BCPMP: Business Continuity Program Initiation and Management

BCPMP · Work through your exam, one topic at a time.

All guide sections

Business Continuity Program Initiation and Management

Why programs fail before they start

A continuity program lives or dies on governance. Candidates must know the difference between program management (the ongoing cycle of establishing, operating, and improving capability) and plan management (maintaining individual documents). The initiating phase establishes scope, policy, governance structure, budget, and authority. The professional's first job is to secure senior management sponsorship and a written policy statement that defines scope, objectives, and accountability.

Know the standard project phases: establishing need, project initiation and management, risk assessment, business impact analysis, strategies, plan development, awareness and training, exercises, and maintenance. Also know the roles: the sponsor/executive provides authority and resources; the continuity coordinator/manager runs the program; business unit owners validate recovery requirements and own their plans; crisis management and emergency response teams handle distinct but linked functions.

Traps

  • Confusing program scope with plan scope. A program scope statement covers the whole enterprise and its dependencies; a plan covers one function or site.
  • Assuming the coordinator owns all plans. Ownership sits with business units; the coordinator enables and assures.
  • Treating the steering committee as optional. Without cross-functional oversight, recovery requirements conflict and funding stalls.
  • Believing a plan equals a program. A program includes policy, BIA, risk assessment, exercises, and maintenance.

Rule of thumb

If a decision requires funding, priority trade-offs, or authority across departments, it belongs to the sponsor and steering committee, not the coordinator alone. If it requires analysis, documentation, or exercise design, it belongs to the program team.

Worked example

A new coordinator is asked to "write the continuity plan" in six weeks. Correct response: define scope and policy, obtain executive sponsorship, form a steering committee, and sequence BIA and risk assessment before drafting any plan content.