CPC31320 Wall & Floor Tiling study plan
CPC31320 Wall & Floor Tiling · Give each week a clear focus.
8 weeks · About 7 hours per week
Core units of competency (construction industry common skills and wall and floor tiling)
Map the CPC31320 core unit structure and list every core unit with its performance criteria and required knowledge
Explain WHS obligations for tiling work including hazard identification, risk control hierarchy and site induction requirements
Identify the personal protective equipment and safe work practices required for cutting, mixing and fixing tasks
Interpret a simple set of tiling drawings and specifications to extract dimensions, finishes and substrate requirements
Your checkpoint
A one-page unit map plus a completed WHS risk-control worksheet for a simulated bathroom tiling job, cross-referenced to core unit performance criteria
Core units of competency (construction industry common skills and wall and floor tiling)
Describe substrate types (concrete, screed, fibre-cement, plasterboard, render) and their preparation and priming requirements
Select appropriate adhesives, grouts and sealants for given tile types and service conditions
Calculate tile quantities, adhesive and grout coverage from plan dimensions allowing for wastage and cuts
Set out a floor to achieve balanced cuts and correct falls to wastes and drains
Your checkpoint
A material take-off and setting-out sketch for a 12 m² bathroom including tile count, adhesive and grout quantities with wastage allowance
Core units of competency (construction industry common skills and wall and floor tiling)
Demonstrate safe and accurate measuring, marking and cutting of ceramic and porcelain tiles using manual and wet saws
Prepare and apply adhesive to correct notched-trowel size, coverage and open-time standards
Install floor tiles to a flat, level plane with consistent joint widths and correct falls
Grout and finish a tiled floor, cleaning joints and applying sealant at movement and perimeter joints
Your checkpoint
A completed and photographed practice floor panel (at least 2 m²) with self-assessment against flatness, joint width and fall tolerances
Core units of competency (construction industry common skills and wall and floor tiling)
Set out and install wall tiles to a vertical plane using spacers, levels and battens to control line and plumb
Form internal and external corners, window reveals and around fittings with accurate cuts
Apply waterproofing membrane to a shower area to manufacturer and standard requirements including bond breakers and upturns
Explain the purpose and location of movement joints in wall and floor tiling
Your checkpoint
A waterproofed and tiled shower recess model or practice bay showing correct membrane coverage, corner detail and movement joints
Core units of competency (construction industry common skills and wall and floor tiling)
Read and apply relevant Australian Standards and the National Construction Code provisions that govern wet-area tiling and waterproofing
Identify defects such as lippage, drummy tiles, efflorescence and failed grout, and state their likely causes and remedies
Plan a tiling sequence for a full bathroom including demolition, substrate repair, waterproofing, tiling and curing times
Produce a simple cost estimate covering labour, materials and waste for a quoted job
Your checkpoint
A written bathroom project plan with sequenced task list, curing and waterproofing timeframes, defect-prevention checklist and itemised cost estimate
Core units of competency (construction industry common skills and wall and floor tiling) & Elective units of competency
Interpret and apply the plans and specifications for a selected elective unit context such as mosaic, terrazzo or large-format tile work
Demonstrate the specific installation technique required by the chosen elective unit
Solve two realistic on-site problems (out-of-square walls, uneven substrate) and document the chosen corrective action
Complete a short written quiz on core-unit knowledge without reference material
Your checkpoint
A worked elective-unit task portfolio containing the installation evidence, two documented problem-solving records and a scored knowledge quiz
Core units of competency (construction industry common skills and wall and floor tiling) & Elective units of competency
Assemble a portfolio of evidence mapped to every core and elective unit performance criteria
Identify gaps in the evidence collected and plan how to close each gap before assessment
Rehearse practical assessment tasks under time limits for cutting, fixing, grouting and finishing
Explain quality control and housekeeping expectations at handover of a completed tiling job
Your checkpoint
A gap-analysis table showing each unit and performance criterion against the evidence held, with an action for every gap
Core units of competency (construction industry common skills and wall and floor tiling) & Elective units of competency
Close all remaining evidence gaps identified in the week-7 analysis
Complete a full timed mock practical assessment covering floor and wall tiling with waterproofing
Complete a full mock theory assessment covering all core and elective units
Review every incorrect answer and record the correct principle behind it
Your checkpoint
A completed mock assessment pack (practical checklist plus theory paper) with a written correction log and a final evidence portfolio ready for sign-off
Milestones
Week 2: Can independently produce an accurate material take-off and setting-out plan for a simple wet area without reference to notes
Week 4: Practice floor and wall panels meet flatness, plumb, joint width and fall tolerances on self-inspection, with waterproofing applied to manufacturer requirements
Week 6: Elective-unit task portfolio complete and core-unit knowledge quiz passed at 80 percent or better
Week 8: All performance criteria covered by portfolio evidence and mock practical and theory assessments completed with correction log closed out