AZ General Contractor study materials
AZ General Contractor study resources

AZ General Contractor flashcards

AZ General Contractor · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Arizona Registrar of Contractors
The state agency that licenses and regulates contractors in Arizona, investigates complaints, and can suspend, revoke, or fine a contractor license.
License threshold Arizona
Arizona generally requires a contractor license for construction work totaling $1,000 or more in labor and materials, including residential and commercial projects.
Qualifying party
An individual who meets experience and exam requirements and is designated to qualify a contractor license, ensuring the licensed entity has responsible technical knowledge.
A license classification
Arizona's general engineering license classification, covering fixed works such as roads, bridges, dams, and utilities; it is broader than general building.
B license classification
Arizona's general building contractor license, covering construction of structures and related improvements requiring multiple trades; specialty work may require a C license.
C license classification
Arizona specialty contractor license covering a specific trade, such as electrical, plumbing, roofing, or concrete, rather than whole-building construction.
Residential recovery fund
Arizona fund that may reimburse homeowners for certain losses caused by a licensed residential contractor's failure to perform or comply; statutory limits apply.
Statute of Frauds
Legal rule requiring certain contracts, including those not performable within one year and certain real property agreements, to be in writing and signed.
Mechanics lien
A statutory claim against real property securing payment for labor, materials, or services that improved the property; strict notice and recording deadlines apply.
Preliminary 20-day notice
Arizona notice that certain lien claimants must give the owner and lender within 20 days after first furnishing labor or materials to preserve full lien rights.
Prompt Payment Act
Arizona law setting deadlines for owners and contractors to pay construction invoices and limiting when payments may be withheld; check contract and statute.
Change order
A written modification to contract scope, price, or schedule signed by authorized parties; it prevents disputes over extra work and time extensions.
Substantial completion
The stage when the work is sufficiently complete for its intended use, triggering warranty, payment, lien, and statute-of-limitation periods under contract and law.
Concrete cubic yards
Calculate volume as length times width times depth in feet, then divide by 27 to convert cubic feet to cubic yards; add a waste factor.
Waste factor
A percentage added to estimated material quantities to account for cutting, breakage, and installation loss; order quantity equals net quantity times one plus waste rate.
Board feet formula
Board feet equals thickness in inches times width in inches times length in feet, divided by 12; used to estimate lumber quantity and cost.
Markup versus margin
Markup is profit divided by cost, while margin is profit divided by selling price; price equals cost divided by one minus margin percentage.
Critical path
The longest sequence of dependent activities through a project network; it has zero total float and determines the shortest possible project duration.
Total float formula
Total float equals late start minus early start, or late finish minus early finish, for an activity; zero float indicates a critical activity.
Rebar earth cover
Concrete cast against and permanently in contact with earth generally requires at least 3 inches of cover over reinforcement to protect steel from corrosion.
Vapor retarder under slab
A membrane placed beneath a concrete slab to reduce moisture migration; lap and seal joints and protect it during placing of concrete.
Water heater TPR discharge
The temperature-pressure relief valve discharge pipe must terminate within 6 inches above the floor or at an approved drain, and must not be capped.
GFCI protection
Ground-fault circuit interrupter protection is required for receptacles in bathrooms, kitchens, outdoors, garages, and other wet or damp locations per code.
Mortar joint thickness
Standard masonry mortar joints are typically about 3/8 inch thick; joints should be uniform and tooled for weather resistance and appearance.
Roof underlayment
A water-resistant layer installed beneath roof covering to protect the deck; required by code and manufacturer instructions, with flashing at penetrations and valleys.
Stud notch limit
The building code limits notching and boring of wood studs; bearing walls generally allow less notching than nonbearing walls, and holes must avoid utilities.
Fall protection threshold
OSHA construction rules generally require fall protection when workers are exposed to falls of 6 feet or more, or into hazardous equipment or openings.
Scaffold fall protection
Scaffolds generally require guardrails and fall protection when the work platform is 10 feet or more above a lower level; inspect before use.
Ladder 4-to-1 rule
For every 4 feet of ladder height, the ladder base should be set 1 foot away from the wall, and the ladder must extend above the landing.
Trench protective system
Excavations 5 feet or deeper generally require a protective system unless made entirely in stable rock; a competent person must inspect daily.
ADOSH
The Arizona Division of Occupational Safety and Health enforces workplace safety standards in Arizona under a state plan approved by federal OSHA.
Competent person
An individual capable of identifying existing and predictable hazards and authorized to take prompt corrective action, required for excavations and other high-risk work.