- Adhesion (pull-off) testing
- Related: Cohesive failure, Adhesive failure, Dolly
A quantitative method in which a loading fixture is glued to a cured coating and pulled normal to the surface until the coating detaches, giving a tensile stress value and a failure mode description.
- Dolly
- Related: Adhesion (pull-off) testing
The small cylindrical puck bonded to a coating surface for a pull-off adhesion test; the force at which it detaches, divided by its face area, yields the reported adhesion value.
- Adhesive failure
- Related: Cohesive failure, Adhesion (pull-off) testing
Separation occurring at the interface between coating and substrate, or between two coating layers, leaving no coating on one of the separated faces; usually indicates poor surface preparation or contamination.
- Cohesive failure
- Related: Adhesive failure, Adhesion (pull-off) testing
Rupture within a single material rather than at a bond line, such as within the coating film, within the adhesive, or within the substrate; generally preferred over adhesive failure at the coating-substrate interface.
- Holiday
- Related: Pinhole, High-voltage holiday detection
A discontinuity or void in a coating film that exposes or nearly exposes the substrate, allowing corrosion to initiate; detected with high-voltage or low-voltage holiday detectors depending on film thickness.
- High-voltage holiday detection
- Related: Holiday, Pinhole, Continuity testing
A non-destructive test in which an energized probe is passed over a coating and a spark or audible alarm indicates a discontinuity; used for thicker films where low-voltage wet-sponge testing is unsuitable.
- Continuity testing
- Related: Holiday, High-voltage holiday detection
Verification that a coating film is free of gaps, pinholes, and thin spots over the full inspected area, typically performed with spark, wet-sponge, or similar detectors after the film has cured sufficiently.
- Pinhole
- Related: Holiday, Continuity testing
A tiny hole through a coating film, often formed by solvent escape, air entrapment, or application defects; a type of holiday detectable by continuity testing and significant on immersion service.
- Dry film thickness (DFT)
- Related: Wet film thickness (WFT), Type 1 and Type 2 gauges, Profile
The measured thickness of the cured coating remaining on the substrate, determined with magnetic, eddy-current, ultrasonic, or destructive gauges and compared against the specified minimum and maximum.
- Wet film thickness (WFT)
- Related: Dry film thickness (DFT), Volume solids
The thickness of a coating measured immediately after application while still fluid, commonly with a comb gauge; used with volume solids to predict the dry film thickness that will result.
- Type 1 and Type 2 gauges
- Related: Dry film thickness (DFT), Eddy-current gauge
Magnetic film thickness gauges classified by their magnetic principle: Type 1 uses a permanent magnet, Type 2 uses electromagnetic induction; both apply to ferrous substrates and require calibration on the actual surface.
- Eddy-current gauge
- Related: Type 1 and Type 2 gauges, Dry film thickness (DFT)
A film thickness instrument that induces eddy currents in a conductive non-ferrous substrate and correlates the response with coating thickness; used on aluminum and similar metals where magnetic gauges do not apply.
- Profile
- Related: Surface preparation, Comparator, Anchor pattern
The roughness pattern imparted to a substrate by abrasive blasting or surface preparation, described by its amplitude and angularity; it promotes mechanical adhesion and must be within the specified range.
- Anchor pattern
- Related: Profile, Comparator
The abrasive-blasted surface texture that a coating flows into and grips mechanically; too shallow reduces adhesion, while too deep can leave peaks exposed through the film.
- Comparator
- Related: Profile, Anchor pattern
A reference disc or plate with known surface roughness patches used to visually and tactilely estimate blast profile by comparison with the prepared surface.
- Surface preparation
- Related: Profile, Solvent cleaning, Salt contamination
All operations performed on a substrate before coating application, including cleaning, degreasing, and abrasive blasting, which establish the cleanliness and roughness needed for adequate coating adhesion.
- Salt contamination
- Related: Osmotic blistering, Surface preparation
Soluble chloride, sulfate, and other ionic residues left on a prepared surface, often from marine exposure or blasting; measured by conductivity or test kits because they cause osmotic blistering and premature failure.
- Osmotic blistering
- Related: Salt contamination, Blistering
Coating failure in which water passes through the film and dilutes soluble salts or solvents trapped at the interface, drawing more water in and forming fluid-filled blisters under osmotic pressure.
- Blistering
- Related: Osmotic blistering, Underfilm corrosion
Localized lifting of a coating film into dome-shaped raised areas, caused by trapped solvent, osmotic gradients, corrosion products beneath the film, or poor adhesion; classified by size and density for reporting.
- Underfilm corrosion
- Related: Blistering, Holiday
Corrosion that spreads laterally beneath a coating from a break or defect, lifting the film and producing rust staining or blisters; accelerated by moisture, salts, and poor adhesion.
- Dew point
- Related: Relative humidity, Surface temperature
The temperature at which air must be cooled for water vapor to condense; coating application is generally prohibited when the substrate surface is at or near dew point because moisture harms adhesion.
- Relative humidity
- Related: Dew point, Surface temperature
The amount of water vapor in air expressed as a percentage of the maximum it can hold at that temperature; it affects drying, curing, and the risk of condensation on a surface.
- Surface temperature
- Related: Dew point, Relative humidity
The temperature of the substrate itself, measured with a contact thermometer, which governs coating cure and condensation risk and can differ markedly from ambient air temperature.
- Volume solids
- Related: Wet film thickness (WFT), Dry film thickness (DFT)
The percentage of a coating's liquid volume that remains as dry film after the solvents evaporate; used to calculate wet film thickness needed to achieve a target dry film thickness.
- Stripe coat
- Related: Holiday, Dry film thickness (DFT)
An extra brush-applied coat on edges, welds, corners, and other hard-to-spray areas, applied before or after the main coat to build film where spray coverage is typically thin.
- Zinc-rich primer
- Related: Cathodic protection, Sacrificial coating
A primer containing a high percentage of zinc dust in the dry film that protects steel galvanically, sacrificing itself to protect exposed steel at breaks; requires careful topcoating for immersion service.
- Cathodic protection
- Related: Zinc-rich primer, Sacrificial coating
A technique that makes a metal structure the cathode of an electrochemical cell, using sacrificial anodes or impressed current to suppress corrosion; coatings reduce the current required.
- Sacrificial coating
- Related: Zinc-rich primer, Cathodic protection
A coating that corrodes preferentially to protect the underlying metal, such as zinc or aluminum-rich systems on steel; effective only where electrical contact and electrolyte paths exist.
- Intumescent coating
- Related: Fireproofing, Topcoat
A fire-protective coating that swells and chars when heated, forming an insulating carbonaceous layer that slows temperature rise in the protected steel substrate.
- Fireproofing
- Related: Intumescent coating
Materials and systems applied to structural steel to delay its temperature rise and maintain load capacity during a fire, including intumescent coatings, cementitious sprays, and board products.
- Topcoat
- Related: Primer, Intermediate coat
The final coating layer in a system, chosen for appearance, weather resistance, chemical resistance, or color; it may also carry special properties such as anti-skid or fire protection.
- Primer
- Related: Topcoat, Intermediate coat, Zinc-rich primer
The first coating applied to a prepared substrate, formulated for adhesion and often for corrosion inhibition or galvanic protection; it anchors the rest of the coating system.
- Intermediate coat
- Related: Primer, Topcoat
A coating layer between primer and topcoat that builds total film thickness, improves barrier properties, and helps tie the system together; its color often differs to aid thickness and coverage checks.
- Epoxy coating
- Related: Recoat window, Polyurethane coating
A thermosetting coating based on epoxy resin, valued for adhesion, chemical resistance, and barrier properties; typically requires a recoat window and may chalk when exposed to sunlight.
- Polyurethane coating
- Related: Epoxy coating, Topcoat
A coating based on polyurethane resin, often used as a topcoat for its color and gloss retention and ultraviolet resistance; aliphatic versions resist chalking better than aromatic types.
- Recoat window
- Related: Epoxy coating, Intermediate coat
The time interval after application during which a coating may be successfully overcoated without surface preparation; exceeding it may require abrading the surface to restore adhesion.
- Abrasive blasting
- Related: Profile, Surface preparation, Anchor pattern
Surface preparation by propelling abrasive particles at a substrate to remove rust, mill scale, and old coatings and to create a profile; classified by cleanliness and profile standards.
- Solvent cleaning
- Related: Surface preparation, Salt contamination
Removal of oil, grease, and similar contaminants with solvents or detergents before other surface preparation, preventing contamination from being driven into the surface during blasting.