AMPP Pipeline Coatings study materials
AMPP Pipeline Coatings study resources

AMPP Pipeline Coatings study plan

AMPP Pipeline Coatings · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Corrosion fundamentals and protective coating theory & Pipeline coating types, materials, and selection

  • Define the electrochemical corrosion cell and list the four required elements for pipeline steel corrosion.

  • Differentiate uniform, pitting, crevice, galvanic, microbiologically influenced, and cathodic-disbondment-related degradation modes.

  • Classify the major pipeline coating families (fusion-bonded epoxy, three-layer polyolefin, liquid epoxies, polyurethanes, coal-tar epoxy, tape systems) by chemistry and barrier mechanism.

  • Relate coating selection variables (operating temperature, soil resistivity, cathodic protection interaction, installation method) to candidate coating families.

Your checkpoint

A one-page matrix scoring six coating families against four service environments (buried, subsea, above-ground, high-temperature), with a two-sentence written justification for every score.

Week 2

Corrosion fundamentals and protective coating theory & Surface preparation for pipeline coatings

  • Explain adhesion mechanisms (mechanical keying, chemical bonding, van der Waals forces) and how surface profile and cleanliness govern bond strength.

  • Compare abrasive blast cleaning grades and surface profile ranges appropriate for pipeline coating systems.

  • Identify soluble salt contamination sources and describe field test methods used to quantify them before coating.

  • Sequence the surface preparation steps from pre-cleaning through blast and post-blast inspection, including hold-time controls.

Your checkpoint

An annotated surface preparation decision tree that starts with incoming pipe condition and ends with a go/no-go release criterion, citing at least six controllable variables.

Week 3

Pipeline coating types, materials, and selection & Coating application and application equipment

  • Select an appropriate coating system for three pipeline scenarios with differing temperature, burial, and cathodic protection conditions.

  • Describe application methods for fusion-bonded epoxy, three-layer polyolefin, and liquid-applied systems, including equipment and cure requirements.

  • Calculate wet film thickness from desired dry film thickness and measured volume solids for two coating products.

  • Diagnose common application defects (orange peel, sagging, pinholes, inadequate cure, striping failures) and trace each to a process cause.

Your checkpoint

A three-scenario coating selection case study, each with a selected system, application method, calculated wet film thickness target, and one identified defect risk with mitigation.

Week 4

Surface preparation for pipeline coatings & Coating application and application equipment

  • Set blast parameters (abrasive type, nozzle pressure, standoff distance, angle, travel speed) for a specified surface profile requirement.

  • Describe the function and safe operation of application equipment used for pipeline coatings, including plural-component proportioning and heating systems.

  • Construct a step-by-step application procedure covering surface preparation, primer and topcoat intervals, stripe coating, and cure verification.

  • Troubleshoot three simulated field application problems by identifying the most probable root cause and a corrective action.

Your checkpoint

A mock field work procedure for one coating system covering surface preparation through cure, written so a technician could execute it without additional verbal instruction.

Week 5

Inspection, testing, and defect assessment

  • Select inspection and test methods for holiday detection, dry film thickness, adhesion, and cathodic disbondment based on coating type and specification.

  • Interpret test results against stated acceptance criteria and decide pass, fail, or retest for five worked examples.

  • Classify coating defects by origin (surface preparation, application, handling, or service) using visual and instrument evidence.

  • Document inspection findings in a format traceable to specification clauses and test records.

Your checkpoint

An inspection checklist covering four test methods, each with sampling frequency, instrument requirement, acceptance criterion, and documentation field.

Week 6

Standards, specifications, and safety/environmental requirements

  • Map key standards and specifications to lifecycle stages: surface preparation, application, inspection, and repair.

  • Interpret specification language for coating qualification, pre-production trials, and acceptance testing.

  • Apply safety controls for abrasive blasting, solvent handling, confined-space entry, and plural-component equipment.

  • Identify environmental compliance requirements for abrasive waste, overspray containment, and volatile organic compound limits.

Your checkpoint

A standards cross-reference table linking at least ten standards or specification clauses to the lifecycle stage they govern and the field record they require.

Week 7

Inspection, testing, and defect assessment & Standards, specifications, and safety/environmental requirements

  • Conduct a structured failure investigation using coating history, inspection records, and laboratory evidence.

  • Audit a sample coating specification for gaps, conflicting requirements, and unverifiable acceptance criteria.

  • Write corrective and preventive actions that address root causes rather than symptoms.

  • Re-test weak objectives from Domains 1 through 4 using targeted practice questions.

Your checkpoint

A failure investigation report for one coating failure, including evidence summary, root-cause determination, specification or process gap, and three corrective actions with owners.

Week 8

Corrosion fundamentals and protective coating theory & Pipeline coating types, materials, and selection & Surface preparation for pipeline coatings & Coating application and application equipment & Inspection, testing, and defect assessment & Standards, specifications, and safety/environmental requirements

  • Complete a timed full-length mock examination under exam conditions without references.

  • Analyze every missed question by domain and error type (knowledge gap, misread, or calculation).

  • Re-drill the two lowest-scoring domains with focused review and new practice items.

  • Build a one-page final reference sheet of formulas, acceptance criteria, and standard numbers.

Your checkpoint

A scored mock examination with a written error log and a one-page final reference sheet, targeting a score of at least 85 percent.

Milestones

Week 2: Score at least 80 percent on a 20-question quiz covering corrosion fundamentals and surface preparation, with every missed item rewritten as a corrected statement.

Week 4: Submit the mock field work procedure to a peer or mentor for review and resolve all comments marked as blocking.

Week 6: Complete the standards cross-reference table with no blank cells and correctly match at least 9 of 10 standards to their lifecycle stage.

Week 8: Achieve at least 85 percent on the timed mock examination and show a downward trend in repeat error categories.