Cert III Scaffolding study materials
Cert III Scaffolding study resources

Cert III Scaffolding flashcards

Cert III Scaffolding · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

PCBU
Person Conducting a Business or Undertaking. Holds the primary duty under WHS law to ensure health and safety so far as reasonably practicable.
Reasonably practicable
Test weighing the likelihood and severity of harm against the cost and effort of control measures, plus what the duty holder knows or should know.
Hierarchy of control
Ranked order of risk controls from most to least effective: elimination, substitution, engineering or isolation, administrative controls, then personal protective equipment.
SWMS
Safe Work Method Statement. A written document listing high-risk construction tasks, the hazards, and the controls, reviewed and signed before work starts.
Duty loading
The rated load a scaffold class is designed to carry per bay: light 225 kg, medium 450 kg, heavy 675 kg, special above 675 kg.
Working platform width
Minimum clear width of a scaffold platform: 450 mm for general duty work, reduced to 225 mm where used only for access.
Toe board
A vertical board at least 150 mm high fixed along the platform edge to stop tools and materials falling to the level below.
Top guardrail height
The upper rail must sit between 900 mm and 1100 mm above the platform surface, with a mid-rail between 450 mm and 600 mm.
Plank overlap
Scaffold planks must overlap their support by at least 300 mm and be fixed against movement or uplift by wind.
Maximum lift height
A working platform must not be erected more than 2.0 m above the supporting level or the last tied and braced level.
Scaffold inspection interval
Inspect before first use, after alteration or any stability-affecting event, and at intervals not exceeding 30 days; record the result.
Tagging system
A colour-coded tag on the access point showing the scaffold is complete, incomplete, or out of service, with the inspection date and inspector.
Exclusion zone
A barricaded ground area beneath scaffold erection or dismantling that keeps people clear of falling objects and dropped components.
Base plate and sole board
Base plates distribute load from the standard onto a sole board, which spreads it over the ground to prevent settlement or punching.
Foundation capacity
Ground must support the fully loaded scaffold without settlement; soft ground requires sole boards, timber packing, or a designed foundation.
Tie and bracing
Ties anchor the scaffold to the structure and bracing resists racking; neither may be removed until the level above is dismantled.
Mobile tower ratio
Tower height to base dimension must not exceed 3:1 indoors or 2:1 outdoors unless outriggers, stabilisers, or ties are fitted.
Sling angle derating
As the included angle between sling legs widens, capacity drops; at 60 degrees each leg carries about 87 percent of its vertical rating.
Right-angle coupler
A load-bearing fitting joining two tubes at 90 degrees, used where the joint transmits force into the scaffold structure.
Swivel coupler
A fitting that joins tubes at any angle; used for bracing and not as a primary load-bearing structural joint.
Cantilever scaffold
A scaffold supported from the structure by spurs or beams rather than the ground; it requires design certification and a tie-back.
Spur
A load-bearing member that projects from the structure to support a cantilever scaffold; its inner end must bear on a solid member.
EWP anchor point
The designated fixing inside an elevating work platform basket to which the operator's lanyard attaches, not the structure outside.
Suspended scaffold
A platform hung from overhead supports by wire ropes and hoists; total load must stay within the hoist rated capacity.
Dismantling sequence
Reverse of erection: remove the top level first, keep ties until the level above is gone, and lower components, never drop them.
Gin wheel
A single-sheave pulley used to lift light scaffold components; it must be rated, inspected, and anchored to a sound point.
Dead load
The permanent weight of the scaffold itself, including tubes, planks, couplers, and toe boards, before any imposed load.
Live load
The imposed load on a platform from workers, tools, and materials; it must not exceed the class duty loading.
Wind loading
Force on the scaffold from wind, increased by netting or sheeting; it governs tie spacing and may require the scaffold to be tied more densely.
Scaffold certificate
A competency card or licence showing the holder is trained and assessed for the scaffold class and height they erect.
Height licensing
Scaffold work is split by height, typically basic up to 4 m, intermediate to 8 m, and advanced above 8 m, each needing its own unit.
Fall arrest
A harness and lanyard system that stops a fall; used where guardrails cannot be fitted, with anchor rated for the arrest force.