APCAT: Planning and Design

APCAT · Work through your exam, one topic at a time.

All guide sections

Planning and Design

Requirements come first

Planning and design questions punish solution-first thinking. The sequence is: elicit requirements, define scope, state objectives, identify constraints and assumptions, assess risk, then design. If an option jumps to a tool or solution before requirements are established, it is almost always wrong regardless of how sensible the solution sounds.

Concepts you must hold

  • Requirement types: functional (what it must do) versus non-functional (performance, usability, accessibility, security, maintainability). Non-functional requirements are frequently forgotten and frequently tested.
  • Scope and boundaries: what is explicitly in and out; the difference between scope change (controlled) and scope creep (uncontrolled).
  • Objectives: specific, measurable, achievable, relevant, time-bound; stated as outcomes rather than activities.
  • Constraints versus requirements: a constraint limits how you may satisfy a requirement; it is not itself a requirement.
  • Traceability: every design decision should link back to a requirement, and every requirement to an acceptance criterion.
  • Risk and assumptions: a risk register with likelihood and impact; an assumptions log that is actively reviewed.
  • Trade-offs: time, cost, quality, and risk are balanced explicitly, with the decision and rationale recorded.

Traps

Treating a constraint as a requirement. Writing objectives that describe activity ("deliver training") rather than result. Confusing a plan with a schedule - the schedule is one component. Failing to define acceptance criteria, so "done" becomes subjective. Accepting vague requirements such as "must be accessible" without a measurable criterion.

Rule of thumb

If a design decision cannot be traced to a requirement, it is a preference - and preferences must be negotiated, documented, and prioritised, not silently adopted.

Worked example

A stakeholder states the system "must be accessible". That is not testable. Convert it into an acceptance criterion that names a standard, a scope, and a verification method, then record who confirmed it and when.