CAOP · Build recall with a focused review session.

33 cards. Read the term and the definition here. The deck at the top of this page is optional.

Project lifecycle stages
The sequence of initiate, plan, execute, monitor and control, and close. Each stage acts as a gate that must be approved before the next stage begins.
Project status transitions
Draft, active, on hold, and closed states control which transactions may be entered. An on-hold project blocks new time and expense submissions until reactivated.
Contract-to-project linkage
One contract can generate many projects, but each project posts revenue to exactly one contract. This cardinality drives how revenue rolls up in reporting.
Project closing prerequisites
A project cannot close while unbilled time, unposted expenses, or open revenue accruals remain against it. All must be resolved or written off first.
Quote revision control
A quote revision supersedes the prior version while preserving history. Only the currently active revision can be converted into a contract.
Discount approval threshold
A rule triggered by discount percentage or total margin. When a quote exceeds the threshold, it routes for approval before it can be marked won.
Effective-dated price lists
A quote locks the price list version valid on the quote date, not the price in effect at contract signature. This preserves quoted pricing through negotiation.
Opportunity close reasons
Win or loss reasons are mandatory when an opportunity closes and feed pipeline analytics. Lost opportunities cannot generate contracts or projects.
Critical path
The longest duration path through dependent tasks. Any delay on a critical path task pushes out the project end date directly.
Hard versus soft booking
A hard booking reserves capacity and blocks conflicting assignments. A soft booking is a proposal that does not consume capacity or prevent other bookings.
Effort-driven task behavior
On effort-driven tasks, total work is fixed, so adding resources shortens duration. On fixed-duration tasks, adding resources reduces per-resource hours instead.
Resource assignment units
The allocation percentage a resource is assigned to a task. At 100% for five days on an eight-hour calendar, the resource consumes 40 hours.
Timesheet approval states
Draft, submitted, approved, rejected, and posted. Only approved and posted time flows into project cost and customer billing calculations.
Billable versus chargeable time
Billable time reaches the customer invoice. Chargeable time is capitalized to project cost but never invoiced, such as internal rework on a fixed fee.
Unbilled revenue accrual
Posted when approved billable transactions exist but no invoice has been generated for the period. It records revenue earned but not yet billed.
Write-up and write-down
An adjustment between the billed amount and the standard bill rate. Both directions are recorded on the invoice line to preserve an audit trail.
Cost-to-cost percent complete
Costs incurred to date divided by total estimated costs at completion. Multiplying that ratio by total contract value gives recognized revenue.
Cumulative catch-up adjustment
When estimated cost at completion changes, recognized revenue is recalculated on the new estimate. The difference posts in the current period, not retroactively.
Work in progress calculation
Costs incurred plus recognized profit minus amounts billed. A positive balance is an asset; a negative balance represents a liability to the customer.
Loss contract provision
Recorded immediately when estimated cost at completion exceeds contract value. The full expected loss is recognized regardless of percent complete.
Deferred revenue
A liability arising when billing exceeds revenue recognized. It represents cash collected or invoiced for work not yet performed or earned.
Utilization formula
Billable hours divided by available hours. Available hours exclude holidays, approved leave, and non-working calendar days, so they reflect true capacity.
Over-allocation detection
Occurs when summed assignment units exceed 100% across overlapping date ranges. Leveling resolves it by shifting dates or splitting assignments across resources.
Bench reporting
Identifies resources whose utilization falls below a threshold over a rolling window, typically four to twelve weeks, signaling available capacity.
Net available capacity
Full-time equivalents times working days times hours per day, minus planned non-project time such as training and administration. This yields realistic project capacity.
Report data grain
Transaction-level reports reconcile to the general ledger. Summary reports aggregate records and may differ slightly from ledger totals due to rounding.
Row-level security
Restricts report data by business unit, project, or resource. Report access inherits the user's assigned security role rather than being granted separately.
Audit trail immutability
Posted transactions cannot be edited directly. Corrections are made through reversing entries, and every rate or amount change records who changed it and when.
Project margin metric
Revenue minus cost, divided by revenue, expressed as a percentage. It is the core profitability measure used in project financial reporting.
Master data sync order
Customers and resources must exist before projects, and projects before transactions. Violating this order causes integration failures and orphaned records.
Idempotency keys
Unique identifiers attached to integration requests. They prevent duplicate transaction posting when a system retries after a timeout or network failure.
Suspense table error handling
Failed integration records route to a staging or suspense table with error codes. Reprocessing occurs manually after the underlying data is corrected.
Integration monitoring metrics
Record counts, latency, and failure rates are tracked per interface. Alerts fire when volume or error rate deviates from the expected baseline.