API SIFE study plan
API SIFE · Give each week a clear focus.
8 weeks · About 7 hours per week
Source Inspection Fundamentals, Roles, and Quality Surveillance Planning & Fixed Equipment: Pressure Vessels, Heat Exchangers, Piping, Valves, and Fittings
Map the four stages of a source inspection (pre-award review, pre-production meeting, in-process surveillance, final/closeout) to the inspector's authority, communication lines, and documentation duties, and build a one-page role-and-responsibility matrix.
Build a generic inspection and test plan (ITP) for a horizontal ASME Section VIII Division 1 pressure vessel with at least 15 line items, tagging each as hold, witness, monitor, or document review.
Locate and annotate the Section VIII Div. 1 rules for shell thickness, joint efficiency, radiographic requirements by joint type, and impact-test exemption curves in your own copy of the code.
Define quality surveillance planning inputs: purchase order, datasheets, approved drawings, specification deviations, and subcontractor scope, and list what triggers a hold point.
Your checkpoint
A finished role matrix plus a 15-line-item ITP for a pressure vessel, self-scored against a 10-point completeness checklist (all five inspection stages covered, every hold point justified in one sentence).
Fixed Equipment: Pressure Vessels, Heat Exchangers, Piping, Valves, and Fittings & Source Inspection Fundamentals, Roles, and Quality Surveillance Planning
Compare shell-and-tube, plate, air-cooled, and double-pipe heat exchangers on construction, tube-to-tubesheet joint types, expansion provisions, and the inspection points each design demands.
Identify the piping and fitting standards governing dimensions, ratings, and marking for flanges, butt-weld fittings, and valves (ASME B16.5, B16.9, B16.34, API 6D), and state what each standard requires the inspector to verify on the component.
Outline valve testing per API 598: shell test, seat test, backseat test, allowable leakage, and duration, including what changes for metal-seated versus soft-seated valves.
Explain how to convert code and specification requirements into witness and hold points on a vendor ITP, and identify three common vendor ITP gaps.
Your checkpoint
A 20-row component comparison table (heat exchanger types, flange/fitting families, valve classes) with the applicable standard, inspection point, and acceptance document listed for each row.
Materials, Welding, and Fabrication Processes
Interpret material test reports and certificates of compliance, distinguishing EN 10204 type 2.2, 3.1, and 3.2 reports and stating what traceability each provides from heat number to installed component.
Compare SMAW, GTAW, GMAW, FCAW, and SAW on application, deposition, likely defects, and the essential variables that control each.
Read a WPS and supporting PQR and identify mismatched essential variables (process, filler classification, preheat, PWHT, thickness range, position) that would invalidate the qualification.
Describe welder and welding operator qualification logic, including essential and performance variables, position coverage, and continuity requirements.
List fabrication checkpoints for fit-up, alignment, roundness, nozzle orientation, weld prep, preheat, post-weld heat treatment, and dimensional tolerance.
Your checkpoint
A written PQR-versus-WPS discrepancy finding with at least five flagged variables, each annotated with why it is essential and what corrective evidence the vendor would need to supply.
Materials, Welding, and Fabrication Processes & Non-Destructive Examination and Pressure Testing
Build a defect-to-method map linking lack of fusion, porosity, slag, cracks, laminations, and incomplete penetration to the NDE methods most likely to detect each and the orientation limits of each method.
Explain the physical basis, typical applications, and blind spots of visual, penetrant, magnetic particle, radiography, ultrasonic, and positive material identification testing.
State acceptance criteria logic: how code acceptance limits, specification addenda, and fracture mechanics-based criteria can differ, and which governs.
Complete a timed 40-question self-authored quiz spanning domains 1 through 3 and log every missed item with a one-line root cause.
Your checkpoint
A defect-to-method matrix covering at least 10 defect types plus a scored 40-question quiz log showing 80 percent or better, with a written remediation note for each missed question.
Non-Destructive Examination and Pressure Testing
Evaluate radiographs against film-quality requirements for density, sensitivity, and image quality indicators, and describe how technique affects discontinuity detection.
Explain ultrasonic examination variables: probe angle and frequency, calibration blocks, scanning coverage, and amplitude versus length sizing.
Compare ASNT SNT-TC-1A and ISO 9712 personnel certification schemes on employer responsibility, level definitions, and validity, and state how to verify a technician's certification before accepting results.
Review an NDE procedure against a checklist covering scope, reference standards, technique, calibration, acceptance criteria, and reporting, and identify missing elements.
Your checkpoint
A one-page NDE procedure review checklist applied to a sample procedure, producing a written list of at least six deficiencies with the required correction for each.
Non-Destructive Examination and Pressure Testing & Codes, Standards, Documentation, and Release of Equipment
Calculate hydrostatic and pneumatic test pressures from code formulas, apply the temperature correction for the test gauge, and state the holding time and inspection requirements for each.
Specify test-fluid quality limits, chlorides, temperature constraints, and the safety precautions and exclusion zone required for pneumatic testing.
Describe gauge selection and calibration requirements, including range, graduation, number of gauges, and calibration currency, and identify what invalidates a test.
Assemble the document set required for release: material certificates, WPS and PQR, welder qualifications, NDE reports, heat treatment charts, test records, dimensional reports, nameplate data, and the manufacturer's data report.
Your checkpoint
A complete pressure test plan for one vessel covering medium, calculated test pressure, gauge specification, hold time, boundary limits, and safety controls, plus a one-page data book index listing every required document.
Codes, Standards, Documentation, and Release of Equipment
Build a hierarchy map of codes, standards, project specifications, and purchase order requirements, and state the governing document when they conflict.
Identify the certification and marking requirements for release of fixed equipment, including nameplate content, authorized inspection agency involvement, and what the inspector signs versus what the manufacturer certifies.
Process a nonconformance end to end: write the description, disposition options (rework, repair, use-as-is, reject), approval authority, and the re-inspection and documentation trail each disposition requires.
Trace a heat number from mill certificate through cut sheets, weld maps, and NDE reports to the installed item, and flag where traceability commonly breaks.
Your checkpoint
A nonconformance report and traceability audit narrative for a single simulated heat number, including all disposition approvals and the final closeout entry showing the item is releasable.
Source Inspection Fundamentals, Roles, and Quality Surveillance Planning & Materials, Welding, and Fabrication Processes & Non-Destructive Examination and Pressure Testing & Fixed Equipment: Pressure Vessels, Heat Exchangers, Piping, Valves, and Fittings & Codes, Standards, Documentation, and Release of Equipment
Complete two timed full-length practice exams covering all five domains, and score each domain separately to expose weak areas.
Re-teach the two lowest-scoring domains using code text and your own notes, and rewrite the affected study artifacts rather than re-reading them.
Rehearse the inspector's decision path for a disputed hold point: verify against specification, document the objection, escalate, and record the resolution.
Build a one-page reference sheet of key numbers, test pressures, acceptance limits, and document names you must recall without reference.
Your checkpoint
Two scored practice exams with a domain-by-domain score log, a one-page weak-area remediation sheet, and a final reference card that is accurate against the source code.
Milestones
Week 2: Role matrix and 15-line ITP are complete and pass the self-scoring checklist; all hold points are justified in writing.
Week 4: Defect-to-method matrix covers 10 or more defect types and the timed 40-question quiz scores 80 percent or higher.
Week 6: Pressure test plan and data book index are complete, and calculated test pressures match code formulas with the gauge correction shown.
Week 8: Both timed practice exams are scored with per-domain breakdowns, and the two weakest domains show measurable improvement on the second attempt.