BCS Preliminary Test · Put your knowledge to work in context.

All case studies

Choosing a Bridge Site over a Braided River

A district plans a 400-meter bridge over a braided river that shifts its main channel every few years. Two sites are surveyed. Site A is near the town, where the riverbank is sandy and the channel currently runs close to the road. Site B is 6 km downstream, where the bank is firmer clay and the channel is wider but more stable. Site A would cut travel time for about 40,000 people by 25 minutes; Site B would cut it by 15 minutes. Construction at Site A is cheaper by 12 percent, but engineers note that scour around piers is a known problem in sandy beds. The area also floods in monsoon, and the river carries heavy sediment. A local politician favours Site A.

1. Compare the two sites on engineering and social criteria, and recommend one with reasoning.

Read the worked answer

Engineering: Site A has a sandy bank and a channel that shifts, and scour around piers is a known risk in sandy beds. With heavy sediment and monsoon floods, maintenance and failure risk are higher. Site B has firmer clay and a more stable channel, so foundations and approach roads are likely to last longer, even though the bridge is longer.

Social: Site A saves 25 minutes for 40,000 people, against 15 minutes at Site B. That is a real benefit, but it must be weighed against the risk of a bridge that needs repeated repair or fails in a flood.

Recommendation: Site B, unless a detailed scour study at Site A shows the risk can be managed affordably. The 12 percent construction saving at Site A is likely to be outweighed by lifecycle costs of scour protection, river-training works, and disruption if the channel shifts. A stable bridge that saves 15 minutes every day for decades is better than a cheaper bridge that may need closure.

The politician's preference should not override the engineering evidence; the decision should be documented transparently.

2. What additional studies should be done before a final decision, and why does each matter?

Read the worked answer
  1. Hydrological and sediment study: measure peak flood levels, flow velocity, and sediment load over several years. Braided rivers change course, so a single-season survey is unreliable. This determines pier depth and span.

  2. Scour assessment at Site A: model local scour around piers in sandy beds. This tests whether the 12 percent saving survives the cost of protection works.

  3. Geotechnical investigation at both sites: boreholes to confirm the clay depth at Site B and the sand profile at Site A. Foundation design depends on it.

  4. Traffic and economic appraisal: verify the 40,000 and 25-minute figures, and include freight and emergency access. Benefits should be compared over the bridge's design life, not just construction cost.

  5. Environmental and social impact: check displacement, fishing livelihoods, and floodplain effects.

Each study reduces a specific uncertainty, so the final choice rests on evidence rather than on the cheapest bid or political pressure.