High Risk Work Licence - Materials Hoist (HM): Maintenance Responsibilities, Record Keeping and Equipment Documentation

High Risk Work Licence - Materials Hoist (HM) · Work through your exam, one topic at a time.

All guide sections

Maintenance Responsibilities, Record Keeping and Equipment Documentation

Maintenance keeps the hoist in the condition assumed by the risk assessment. The PCBU is responsible for arranging and resourcing maintenance; the operator is responsible for pre-start checks, reporting defects and not operating faulty plant. Maintenance must follow the manufacturer's schedule and be performed by competent persons, with isolations and lock-out/tag-out applied. Major inspections and periodic third-party inspections are separate from routine servicing and must be current before use.

Documentation a candidate should be able to name: the plant registration or design verification where required; the logbook; pre-operational inspection records; maintenance and repair records; periodic and major inspection reports; commissioning and alteration records; operator licence and training records; the risk assessment and safe work procedure; and records of incidents, near misses and corrective actions. Records must be legible, dated, attributable and retained for the period the regulator requires.

Traps: assuming a current service sticker proves the periodic inspection is current; accepting an undocumented repair; and treating the logbook as optional. A hoist without traceable inspection and maintenance history is not verifiably safe.

Rule of thumb: three questions before use - when was it last inspected, what was found, and who fixed it? If you cannot answer all three from the records, treat the hoist as unverified and stop.

Worked example: a repair is made to a rope termination on a Friday. The entry should record the date, the defect, the part replaced, the person and their competency, the test performed afterwards, and the return-to-service authorisation - then the next pre-start check confirms it.