AS 1796 Certificate 10 · Put your knowledge to work in context.

All case studies

Records That Cannot Support the Certificate

At the end of a pipe spool project the supervisor is asked to issue the certification package. The records show: WPS numbers on weld logs that do not match any WPS in the register; three welders whose identification stamps appear on joints but whose qualification certificates cannot be located; heat numbers recorded for the pipe but not traceable to mill certificates; and post-weld heat treatment charts for eleven spools with no spool identification on the charts. The project manager says the welds passed hydrotest, so the records are a paperwork issue and the certificate should be issued. The client will not release final payment without it.

1. Is 'the welds passed hydrotest, so the records are a paperwork issue' a sound argument? Explain what certification attests.

Read the worked answer

No. Certification attests that the work was produced under controlled conditions and meets the specified requirements, evidenced by records. It does not attest merely that a test was passed.

Hydrotest is a single, time-limited proof test at ambient or near-ambient conditions. It does not demonstrate that the correct material was used, that the welds were made by qualified welders to a qualified procedure, or that the required post-weld heat treatment was applied to the correct spools. Those are precisely the facts the records exist to establish. A spool that passed hydrotest but received no heat treatment, or the wrong heat treatment, may pass the test and fail in service.

The four record defects are not clerical: they break the chain between what was specified and what was done. The supervisor cannot certify a chain that does not connect. Issuing the certificate on the strength of the hydrotest would be an unsupported attestation, and the project manager's commercial pressure is not a reason to make one.

2. For each of the four record defects, state what can be reconstructed and what cannot, and the consequence for certification.

Read the worked answer

WPS mismatch on weld logs: if the register contains a WPS that demonstrably covers the joint, material, and thickness, the log entry can be corrected against production records and welder statements, and the correction recorded as a correction. If no WPS covers the joint, the welds were made without a qualified procedure and cannot be certified on reconstruction.

Missing welder certificates: qualification can sometimes be re-established from the issuing body's records or by re-test. If neither is possible, the joints cannot be attributed to qualified welders, and the affected welds require assessment, possibly re-test by examination.

Heat numbers not traceable to mill certificates: material identity can be recovered by product analysis or by the supplier's records if the heat number is genuine. If identity cannot be established, the material cannot be confirmed as specified and the spools cannot be certified as compliant.

PWHT charts without spool identification: if the furnace or treatment records can be matched to the spools by time, batch, and load plan, identification can be reconstructed. If not, there is no evidence that eleven specific spools received the required treatment, and they cannot be certified without re-treatment or other verification.

3. The project manager wants the certificate issued. Draft the substance of what the supervisor should tell him, and identify what would make the supervisor's position untenable.

Read the worked answer

Substance: the certificate will be issued when the records support it, and not before. Of the four defects, some are likely recoverable by reconstruction and some may not be. The supervisor will spend a defined period attempting reconstruction, will document what is recovered and how, and will report by a stated date which spools can be certified and which cannot. For spools that cannot be certified on records, the options are re-examination, re-treatment, or non-certification; the project manager should choose with the client, not with the supervisor's signature.

The supervisor's position becomes untenable if he signs the certificate while knowing the records do not support it. That is not a scheduling decision; it is a false attestation, and it exposes him personally as well as the organisation. Equally, he should avoid the opposite failure of refusing to attempt reconstruction at all: much of this is recoverable, and the professional course is to try, record the attempt, and certify only what the evidence supports.

He should also put the advice in writing, so the decision to proceed or not is visibly the project manager's, taken with the supervisor's advice in front of him.