. Which Workfront capability supports this?

  1. Portfolio Optimization Correct answer.
  2. A request queue report
  3. A queue topic routing rule
  4. A milestone path

Explanation

Portfolio Optimization compares the initiatives in a portfolio using their business case scores together with budget and resource capacity. It helps leadership decide which requests to fund and in what order.

Question 22Request Intake and Project Initiation

A request was converted to a project and the option to keep the original request was selected. What happens to the request?

  1. It is marked as resolved and linked to the new project Correct answer.
  2. It becomes a task inside the new project
  3. It remains open and can be converted again
  4. It is deleted after the conversion completes

Explanation

Keeping the original request preserves the intake record, which is then shown as resolved with the new project recorded as the resolving object. This maintains a traceable link between the original ask and the delivered work.

Question 23Request Intake and Project Initiation

Which fields can a routing rule use as its criteria?

  1. Any system field available on the request, such as planned completion date
  2. Any field shown in the request list view
  3. Only project owner and sponsor fields
  4. Custom form fields attached to the queue or the selected queue topic Correct answer.

Explanation

Routing rules evaluate the answers a requester supplies, so their criteria come from custom form fields on the queue or its topics. Fields that the requester never sees cannot drive routing.

Question 24Request Intake and Project Initiation

A project manager wants service desk requests assigned to the support team automatically and reviewed by the support manager before work starts, with no manual triage. Which configuration achieves this with the fewest manual steps?

  1. A scorecard on the business case and a portfolio
  2. A routing rule that sends requests to a project on hold
  3. An access level change for the requester group
  4. A default assignee on the queue topic plus an approval process on that topic Correct answer.

Explanation

The default assignee on the queue topic routes each new request to the support team immediately, and the approval process attached to that topic forces manager sign-off before work begins. Together they remove the need for a person to triage and forward each submission.

Question 25Project Planning, Scheduling, and Dependencies

Which task relationship requires the predecessor task to be finished before the successor task can begin?

  1. Start-to-Finish
  2. Finish-to-Start Correct answer.
  3. Finish-to-Finish
  4. Start-to-Start

Explanation

In a Finish-to-Start relationship the successor's planned start is driven by the predecessor's planned completion, and this is the default relationship type in Workfront.

Question 26Project Planning, Scheduling, and Dependencies

What distinguishes a milestone from a regular task in Workfront?

  1. It is excluded from the critical path
  2. It cannot be assigned to a user
  3. It has zero duration and marks a key date Correct answer.
  4. It automatically becomes a parent task

Explanation

A milestone is a task flagged as a milestone with a duration of zero, so it represents a single point in time rather than a span of work.

Question 27Project Planning, Scheduling, and Dependencies

In Workfront, what does a task's Duration measure?

  1. The total planned hours assigned to the task
  2. The calendar days including weekends and holidays
  3. The number of users assigned to the task
  4. The working days between planned start and planned completion Correct answer.

Explanation

Duration is the number of working days between the task's planned start and planned completion, calculated from the schedule in use. Effort is tracked separately as planned hours.

Question 28Project Planning, Scheduling, and Dependencies

Which Workfront object stores a snapshot of a project's plan so you can later compare the original dates with the current schedule?

  1. A baseline Correct answer.
  2. A milestone path
  3. A task constraint
  4. A predecessor link

Explanation

A baseline captures the approved plan's dates and effort at a point in time; comparing against it shows how far the live schedule has drifted.

Question 29Project Planning, Scheduling, and Dependencies

When a project is configured to schedule from the start date, which task constraint is applied by default to new tasks?

  1. As Soon As Possible Correct answer.
  2. Must Start On
  3. Fixed Dates
  4. As Late As Possible

Explanation

Projects that schedule from the start date default their tasks to As Soon As Possible, so tasks begin as early as their dependencies and the schedule permit.

Question 30Project Planning, Scheduling, and Dependencies

You need Task B to wait until Task A is complete. Where is that relationship established?

  1. Set Task B's constraint to Fixed Dates
  2. Add Task B as a predecessor on Task A
  3. Set Task A's duration to zero
  4. Add Task A as a predecessor on Task B Correct answer.

Explanation

The predecessor is recorded on the successor task, so Task A is entered in the predecessor field of Task B to make B wait for A.

Question 31Project Planning, Scheduling, and Dependencies

What do planned hours on a task represent?

  1. The hours already logged against the task
  2. The maximum hours a resource may log per day
  3. The calendar days the task will span
  4. The estimated work effort needed to complete the task Correct answer.

Explanation

Planned hours express the effort the team estimates the task requires, independent of how many working days the task spans.

Question 32Project Planning, Scheduling, and Dependencies

What does the Gantt chart in Workfront primarily display?

  1. The approval history for the project
  2. A list of project risks and issues
  3. Logged hours by user for each billing period
  4. Task bars positioned on a timeline with dependency lines Correct answer.

Explanation

The Gantt chart plots each task as a bar along a timeline and draws connector lines between tasks that depend on one another, making the schedule sequence visible.

Question 33Project Planning, Scheduling, and Dependencies

A task uses the Effort Driven duration type, has 40 planned hours, and has one assignee at 100% allocation. A second assignee is added at 100% allocation. What is the result?

  1. The duration shortens because the same planned hours are shared by more assignees Correct answer.
  2. The task's constraint changes to Fixed Dates
  3. The planned hours double to match the two assignees
  4. The duration stays the same and each assignee's planned hours are halved

Explanation

Effort Driven holds planned hours constant; adding assignees spreads the same work across more capacity, so the task finishes in fewer working days.

Question 34Project Planning, Scheduling, and Dependencies

A task uses the Calculated Assignment duration type with a single assignee and 8 planned hours over one day. The planned hours are raised to 16 and the assignee stays the same. What happens?

  1. The duration stays at one day
  2. The duration doubles to two days Correct answer.
  3. A second assignee is added automatically
  4. The task is converted into a milestone

Explanation

Calculated Assignment keeps the assignee list fixed and recalculates duration from planned hours and allocation, so doubling the hours doubles the working days.

Question 35Project Planning, Scheduling, and Dependencies

Which duration type keeps a task's duration fixed and recalculates planned hours when assignees are added or removed?

  1. Effort Driven
  2. Calculated Work Correct answer.
  3. Calculated Assignment
  4. Simple

Explanation

Calculated Work fixes the duration and derives planned hours from the number of assignees and their allocations, so adding people increases total planned hours.

Question 36Project Planning, Scheduling, and Dependencies

A task carries the Start No Earlier Than constraint with a date of March 10, and its predecessor finishes on March 3. When does the task start?

  1. March 10, because the task cannot start before that date Correct answer.
  2. The next working day after March 3
  3. March 3, because the predecessor drives the start
  4. It stays unscheduled until the constraint is removed

Explanation

Start No Earlier Than sets a floor on the planned start; scheduling will not pull the task earlier than that date even when the predecessor would allow it.

Question 37Project Planning, Scheduling, and Dependencies

Which constraint pins a task's planned completion date and back-schedules its start date from that date?

  1. Start No Later Than
  2. Finish No Later Than
  3. Must Finish On Correct answer.
  4. As Soon As Possible

Explanation

Must Finish On locks the planned completion date, and Workfront works backward from it using the task's duration and the schedule to place the start.

Question 38Project Planning, Scheduling, and Dependencies

Task A finishes on a Wednesday. Task B has a Finish-to-Start predecessor on Task A with one day of lag, and the project uses a Monday-to-Friday schedule with no holidays. When does Task B start?

  1. Thursday Correct answer.
  2. Wednesday
  3. Monday of the following week
  4. Friday

Explanation

Lag inserts additional waiting time after the predecessor's completion before the successor may begin, so one day of lag after Wednesday pushes the start to Thursday.

Question 39Project Planning, Scheduling, and Dependencies

What is the critical path in a Workfront project?

  1. The tasks carrying the highest priority ranking
  2. The tasks assigned to the project owner
  3. The sequence of tasks with the largest planned hours
  4. The longest chain of dependent tasks, which drives the project's completion date Correct answer.

Explanation

The critical path is the longest dependent chain through the plan; slipping any task on it pushes out the project's completion date.

Question 40Project Planning, Scheduling, and Dependencies

How does Workfront derive a parent task's planned dates from its subtasks?

  1. From the parent task's own duration field only
  2. From the subtask with the most planned hours
  3. From the average of the subtask durations
  4. From the earliest subtask start to the latest subtask completion Correct answer.

Explanation

A parent task spans its children, so its planned start rolls up from the earliest child start and its planned completion from the latest child completion.

Question 41Project Planning, Scheduling, and Dependencies

A task's scheduling mode is set to Completion Date. How does Workfront place the task on the timeline?

  1. It is scheduled as early as its predecessors allow
  2. It inherits the constraint applied to its parent task
  3. It is scheduled as late as possible against its planned completion date Correct answer.
  4. It ignores the predecessors attached to it

Explanation

The Completion Date scheduling mode works backward from the required finish so the task starts as late as it can while still meeting that date.

Question 42Project Planning, Scheduling, and Dependencies

How can a task in one project be made dependent on a task in a different project?

  1. By placing both projects in the same portfolio
  2. By copying the other task into the same project
  3. By giving both tasks the milestone duration type
  4. By adding the other project's task as a cross-project predecessor Correct answer.

Explanation

Workfront supports cross-project predecessors, letting a successor in one project wait on a task that lives in another project.

Question 43Project Planning, Scheduling, and Dependencies

A successor task has a Finish-to-Start predecessor and the As Soon As Possible constraint. The predecessor's planned completion slips by three working days. What happens to the successor?

  1. It is automatically converted into a milestone
  2. Its planned start moves later by three working days Correct answer.
  3. Its dates stay fixed because they were set at creation
  4. Its duration increases by three days

Explanation

With As Soon As Possible in place, the successor has no fixed date pinning it, so it is recalculated forward whenever its predecessor slips.

Question 44Project Planning, Scheduling, and Dependencies

A task has a duration of five days and starts on a Thursday. Assuming a Monday-to-Friday schedule with no holidays, when does it complete?

  1. Thursday of the following week
  2. Wednesday of the following week Correct answer.
  3. Tuesday of the following week
  4. Monday of the following week

Explanation

Counting five working days from Thursday gives Thursday, Friday, Monday, Tuesday and Wednesday, so the task completes on Wednesday of the following week.

Question 45Project Planning, Scheduling, and Dependencies

A task has a Finish-to-Start predecessor and a Must Start On constraint set to a date earlier than the predecessor's completion. What does Workfront do?

  1. It deletes the predecessor relationship from the task
  2. It moves the predecessor earlier so the dependency is satisfied
  3. It leaves the task unscheduled until the conflict is resolved
  4. It places the start on the constrained date and flags that the dependency is at risk Correct answer.

Explanation

A hard constraint such as Must Start On overrides the calculated dependency date, so the task is placed on the required date and the plan shows a scheduling conflict.

Question 46Project Planning, Scheduling, and Dependencies

A Finish-to-Start dependency carries a lag of negative two days. What is the effect on the successor?

  1. The relationship is converted into Start-to-Start
  2. The predecessor's duration is shortened by two days
  3. It can start two days before the predecessor finishes Correct answer.
  4. It starts two days after the predecessor finishes

Explanation

A negative lag, often called lead time, lets the successor begin before the predecessor completes, creating deliberate overlap between the two tasks.

Question 47Project Planning, Scheduling, and Dependencies

Task A starts on day 1 with a duration of 10 days. Task B has a Finish-to-Finish predecessor on Task A with no lag and a duration of 4 days. On which day does Task B start?

  1. Day 4
  2. Day 1
  3. Day 7 Correct answer.
  4. Day 11

Explanation

Finish-to-Finish makes Task B finish when Task A finishes, at the end of day 10. Backing up four working days places Task B's start on day 7.

Question 48Project Planning, Scheduling, and Dependencies

An Effort Driven task has 24 planned hours and one assignee at 100% allocation, giving a three-day duration on an eight-hour day. A second assignee is added at 50% allocation. What is the new duration?

  1. Three days
  2. Four days
  3. One and a half days
  4. Two days Correct answer.

Explanation

Effort Driven keeps the 24 planned hours fixed. Combined capacity becomes 8 hours plus 4 hours per day, so 24 hours takes two working days.

Question 49Project Planning, Scheduling, and Dependencies

A project has Task A with a 4-day duration feeding Task C, and Task B with a 7-day duration also feeding Task C, which has a 3-day duration. All links are Finish-to-Start. Which tasks lie on the critical path?

  1. Tasks A and C
  2. Tasks A, B and C
  3. Tasks B and C Correct answer.
  4. Task C only

Explanation

The chain through Task B runs 7 plus 3 days for a 10-day total, while the chain through Task A runs only 7 days. The longer chain sets the completion date and is therefore critical.

Question 50Project Planning, Scheduling, and Dependencies

A task in a Workfront project is flagged as a milestone. What is the task's duration?

  1. The remaining duration of its parent task
  2. One day
  3. Zero days Correct answer.
  4. The same as its predecessor's duration

Explanation

A milestone is a marker for a single point in time rather than a period of work, so Workfront gives it a duration of zero. It can still carry predecessors, assignees for notification purposes, and custom data, but it consumes no working time on the timeline.