AR Fire Sprinkler study materials
AR Fire Sprinkler study resources

AR Fire Sprinkler cheat sheet

AR Fire Sprinkler · Keep the key ideas within reach.

Quick reference

Fire Sprinkler System Design and Installation Standards

  • NFPA 13 governs design and installation of commercial sprinkler systems; NFPA 13R covers residential occupancies up to four stories, and NFPA 13D covers one- and two-family dwellings.

  • Light hazard design density is typically 0.10 gpm/ft² over 1,500 ft²; Ordinary Hazard Group 1 is 0.15 gpm/ft² over 1,500 ft², and Ordinary Hazard Group 2 is 0.20 gpm/ft² over 1,500 ft².

  • Design area may be reduced for dry systems (by 30%), for sloped ceilings, and for use of quick-response sprinklers in wet systems, but the reduction is capped and never below 1,500 ft².

  • Maximum sprinkler spacing for light hazard is 15 ft between sprinklers and 225 ft² per sprinkler; ordinary hazard allows up to 130 ft² per sprinkler at 15 ft spacing.

  • Sprinklers must be positioned so deflection does not exceed 12 in. below the ceiling for standard spray sprinklers, with higher limits permitted for specific ceiling types.

  • A 1 in. main drain and a flow test are required at the remote point; system demand must not exceed available water supply at the point of connection.

  • Hydraulic calculations must use the Hazen-Williams formula with C=120 for steel pipe (wet systems) and C=100 for dry systems, unless other listed values apply.

  • Sprinkler systems must be hydrostatically tested at 200 psi for 2 hours (or 50 psi above working pressure if it exceeds 150 psi).

Quick reference

Arkansas Fire Protection Licensing Statutes and Rules

  • The Arkansas Fire Protection Licensing Board regulates sprinkler system contractors and installers under Arkansas Code Title 20, Chapter 22.

  • A firm must hold a valid fire sprinkler contractor license and employ at least one licensed responsible managing employee to legally contract for sprinkler work.

  • Individual installers must be licensed; apprentice or helper registration is required for those working under a licensed installer.

  • Licenses must be renewed on the Board's renewal cycle, and continuing education or fees may be required to maintain active status.

  • Contractors must provide proof of insurance, including general liability, as a condition of licensure and renewal.

  • Unlicensed practice or contracting without a license is subject to civil penalties and possible criminal sanctions under state statute.

  • Plans and specifications for sprinkler installations are typically required to be submitted to the local authority having jurisdiction, which may also require Board-licensed contractor identification.

  • Licensee records, including contracts and installation documentation, must be maintained and made available to the Board upon request.

Quick reference

NFPA 13 System Components, Hydraulics, and Water Supply

  • Wet-pipe systems are the standard for heated occupancies; dry-pipe systems are used where freezing is possible and require a dry pipe valve and air pressure.

  • A dry pipe valve must have a quick-opening device or be sized so that water delivery occurs within 60 seconds of the farthest sprinkler opening.

  • Check valves, OS&Y gate valves, and indicating control valves must be provided at the riser and at connections to water supplies.

  • Sprinkler temperature ratings must be at least 20°F above the maximum expected ambient ceiling temperature.

  • Water supply sources include public mains, gravity tanks, suction tanks, and fire pumps; each must be capable of supplying the calculated demand plus hose stream allowance.

  • A fire pump must be sized so the pump curve provides at least the required system demand at the design point, and a bypass is required around the pump.

  • Hazen-Williams head loss: p (psi) = 4.52 × Q^1.85 / (C^1.85 × d^4.87) per foot of pipe, with Q in gpm and d in inches.

  • A backflow preventer is required where the sprinkler system connects to a potable water supply, and its friction loss must be included in the hydraulic calculation.

Quick reference

Inspection, Testing, and Maintenance of Sprinkler Systems

  • NFPA 25 establishes the minimum inspection, testing, and maintenance requirements for water-based fire protection systems after installation.

  • Gauges on wet systems must be inspected monthly; main drain flow tests are performed quarterly, and waterflow alarm tests are performed quarterly.

  • Dry pipe valves and preaction valves require annual trip testing; dry pipe systems must have their air pressure and priming water checked monthly.

  • Sprinkler heads must be inspected annually for corrosion, paint, and damage; heads that have operated or are more than 50 years old in certain conditions must be replaced or tested.

  • Internal pipe inspection is required every 5 years for dry systems and every 5 years for wet systems where conditions warrant.

  • The main drain test compares static and residual pressure to detect supply degradation; a significant drop from baseline indicates a supply or valve problem.

  • Records of all inspections, tests, and maintenance must be retained and made available to the AHJ; NFPA 25 requires a written record for each activity.

  • Impairment procedures require notification of the AHJ and building owner, a fire watch if the system is out of service, and documentation of the impairment.

Quick reference

Business, Contracting, and Safety Practices

  • A written contract should define scope, applicable codes, schedule, payment terms, and responsibility for permits and inspections.

  • Change orders must be documented in writing before additional work proceeds to preserve the contractor's right to payment.

  • Jobsite safety includes controlling hot work with a permit, maintaining fire watch, and following OSHA fall protection and lockout/tagout requirements.

  • Lien rights in Arkansas generally require timely notice and filing; contractors should track statutory deadlines for mechanics' liens.

  • Insurance coverage should include general liability, workers' compensation, and completed operations coverage for sprinkler installations.

  • Toolbox talks and documented safety training reduce liability and support compliance with OSHA and project-specific safety plans.

  • Bid estimates should account for material takeoff, labor hours, equipment, permits, overhead, and profit margin, with a contingency for site conditions.

  • Retain project records, as-built drawings, and test reports for the period required by contract and statute to defend against claims.