Electrical Theory, Circuits, and Calculations

  • Ohm's law: E = I × R; power P = E × I = I²R = E²/R. In AC circuits substitute impedance Z for R and use RMS values.

  • Series circuit: current is identical everywhere; resistances add (R_T = R₁+R₂+…); voltage divides in proportion to resistance.

  • Parallel circuit: voltage is identical across branches; conductances add (1/R_T = 1/R₁+1/R₂+…); branch currents divide inversely with resistance.

  • Single-phase power: P = E × I × PF for unity and non-unity loads; apparent power S in VA = E × I; reactive power Q in VAR = E × I × sin θ.

  • Balanced three-phase: P = √3 × E_line × I_line × PF; line voltage = √3 × phase voltage in wye; line current = √3 × phase current in delta.

  • Conductor resistance R = ρL/A, where ρ is resistivity (circular-mil-ohm per foot for copper ≈ 12.9 at 75 °C); resistance rises with temperature.

  • Voltage drop single-phase: VD = 2 × K × I × L / CM (K ≈ 12.9 for copper, 21.2 for aluminum); three-phase uses 1.732 × K × I × L / CM.

  • Transformer turns ratio: E_primary/E_secondary = N_primary/N_secondary; power is essentially constant, so current ratio is inverse of voltage ratio.

  • Impedance Z = √(R² + X²); inductive reactance X_L = 2πfL; capacitive reactance X_C = 1/(2πfC); resonance occurs when X_L = X_C.

Quick reference

Wiring Methods, Materials, and Installation Standards

  • Conductor ampacity depends on insulation temperature rating, ambient temperature correction, and adjustment for more than three current-carrying conductors in a raceway.

  • NM-B cable is permitted in dry interior locations but not in wet locations, exposed to weather, embedded in masonry, or in hazardous locations.

  • Rigid metal conduit, IMC, and EMT differ in wall thickness and permitted uses; EMT is not permitted where severe physical damage is likely unless protected.

  • Box fill is calculated by counting each conductor, each device yoke, each clamp, and each equipment grounding conductor by assigned volume, then comparing with the box's marked cubic-inch capacity.

  • Support intervals are method-specific: EMT within 3 ft of boxes and at intervals not exceeding 10 ft; rigid metal conduit at intervals not exceeding 10 ft.

  • Bending radius and number of bends between boxes are limited to protect conductor insulation; no more than 360° of bends is permitted between pull points.

  • Cable and raceway entries into boxes require approved connectors, and unused openings must be closed with listed plugs or covers.

  • Conductor identification is color- and marking-based: grounded conductor white or gray, equipment grounding conductor green or bare, ungrounded conductors other colors.

  • Wet-location and underground installations require conductors and raceways listed for wet locations; direct-burial cable must be listed and buried at the required depth.

Quick reference

Grounding, Bonding, and Overcurrent Protection

  • The equipment grounding conductor provides a low-impedance fault path so overcurrent devices open quickly; it is not a current-carrying circuit conductor under normal operation.

  • The grounded (neutral) conductor is bonded to the enclosure and grounding electrode system at the service only; downstream panels keep neutral and ground separated.

  • Overcurrent device ratings must not exceed conductor ampacity after correction and adjustment, and the next standard size rule allows limited rounding up for certain loads.

  • Fuses and circuit breakers protect against overload and short circuit; ground-fault circuit interrupters protect people from line-to-ground leakage, and arc-fault devices detect arcing.

  • Grounding electrode systems may include metal water pipe, concrete-encased electrode, ground ring, and rod electrodes; the electrode conductor sizing follows the code table.

  • Bonding jumpers are required around water meters, gas piping, and other components that could interrupt the grounding path.

  • Selective coordination arranges overcurrent devices so the device nearest a fault opens first, preserving upstream service.

  • Series-rated systems require the downstream device to be listed for use with the specific upstream device; untested combinations are not permitted.

  • Available fault current at the service must be compared with the interrupting rating of every overcurrent device in the system.

Quick reference

Electrical Codes, Regulations, and Permit Procedures

  • A permit is generally required before installing or altering electrical wiring; ordinary minor repair and replacement work is often exempt but must still comply with code.

  • Plan review precedes permit issuance for larger projects; approved plans must be kept on site and work must match the approved drawings.

  • Inspections are typically staged: rough-in before concealment, and final after devices, fixtures, and labeling are complete.

  • The adopting jurisdiction's code edition governs; the model code applies only as amended and adopted locally.

  • Licensing rules define who may perform electrical work and who may supervise apprentices; unlicensed contracting is a violation.

  • Stop-work orders may be issued when work proceeds without a permit or in an unsafe manner; work must cease until the issue is resolved.

  • Certificate of occupancy or final approval is issued only after all required inspections pass and any corrections are verified.

  • Records of inspections, corrections, and re-inspections must be retained per the jurisdiction's retention schedule.

  • Utility connection approval typically requires an inspection release or cut-in card from the authority having jurisdiction.

Quick reference

Inspection Procedures, Plan Review, and Documentation

  • Plan review checks load calculations, service size, conductor and overcurrent ratings, grounding design, and compliance with adopted code editions.

  • A systematic inspection sequence covers service equipment, feeders, panelboards, branch circuits, boxes, devices, and fixtures in that order.

  • Test instruments include low-resistance ohmmeters for continuity, insulation resistance testers, clamp meters, and receptacle testers with GFCI/AFCI functions.

  • Documentation should record date, location, code references for deficiencies, corrective actions requested, and re-inspection results.

  • Photographs and marked-up drawings support findings and provide evidence if a decision is later disputed.

  • Deficiency notices should cite the specific code section and describe the observed condition, not merely state that work is noncompliant.

  • Final inspection verifies labeling of circuits and disconnects, directory accuracy, cover plates, and accessibility of equipment.

  • Inspection reports should distinguish code violations from recommendations to avoid implying authority beyond the code.

Quick reference

Safety, Hazard Identification, and Risk Assessment

  • Energized work requires a permit, a risk assessment, appropriate PPE, and qualified persons; de-energization is the default control.

  • Lockout/tagout isolates energy sources, verifies absence of voltage with a tested meter, and prevents unexpected re-energization.

  • Arc flash risk depends on available fault current, clearing time, and working distance; boundaries define required PPE levels.

  • Approach boundaries include limited, restricted, and prohibited distances; unqualified persons must stay outside the limited approach boundary.

  • PPE categories include arc-rated clothing, face shields, insulating gloves with leather protectors, and insulated tools rated for the voltage.

  • Hazard identification considers shock, arc flash, fire, fall, confined space, and environmental hazards such as wet locations.

  • Risk assessment ranks hazards by severity and likelihood, then applies controls in order: elimination, substitution, engineering, administrative, and PPE.

  • Test-before-touch is mandatory; meters and test leads must be rated for the voltage and category of the circuit being tested.

  • Incident investigation documents root cause and corrective action to prevent recurrence and support regulatory reporting.

Quick reference

Special Occupancies, Equipment, and Systems

  • Hazardous locations are classified by class, division or zone, and group; equipment must be listed for the specific classification.

  • Class I locations involve flammable gases or vapors; Class II involves combustible dust; Class III involves ignitable fibers.

  • Health care facilities require redundant grounding, isolated power in critical care areas, and special receptacle requirements.

  • Assembly occupancies impose stricter requirements for emergency lighting, exit signage, and wiring methods in egress paths.

  • Fire pumps require dedicated, reliable supply conductors routed to survive fire conditions and protected from overload.

  • Emergency and legally required standby systems must be separate from normal power and tested periodically.

  • Photovoltaic systems require rapid shutdown provisions, listed DC-rated equipment, and labeling of disconnects and conductors.

  • Electric vehicle supply equipment requires GFCI protection, listed connectors, and load management where the service capacity is limited.

  • Swimming pools, spas, and fountains require equipotential bonding, GFCI protection, and restrictions on overhead conductors.

Quick reference

Professional Ethics, Liability, and Inspector Conduct

  • Inspectors must act within their authority, applying only adopted code provisions and not personal preference.

  • Conflicts of interest, including financial interest in inspected work, must be disclosed and avoided.

  • Inspectors should not accept gifts or favors that could influence enforcement decisions.

  • Findings must be documented objectively and consistently; identical conditions should receive identical treatment.

  • Confidentiality applies to plans, proprietary designs, and business information obtained during inspection.

  • Negligent inspection can create liability for the jurisdiction and the inspector; accurate records are the primary defense.

  • Inspectors must maintain competence through continuing education and stay current with code editions and amendments.

  • Communication with contractors and owners should be professional, respectful, and focused on code compliance.

  • Inspectors must not perform design or installation work on projects they inspect, to preserve independence.