Cert III Plumbing: Plans, Specifications, Drawings and Setting Out

Cert III Plumbing · Work through your exam, one topic at a time.

All guide sections

Plans, Specifications, Drawings and Setting Out

Reading drawings

Plumbing drawings come in sets: site plan, floor plans, elevations, sections, detail drawings, and services coordination drawings. Know the title block (project, drawing number, revision, scale, date) and the revision cloud convention. Line types matter - solid for visible, dashed for hidden or existing, chain-dotted for centre lines and boundaries. Symbols identify fixtures, valves, floor wastes, and inspection openings; abbreviations and legends must be read before interpreting the plan.

Scales and dimensions

Be able to convert a scaled measurement to real size: a 1:50 drawing means 1 mm on paper equals 50 mm real. Dimensions on drawings override scaled measurements - never scale off a drawing when a written dimension exists. Check for missing or conflicting dimensions and request clarification rather than guessing.

Specifications and setting out

Specifications state materials, standards, testing, and workmanship that drawings cannot show. Setting out means transferring design to site: establishing levels with a dumpy level or laser, marking centrelines, checking fall, and confirming clearances and cover. Confirm before cutting or coring, and check for concealed services.

Worked example and traps

On a 1:100 plan, a drain run measures 85 mm on paper. Real length = 85 × 100 = 8500 mm = 8.5 m. At 1:60 fall, drop = 8.5 ÷ 60 ≈ 0.142 m, or about 142 mm. Traps: applying the scale factor backwards (dividing instead of multiplying), mixing drawing scales within one sheet, ignoring revision clouds, and treating an unlabelled dimension as confirmed. Always build from the latest revision and record any site instruction.