Contract Penalty or Unjust Enrichment?

Armenia Advocate Qualification · Put your knowledge to work in context.

All case studies

Contract Penalty or Unjust Enrichment?

Lilit contracted with a construction company to build a house for 50 million AMD, with a penalty clause of 0.1% per day for delay. The company delayed completion by 100 days. Lilit paid the full contract price but now claims the penalty (5 million AMD) plus 2 million AMD for emotional distress. The company argues that the penalty is excessive and should be reduced under Article 404 of the Civil Code, which allows courts to reduce penalties if they are disproportionate to the loss. Lilit's actual loss from the delay is estimated at 3 million AMD (rent she had to pay). The company also claims that Lilit's emotional distress is not recoverable in contract. Lilit's lawyer argues that the penalty is a liquidated damages clause and should be enforced as agreed.

1. Should the court reduce the penalty? Analyze under the Armenian Civil Code and relevant case law.

Read the worked answer

Under Article 404 of the Armenian Civil Code, a court may reduce a penalty if it is clearly disproportionate to the loss suffered. The penalty here is 5 million AMD, while the actual loss is 3 million AMD. The difference is about 67% above the actual loss, which may be considered disproportionate, especially since the penalty rate of 0.1% per day is not unusually high. Armenian courts have reduced penalties when the amount significantly exceeds the creditor's loss. However, the penalty clause is a agreed remedy, and courts are cautious to interfere with freedom of contract. The key factor is whether the penalty is 'clearly disproportionate'. A 67% excess might not meet that threshold; courts often require a much higher disparity (e.g., double or triple the loss). Additionally, the penalty serves a deterrent function. Therefore, the court might uphold the penalty or reduce it slightly. Lilit's claim for emotional distress is separate: under Armenian law, non-pecuniary damages in contract are generally not recoverable unless provided by law or contract. The Civil Code allows moral damages only in specific cases (e.g., consumer protection). Thus, the 2 million AMD for emotional distress is likely not recoverable.

2. If the court reduces the penalty, what factors should it consider? Provide a reasoned approach.

Read the worked answer

If the court decides to reduce the penalty under Article 404, it should consider: (1) the ratio between the penalty and the actual loss (here 5M vs 3M); (2) the nature of the breach (delay in construction, which is common); (3) the debtor's fault (was the delay due to unforeseen circumstances?); (4) the creditor's interest in timely performance (Lilit needed the house, incurred rent); (5) the penalty rate compared to market standards (0.1% per day is typical); (6) the principle of proportionality and fairness. The court should also consider that the penalty was freely agreed upon by sophisticated parties (assuming the construction company is professional). A reduction is justified only if the penalty is 'clearly disproportionate', meaning it shocks the sense of justice. Given the 67% excess, a court might reduce the penalty to 3.5 or 4 million AMD, aligning it more closely with the loss while preserving some deterrent effect. The court must provide reasoned justification for any reduction, as arbitrary interference with contractual terms is discouraged.