A 200 MW wind farm is proposed on farmland. At a 35% capacity factor it would generate about 613 GWh per year. The regional grid currently produces 0.75 t CO2-e per MWh, so the farm could displace about 460,000 t CO2-e annually. Construction emits an estimated 90,000 t CO2-e, and the turbines have a 25-year life. Concerns raised include bird strike, noise, visual impact on a nearby town, and the land footprint. A councillor argues the farm is pointless because construction emissions and variability mean it cannot reliably replace baseload coal.

1. Calculate the lifetime avoided emissions and evaluate the councillor's claim.

Read the worked answer

Annual generation: 200 MW × 0.35 × 8,760 h ≈ 613,000 MWh (613 GWh).

Annual avoided emissions: 613,000 MWh × 0.75 t/MWh ≈ 460,000 t CO2-e.

Lifetime avoided: 460,000 × 25 ≈ 11.5 Mt CO2-e, minus 0.09 Mt construction ≈ 11.4 Mt net.

Payback time: 90,000 / 460,000 ≈ 0.2 years, i.e. under three months of operation.

Evaluating the claim:

  • The 'pointless' argument fails on emissions: construction is repaid in months, and net lifetime savings are large.
  • The variability point is valid but not fatal: wind output varies, so it needs backup, storage, or grid balancing. It reduces the firm capacity value, not the emissions benefit.
  • 'Cannot replace baseload coal' conflates energy and capacity. The farm supplies energy and reduces coal running hours; reliability is a system-design issue, addressed by diversified generation and storage.

2. Recommend what information the council should require before deciding, and explain how you would weigh the trade-offs.

Read the worked answer

Information required:

  • Site-specific bird and bat survey data (seasonal, at least one year) and collision-risk modelling.
  • Noise contour modelling at the nearest dwellings against standards.
  • Visual impact assessment, including viewshed analysis from the town.
  • Grid connection study and expected curtailment.
  • Land-use plan showing continued farming between turbines.
  • Updated emissions factor for the grid over the project life, since a cleaner grid reduces future avoided emissions.

Weighing trade-offs:

  • Quantify what can be quantified (emissions, noise levels, land use) and use structured assessment for what cannot (amenity, landscape).
  • Compare alternatives, including solar or offshore wind, on the same criteria.
  • Apply mitigation hierarchy: avoid, minimise, rehabilitate, offset.

Judgement: the emissions case is strong (≈11.4 Mt net), but approval should be conditional on acceptable bird-risk and noise outcomes and a credible grid plan; benefits do not automatically override local impacts.