Sustaining a Gain After the Green Belt Leaves
A Green Belt has reduced a call centre's average handling time from 6:10 to 5:20 and first-call resolution improved from 71% to 79% over a 10-week pilot. The improvement came from a redesigned knowledge-base search and a daily 10-minute huddle. The pilot team of 12 agents was volunteer-selected. The Green Belt's project ends in 3 weeks. The operations manager wants to 'roll it out to all 90 agents next month'. Two weeks after the pilot ended, AHT on the pilot team drifted to 5:45 and FCR to 76%. The knowledge-base owner says the search index 'needs manual refreshing' and no one has been assigned to do it.
1. Diagnose the drift and assess whether immediate full roll-out is wise.
Read the worked answer
Diagnosis - the drift has a plausible, identifiable mechanism: the knowledge-base index needs manual refreshing and no owner exists. That is an unassigned control, not a motivation problem. AHT rising 25 seconds and FCR falling 3 points within two weeks is consistent with a degrading search index, though it could also be regression toward the mean or loss of huddle discipline - both need checking.
Roll-out risk:
- Volunteer bias. The 12 agents self-selected; they may be more receptive or more experienced. The 79% FCR may not transfer to 90 agents.
- Unstable control. Rolling out a process whose support mechanism (index refresh) is unowned will replicate the decay at 7.5× the scale.
- Huddle dilution. A 10-min huddle works at 12; at 90 it needs a structure (team-level huddles, escalation) that has not been designed.
Recommendation: do not roll out next month. First stabilise: assign an index-refresh owner with a defined frequency and a check, reinstate the huddle on the pilot team, and confirm AHT returns to ~5:20. Then roll out in waves (e.g. 20 agents), each with the same control in place, measuring against the pilot result.
2. What control plan elements must be in place before the project closes?
Read the worked answer
A control plan that survives the Green Belt's departure needs, at minimum:
- Ownership - a named person for each control (index refresh, huddle facilitation, data reporting), with a named deputy. 'The team' is not an owner.
- Metric definitions and frequency - AHT and FCR defined exactly as in the pilot, reported weekly, with the chart (not just the number) reviewed.
- Reaction plan - what happens if AHT exceeds a trigger (e.g. 5:35 for two consecutive weeks): who investigates, what they check first (index freshness, huddle attendance), and by when.
- Documentation - the redesigned search procedure and huddle agenda written down so it does not depend on individuals.
- Audit - a periodic check (monthly) that the controls are actually being performed, not just documented.
- Handover evidence - a run of stable data (e.g. 6–8 weeks) at the improved level with the controls in place, not just the pilot result.
Without items 1 and 3 the project is not controlled - it is merely finished. The drift already observed is direct evidence that the control gap is real, and should be cited when requesting the handover sign-off.
3. The operations manager says the drift is 'just people relaxing after the project'. How do you respond?
Read the worked answer
Treat it as a hypothesis to test, not a claim to accept or dismiss.
- If it were motivational drift, you would expect a gradual, uniform decline across agents and metrics. The observed pattern - both metrics moving together within two weeks, coinciding with an unowned index refresh - fits a mechanism explanation at least as well.
- Test it cheaply: check index freshness dates against the AHT timeline; if AHT rose after the index went stale, the mechanism is supported. Compare individual agent trajectories - motivational drift tends to be diffuse; a mechanism tends to hit agents who rely most on search.
- Either way, the response is the same: assign the owner and the reaction plan. If it is motivational, an unowned control will not fix it either, and the huddle needs a named facilitator.
Avoid arguing about intent. Reframe: 'Whatever the cause, we have an unassigned control and a metric moving in the wrong direction. Let's fix the control and see if the metric responds - that also tells us which explanation is right.' This keeps the conversation on evidence and gets the handover signed off with a real control plan.