API 570 · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Causes of Deterioration and Failure in Piping Systems

  • Classify at least 15 deterioration mechanisms from API 571 by susceptible alloy, process environment, and the piping component where they initiate.

  • Distinguish CUI, chloride SCC, HTHA, erosion-corrosion, and galvanic corrosion by the inspection method that detects each most reliably.

  • Map each mechanism to the API 570 inspection response it triggers (CML placement, location emphasis, interval shortening).

  • Solve 25 scenario items that describe a failure and ask which mechanism explains it.

Your checkpoint

One-page damage-mechanism matrix (mechanism to susceptible material to typical location to detection method) covering 15 mechanisms, self-quizzed to 90% accuracy.

Week 2

Causes of Deterioration and Failure in Piping Systems & Inspection, Rating, Repair, Alteration, and Rerating of In-Service Piping

  • Compute long-term and short-term corrosion rates from two or more sets of survey thickness readings.

  • Calculate remaining life and minimum required thickness for straight pipe and formed components using the ASME B31.3 formulas cited by API 570.

  • Set inspection intervals and maximum intervals from remaining life and the applicable remaining-life fractions.

  • Apply shorter-interval logic where mechanisms such as CUI, injection points, or soil-to-air interfaces govern.

Your checkpoint

Ten fully worked corrosion-rate, remaining-life, and interval problems with answers and the clause reference supporting each step.

Week 3

Inspection, Rating, Repair, Alteration, and Rerating of In-Service Piping

  • Differentiate repair, alteration, and rerating using API 570 definitions and worked examples.

  • Apply welded-repair requirements: authorization, WPS/PQR qualification, preheat and PWHT, and hardness verification.

  • Evaluate acceptability of temporary repairs and clamped or boxed enclosures, including time limits and documentation.

  • Assign inspection hold points and required NDE for a described repair scenario.

Your checkpoint

Repair-versus-alteration-versus-rerating decision checklist applied to 12 written scenarios, each with a verdict and the documentation it requires.

Week 4

Inspection Practices, Methods, and Referenced Code Requirements

  • Match NDE methods (VT, RT, UT, MT, PT, WFMT, ACFM, shear-wave UT) to the discontinuities they detect and the acceptance criteria they invoke.

  • Select CML grid density and placement for a given piping circuit based on mechanism, geometry, and expected corrosion pattern.

  • Apply API 570 inspection requirements for buried, insulated, and high-temperature piping systems.

  • Extract the referenced-code requirements from ASME B31.3 and B16.5 that govern in-service inspection decisions.

Your checkpoint

NDE selection table plus a completed CML layout for one example circuit with a written justification for each location.

Week 5

Inspection, Rating, Repair, Alteration, and Rerating of In-Service Piping & Inspection Practices, Methods, and Referenced Code Requirements

  • Determine rerating outcomes: reduced MAWP, changed service, and pressure-temperature ratings of flanges and components.

  • Apply requirements for hot taps, line blanks, valve replacement, and bolted joint assembly and integrity.

  • Delineate owner/user, inspector, and repair-organization responsibilities for repair and alteration acceptance.

  • Apply weld acceptance criteria from the referenced fabrication code to given discontinuity indications.

Your checkpoint

Twenty flashcards of numeric and acceptance criteria plus 15 practice problems solved and cross-checked against clause references.

Week 6

Scope, Definitions, and Organization of API 570

  • State the scope and exclusions of API 570 and describe how it interfaces with API 510, API 653, and ASME B31.3.

  • Define key terms including authorized inspector, CML, inspection, repair, alteration, rerating, and MAWP.

  • Describe the roles of the owner/user, inspector, repair organization, and jurisdictional authority.

  • Explain the qualification and certification requirements for an API 570 inspector.

Your checkpoint

Definitions sheet for 35 key terms, self-tested to 90% unaided recall.

Week 7

Records, Reports, and Repair/Replacement Documentation

  • Draft an inspection report containing every element API 570 requires.

  • Record CML thickness data and remaining life in a format traceable to the inspection plan.

  • Assemble a repair/alteration package with the required attachments: WPS/PQR, NDE results, and rerating calculations.

  • Determine record retention periods and record-keeping obligations for inspection and repair documentation.

Your checkpoint

One complete mock inspection report and one repair package for a sample circuit, checked line by line against a requirements checklist.

Week 8

Inspection, Rating, Repair, Alteration, and Rerating of In-Service Piping & Inspection Practices, Methods, and Referenced Code Requirements

  • Complete a full-length timed mock exam covering all five domains and tabulate every miss by domain and error type.

  • Re-work every missed question in the repair, alteration, rerating, and inspection-practice areas back to the governing clause.

  • Rehearse thickness, corrosion-rate, remaining-life, and interval calculations until ten consecutive items are correct without notes.

  • Build a one-page last-look sheet listing interval-setting rules and repair/alteration/rerating triggers.

Your checkpoint

Mock exam score report with a domain breakdown, a written remediation log, and the completed last-look sheet.

Milestones

Week 2: Score 80% or better on a closed-book set of 20 corrosion-rate and remaining-life problems.

Week 4: Score 75% or better on a 40-question timed quiz covering Domains 2, 3, and 4.

Week 6: Recall 35 Domain 1 definitions with at least 90% accuracy on a self-administered quiz.

Week 7: Mock inspection report and repair package satisfy 100% of the checklist of required elements.

Week 8: Score 80% or better overall on the full-length mock exam with no domain below 70%.