32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Business analysis
- The practice of enabling change in an enterprise by defining needs and recommending solutions that deliver value to stakeholders, spanning strategy, requirements and solution evaluation.
- Requirement levels
- Four levels: business requirements state enterprise goals; stakeholder requirements state the needs of a group; solution requirements cover functional and non-functional detail; transition requirements cover temporary capabilities needed to reach the future state.
- Project versus program
- A project is a temporary effort producing a unique product, service or result; a program is a group of related projects managed together to obtain benefits not available from managing them separately.
- Analyst versus project manager
- The business analyst focuses on defining needs, requirements and value; the project manager focuses on delivering agreed scope within schedule, budget and resource constraints while managing the plan and team.
- Scope creep
- The uncontrolled expansion of scope through small, unapproved additions to requirements, which erodes schedule and budget because no impact analysis or change decision ever takes place.
- Assumption versus constraint
- An assumption is a factor believed true but not yet confirmed, and must be validated; a constraint is a non-negotiable limitation such as a fixed budget, deadline, regulation or technology platform.
- Baseline
- An approved, version-controlled reference point for scope, schedule or cost against which actual performance is compared and against which changes must be formally authorised.
- Agile four values
- The Agile Manifesto values individuals and interactions, working software, customer collaboration and responding to change, while still recognising value in the items listed on the right-hand side.
- DMAIC
- The Six Sigma improvement cycle: Define the problem and goal, Measure current performance, Analyse root causes, Improve the process, and Control the gains so results are sustained.
- Kanban WIP limits
- A Kanban control that caps the number of items in progress at each workflow stage, exposing bottlenecks, reducing multitasking and allowing new work to start only when capacity frees up.
- Predictive versus adaptive choice
- Choose a predictive lifecycle when scope is stable and verification dominates; choose an adaptive lifecycle when uncertainty is high, feedback is cheap and change during delivery is expected.
- PERT estimate
- A three-point weighted estimate where expected duration equals (optimistic plus four times most likely plus pessimistic) divided by six, with approximate standard deviation (pessimistic minus optimistic) divided by six.
- Critical path
- The longest total duration path through the schedule network; activities on it have zero total float, so any delay on the path delays project completion.
- MoSCoW prioritisation
- A scheme grouping requirements as Must have, Should have, Could have and Won't have this time; the Must set is the minimum usable subset, usually no more than 60 percent of timebox effort.
- Gap analysis
- A comparison of the current state with the desired future state that identifies missing capabilities, processes or data and converts each gap into an action or requirement.
- RACI accountability rule
- In a RACI chart each activity has exactly one person Accountable, who owns the outcome and approves the work; any number of people may be Responsible, Consulted or Informed.
- Cost performance index
- CPI equals earned value divided by actual cost; below 1.0 means work is costing more than planned, above 1.0 means cost efficiency is better than planned.
- Change control board
- A group holding authority to review change requests, assess impact on scope, schedule, cost, risk and quality, and approve, reject, defer or modify them.
- Tuckman team stages
- The five stages of team development: Forming for orientation, Storming for conflict, Norming for agreement on working norms, Performing for productive delivery, and Adjourning for disbandment.
- Risk score
- A risk score multiplies probability by impact to rank exposures; scores above the organisation's threshold require a named owner, a documented response and escalation.
- Threat response strategies
- Four standard responses to negative risk: avoid by removing the cause, transfer by shifting financial consequence, mitigate by reducing probability or impact, and accept by retaining the exposure.
- Risk versus issue
- A risk is an uncertain event that may affect objectives in the future; an issue is a problem that has already occurred and requires resolution now.
- Conflict of interest
- A situation where a personal, financial or other interest could improperly influence professional judgement; it must be disclosed and managed, or the affected work reassigned.
- User story format
- A requirement written as: as a role, I want a capability, so that a benefit; stories are refined until they meet INVEST criteria and have agreed acceptance criteria.
- Traceability matrix
- A table linking each requirement to its source, design element, test case and acceptance decision, supporting coverage checks and impact analysis when change is requested.
- Data quality dimensions
- Common dimensions used to assess data: accuracy, completeness, consistency, timeliness, validity and uniqueness, each measured against a defined threshold with a named owner.
- Communication channels formula
- For n participants the number of communication channels is n times (n minus 1) divided by 2; adding one person adds n channels, so coordination complexity grows faster than team size.
- Power-interest grid
- A stakeholder classification plotting influence against interest; high power and high interest are managed closely, high power and low interest kept satisfied, low power and high interest kept informed.
- Thomas-Kilmann conflict modes
- Five conflict-handling approaches defined by assertiveness and cooperativeness: competing, collaborating, compromising, avoiding and accommodating; collaborating suits important issues needing long-term buy-in.
- PDCA cycle
- Plan sets objectives and targets, Do executes the plan, Check compares results with targets, and Act standardises what worked or corrects what did not; it underpins continuous improvement.
- SMART objectives
- Objectives stated as Specific, Measurable, Achievable, Relevant and Time-bound, so that progress can be monitored and completion judged without ambiguity.
- Lessons learned register
- A living record of knowledge gained from successes and problems, including context and recommended action, captured continuously so it can be reused before project closure.