VCE Accounting study materials
VCE Accounting study resources

Budget Variance in a Café

VCE Accounting · Put your knowledge to work in context.

All case studies

Budget Variance in a Café

A café prepared a monthly budget: sales of 2,000 coffees at $5.00 each, with milk cost budgeted at $0.50 per coffee, wages budgeted at $6,000 fixed, and rent $2,500. Actual results: 2,400 coffees sold at an average price of $4.80, milk cost $0.60 per coffee, wages $6,300 and rent $2,500. The owner is pleased because total sales revenue was higher than budget and concludes the business 'did well'. She wants to reward staff with a bonus and is planning to increase the milk price assumption in next month's budget to $0.60 without checking why costs rose.

1. Calculate the sales price and sales volume variances and assess whether the owner's conclusion is justified.

Read the worked answer

Budgeted revenue = 2,000 × $5.00 = $10,000. Actual revenue = 2,400 × $4.80 = $11,520. Total revenue variance is favourable $1,520. Split it: price variance = (actual price − budget price) × actual volume = ($4.80 − $5.00) × 2,400 = −$480, unfavourable. Volume variance = (actual volume − budget volume) × budget price = (2,400 − 2,000) × $5.00 = +$2,000, favourable. The net favourable $1,520 is driven entirely by volume; the price cut of $0.20 per cup reduced revenue by $480. So revenue rose, but the owner's conclusion that the business 'did well' is premature - she must also examine the cost variances before judging performance.

2. Evaluate the milk cost and wages outcomes, and critique the plan to simply raise the budgeted milk price.

Read the worked answer

Budgeted milk cost = 2,000 × $0.50 = $1,000; actual = 2,400 × $0.60 = $1,440, an unfavourable $440. Part of this is volume-driven: 400 extra coffees at the budget rate would cost $200, so the price/usage component is $240 unfavourable - a genuine efficiency or supplier issue. Wages were budgeted $6,000 and actual $6,300, $300 unfavourable, which may be justified by the 20% volume increase, but should be investigated. Simply raising the budget assumption to $0.60 hides the cause and builds a known inefficiency into the plan. The owner should find out whether the increase reflects a supplier price rise (adjust the budget and consider renegotiating) or waste and over-pouring (a control problem). Rewarding staff before this analysis risks rewarding the wrong behaviour.