AMPP CCAS study materials
AMPP CCAS study resources

AMPP CCAS study plan

AMPP CCAS · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Surface Preparation

  • Match each surface preparation standard (solvent, hand tool, power tool, brush-off, commercial, near-white, white metal, waterjetting, concrete) to its cleanliness level and the coating systems it supports.

  • Explain how abrasive type, grit size, nozzle pressure, blast angle, and standoff distance change anchor profile and production rate.

  • Compute dew point spread from ambient readings and decide whether preparation and coating application may proceed.

  • Select the correct verification method (visual comparators, surface profile tape or replica, soluble salt patch, conductivity meter, pH test) for a prepared surface and state typical acceptance limits.

Your checkpoint

A one-page decision table mapping every preparation standard to cleanliness level, profile target, and typical coating system with no factual gaps, plus a 20-question self-quiz scored at 80% or higher.

Week 2

Surface Preparation & Coating Materials and Selection

  • Differentiate the waterjetting cleanliness levels and the flash-rust conditions that accompany each.

  • Prescribe concrete surface preparation methods and the profile and moisture/neutralization checks required before coating.

  • Diagnose how inadequate preparation produces specific failures such as disbonding, undercutting, blistering, and early rusting.

  • Classify the main resin families (alkyd, epoxy, polyurethane, zinc-rich, silicone, polysiloxane) by cure mechanism, service temperature, and suitable substrate.

Your checkpoint

A written cause-and-effect list of 15 preparation-related failures with mechanism and corrective action, plus a 30-question timed surface preparation quiz scored at 85% or higher.

Week 3

Coating Materials and Selection

  • Compare primer, intermediate, and topcoat functions and justify a multi-coat system for a given exposure environment.

  • Calculate mix ratio, usable pot life, and induction time for a multi-component coating applied over a known area at a specified thickness.

  • Explain cure mechanisms and the temperature and humidity windows that govern recoat intervals and minimum/maximum overcoat times.

  • Compute wet-film thickness from volume solids and target dry-film thickness, and convert theoretical coverage to practical coverage with a loss factor.

Your checkpoint

A completed worksheet of 10 coating-selection scenarios, each with the chosen system, mixing and wet-film calculation, and recoat window validated against product data.

Week 4

Coating Materials and Selection

  • Rank coating systems by chemical and solvent resistance and identify incompatible primer/topcoat pairings.

  • Distinguish organic and inorganic zinc-rich primers and state their application and curing constraints.

  • Summarize storage, shelf-life, and handling requirements for temperature-sensitive and moisture-sensitive products.

  • Integrate domains 1 and 2 by tracing a specification from substrate condition through selected system to expected service life.

Your checkpoint

A 50-question mixed exam covering surface preparation and coating materials with at least 80% overall and at least 75% in each domain, plus an error log naming the root cause of every miss.

Week 5

Coating Application Methods and Equipment

  • Trace the fluid path of conventional, airless, and plural-component spray systems and state the function of each component.

  • Select tip orifice size and fan angle for a given coating, film thickness target, and geometry, and compute the resulting flow rate.

  • Set and verify spray parameters including fluid pressure, atomization quality, fan overlap, gun angle, distance, and travel speed.

  • Sequence brush and roller work for stripe coats on edges, welds, and back-side areas before spray application.

Your checkpoint

An equipment setup checklist and spray parameter card for two coating types, plus a table of 10 application faults mapped to the parameter that causes each.

Week 6

Coating Application Methods and Equipment & Inspection, Quality Control, and Defect Analysis

  • Explain plural-component proportioning verification and troubleshoot ratio or off-ratio alarms.

  • Outline cleaning, maintenance, and shutdown procedures for solvent-borne and high-solids materials and equipment.

  • Specify measurement of wet-film thickness, dry-film thickness with the appropriate gauge type, and holiday detection for the relevant thickness range.

  • Simulate an ambient-condition hold point and document the accept/reject decision in inspection format.

Your checkpoint

A written inspection plan with 10 inspection points, each listing instrument, reference standard, frequency, and acceptance criterion, plus a 25-question application and inspection quiz scored at 80% or higher.

Week 7

Inspection, Quality Control, and Defect Analysis & Safety, Environmental, and Regulatory Compliance

  • Classify coating defects by root cause, including blistering, pinholes, cratering, orange peel, sagging, amine blush, mud cracking, and disbondment, and prescribe corrective action.

  • Apply adhesion test methods and interpret results against acceptance criteria.

  • Relate safety data sheet sections and exposure limits to PPE and respirator selection for typical coating products and solvents.

  • Design containment, ventilation, and waste-handling steps for a combined abrasive-blasting and spray operation under environmental requirements for dust, VOC, and hazardous waste.

Your checkpoint

A defect atlas of 20 defects with description, root cause, and remedy, plus a one-page job hazard analysis for a blast-and-spray job covering each identified hazard and control.

Week 8

Inspection, Quality Control, and Defect Analysis & Safety, Environmental, and Regulatory Compliance

  • Audit a documentation package (daily reports, inspection records, nonconformance reports) for completeness and traceability against a specification.

  • Apply confined-space, fall-protection, silica-dust, and flammable-liquid controls to a described job scenario.

  • Rehearse all five domains under timed, weighted conditions and correct every missed item back to its root cause.

Your checkpoint

A full-length 100-question mock exam scored at 85% or higher overall and at least 75% in every domain, with a completed error log citing the study note that resolves each miss.

Milestones

Week 2: Surface preparation quiz at 85% or higher and a completed cause-and-effect failure list covering at least 15 mechanisms.

Week 4: Mixed domains 1 and 2 exam at 80% or higher overall and 75% or higher per domain, with every missed item logged by root cause.

Week 6: Inspection plan accepted against a self-review checklist, with all 10 inspection points carrying instrument, standard, and numeric acceptance criteria.

Week 8: Full-length mock exam at 85% or higher overall and 75% or higher in each of the five domains, with an error log showing fewer than 15 unresolved items.