Sa 2½ blast grade
Near-white blast cleaning per ISO 8501-1; only slight staining is allowed, with no visible oil, grease, dirt, mill scale, rust, or old coating.
Sa 3 blast grade
White metal blast cleaning per ISO 8501-1; the surface is free of all visible contamination and staining, used for the most demanding marine systems.
Surface profile
The roughness of a prepared steel surface, commonly assessed with ISO 8503 comparators or replica tape, and specified to give the coating mechanical key.
Dew point rule
Steel temperature must be at least 3 °C above the dew point during preparation and application to prevent condensation forming on the surface.
Bresle method
A soluble salt test where a patch is applied to the surface, distilled water injected, and the extracted solution measured for conductivity to estimate chloride.
Stripe coating
A brush-applied coat on edges, welds, and corners before full spray application, ensuring minimum film thickness on difficult geometry.
Pot life
The usable time after mixing a two-component coating during which it can still be applied before viscosity rises and application defects occur.
Recoat window
The manufacturer-specified interval between coats; exceeding the maximum may require abrading the surface to restore intercoat adhesion.
Volume solids
The fraction of a coating that remains as dry film after solvent evaporates; used to convert wet film thickness to dry film thickness.
DFT from WFT
Dry film thickness equals wet film thickness multiplied by the volume solids fraction expressed as a decimal, e.g. 200 µm WFT × 0.60 = 120 µm DFT.
Zinc-rich primer
A primer with high metallic zinc content that provides cathodic protection to steel, commonly used in marine immersion and atmospheric systems.
Amine blush
A surface film formed when epoxy cures in high humidity or low temperature; it can impair intercoat adhesion and must be removed before recoating.
Magnetic DFT gauge
An instrument measuring dry film thickness on steel using magnetic or electromagnetic principles; readings are averaged per ISO 19840 or SSPC-PA 2.
Roughness correction
An adjustment applied to DFT readings on blasted steel per ISO 19840 because the profile causes the gauge to overstate the true film thickness.
Holiday test
A test detecting pinholes and discontinuities; a low-voltage wet sponge is used for thin films and high-voltage spark testing for thicker coatings.
Pull-off adhesion test
A destructive test per ISO 4624 where a dolly is bonded to the coating and pulled to measure adhesion strength; the test area must be repaired.
Cross-cut adhesion test
A test per ISO 2409 where a lattice pattern is cut into the coating and tape applied to assess adhesion by the amount of coating removed.
ISO 4628 defects
A series of standards classifying coating defects such as blistering, rusting, cracking, and flaking by quantity and size for consistent visual assessment.
Hold point
A stage in the inspection plan where work cannot proceed until the inspector has verified and signed off on the preceding step.
Witness point
A stage where the inspector must be notified and may attend, but work can proceed if the inspector does not appear.
Nonconformance report
A document recording a deviation from specification, including location, measured value, spec limit, and the agreed disposition.
Pre-job meeting
A meeting before work begins to confirm the specification, inspection plan, hold points, responsibilities, and acceptance criteria among all parties.
Coating system
A specified sequence of coats, typically primer, intermediate, and topcoat, each with defined product and dry film thickness.
Inspection plan
A document defining what will be inspected, how, at which stages, and the acceptance criteria, aligned with the project specification.
Abrasive cleanliness
The requirement that blasting abrasive be free of contaminants such as salts and oil, covered by ISO 11124 and ISO 11126, to prevent embedding contamination.
Weld spatter removal
Removal of weld spatter and grinding of sharp edges before blasting, because irregular geometry causes thin films and early coating failure.
Airless spray parameters
Tip size, fan angle, and pressure settings that control film build and finish; incorrect settings cause thin films, runs, or overspray.
Induction time
The waiting period after mixing a two-component coating before application, allowing chemical reaction to begin as specified by the manufacturer.
Polyurethane topcoat
A topcoat binder offering good gloss and color retention and UV resistance, commonly used as the finish coat in atmospheric marine systems.
Environmental monitoring
Recording ambient temperature, steel temperature, relative humidity, and dew point at each application and inspection stage using calibrated instruments.
Calibration traceability
The requirement that inspection instruments be calibrated against traceable standards, with records kept as part of QC documentation.
Acceptance criteria
The numeric limits in the specification, such as DFT range, adhesion value, or holiday count, against which inspection results are judged.