AS 1796 Certificate 10 · Put your knowledge to work in context.

AS 1796 Certificate 10, listed by Weld Australia as "AS1796 Cert 10," is a welding supervision qualification offered within Weld Australia's training and certification pathways. Weld Australia describes itself as Australia's peak body for the welding industry and a not-for-profit, membership-based organisation that delivers training, certification, engineering expertise and industry advocacy. The AS 1796 Certificate 10 case studies are 5 cases and about 3,408 words.

1

Who Signs Off the Procedure When the Certifying Body Has Not Enumerated the Scope?

A fabricator holds a Certificate 10 scope. The written scope statement reads only 'welding supervision and certification under AS/NZS 1796' with no list of processes, positions, or thicknesses.

703 words, about 4 min
2

A Welder's Qualification Lapses Mid-Contract

A pressure-vessel shop has twelve welders on a six-month contract. Welder A qualified in month one on the production procedure and has welded continuously since, but his qualification certificate carries a expiry date that fell three weeks ago.

662 words, about 3 min
3

Repair Welding on a Joint Already Accepted

Radiography of a completed circumferential butt weld in a 25 mm carbon steel header found three indications: two rounded indications assessed as porosity and one planar indication assessed as lack of fusion on the root. The joint had already been accepted on visual and surface examination and signed off by the supervisor.

669 words, about 3 min
4

A Subcontractor's Welding Is Offered Under the Main Certificate

A certified fabricator has subcontracted 40 percent of a structural steel package to a small workshop with no certification of its own. The subcontractor will weld moment connections using the main contractor's WPS and, in the main contractor's view, 'under our certificate'.

653 words, about 3 min
5

Records That Cannot Support the Certificate

At the end of a pipe spool project the supervisor is asked to issue the certification package. The records show: WPS numbers on weld logs that do not match any WPS in the register; three welders whose identification stamps appear on joints but whose qualification certificates cannot be located; heat numbers recorded for the pipe but not traceable to mill certificates; and post-weld heat treatment charts for eleven spools with no spool identification on the charts.

721 words, about 4 min