BICSI Technician flashcards
BICSI Technician · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Horizontal cable maximum length
- Permanent link is limited to 90 m (295 ft); with patch cords the total channel must not exceed 100 m (328 ft).
- UTP bend radius
- Installed cable must not bend tighter than 4x its outside diameter; during pulling the limit is 8x the outside diameter.
- Fiber bend radius
- Installed fiber cable should maintain at least 10x cable OD; under pull tension the limit is 20x OD unless the manufacturer states otherwise.
- Maximum copper pull tension
- Four-pair copper cable is typically limited to 110 N (25 lbf) pull tension; exceeding this can stretch conductors and degrade performance.
- Cable support spacing
- Horizontal cable must be supported at intervals no greater than 1.5 m (5 ft) and within 300 mm (12 in) of boxes or terminations.
- T568A vs T568B
- Both are eight-position pinouts for RJ-45 termination; the same pinout must be used on both ends of a cable to avoid a crossover.
- Cable tray fill limit
- Cable tray should not exceed 50% of its usable cross-sectional area to allow for future additions and to avoid excess weight.
- Separation from power
- UTP should be at least 2 in (50 mm) from 120/240 V circuits and 4 in (100 mm) from higher-voltage or fluorescent fixtures unless a barrier exists.
- Structured cabling hierarchy
- The sequence is entrance facility, equipment room, backbone, telecommunications room, horizontal cabling, and work area.
- TR floor area limit
- A single telecommunications room should serve no more than 1,000 m2 (10,000 ft2) of usable floor area.
- Horizontal run limit
- No work-area outlet should be more than 90 m of cable from its serving telecommunications room; otherwise add a TR or consolidation point.
- Consolidation point
- A CP allows a horizontal cable to be split into a permanent link and a short patch; only one CP per horizontal run is permitted.
- TR door width
- The telecommunications room door must be at least 910 mm (36 in) wide and swing outward to allow equipment access.
- Backbone fiber distance
- Single-mode fiber supports backbone runs up to 3,000 m; OM3 multimode supports 300 m at 10 Gbps, OM4 up to 400 m.
- Entrance facility clearance
- The entrance facility must provide at least 300 mm (12 in) of clear working space around terminating hardware and grounding.
- J-hook capacity
- Cable supported on J-hooks should not exceed 50% of the hook's rated capacity to prevent cable damage and sag.
- TIA-568 scope
- ANSI/TIA-568 specifies structured cabling performance requirements, including cable categories, connectors, and channel testing.
- TIA-569 scope
- ANSI/TIA-569 covers telecommunications pathways and spaces, including conduit, tray, and telecommunications room requirements.
- TIA-606 scope
- ANSI/TIA-606 specifies administration and labeling of telecommunications infrastructure, including cable and port identifiers.
- TIA-607 scope
- ANSI/TIA-607 covers grounding and bonding for telecommunications, including the TBB and telecommunications grounding busbar.
- NEC Article 800
- NFPA 70 Article 800 covers communications circuits, including wiring methods and protection for telecommunications cabling.
- NEC Article 250
- NFPA 70 Article 250 covers grounding and bonding requirements for electrical systems, including the grounding electrode system.
- Telecommunications bonding backbone
- The TBB is a copper conductor that bonds telecommunications grounding busbars together and connects them to the building grounding electrode system.
- Class 2/3 separation
- Class 2 and 3 circuits must be separated from power and Class 1 circuits by at least 2 in (50 mm) or a barrier, and cannot share a raceway.
- Firestopping requirement
- Penetrations through fire-rated walls or floors must use an approved firestop system listed for that specific penetration type.
- Pre-installation survey
- Before ordering materials, verify pathway capacity, ceiling access, power, HVAC, and fire rating of the installation area.
- As-built documentation
- As-built drawings must reflect actual installed conditions, including cable routes, lengths, and termination records.
- Permanent link test report
- Certification reports must include pass/fail, length, attenuation, NEXT, and return loss for each permanent link or channel.
- Change order
- Any deviation from the design, such as added drops or alternate pathways, requires written approval and revised as-built drawings.
- Job hazard analysis
- A JHA identifies task-specific hazards and controls before work begins, especially for energized or elevated work.
- Punch list closure
- Each deficiency is tracked with location, description, responsible party, and correction date until the item is verified closed.
- Critical path
- The longest sequence of dependent tasks; cable pulls and terminations must precede testing and certification on the schedule.