Boiler Operator study materials
Boiler Operator study resources

Boiler Operator flashcards

Boiler Operator · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Boiler horsepower definition
One boiler horsepower equals 33,475 Btu per hour, the heat needed to evaporate 34.5 pounds of water per hour from and at 212 F.
Fire-tube vs water-tube
In a fire-tube boiler hot gases flow inside tubes surrounded by water; in a water-tube boiler water flows inside tubes surrounded by hot combustion gases.
ASME Section I scope
ASME Boiler and Pressure Vessel Code Section I covers power boilers and their appurtenances, setting requirements for materials, design, fabrication, inspection, and safety valve capacity.
Staybolt function
Staybolts tie together the flat plates of firebox and locomotive-type boilers, preventing the sheets from bulging or deforming under internal steam pressure.
Three T's of combustion
Complete combustion requires adequate Temperature, Turbulence for mixing fuel with air, and Time in the furnace for the combustion reaction to finish.
Excess air purpose
Air supplied beyond the theoretical amount ensures complete combustion; typical excess air is 10-20 percent for gas and oil and 20-40 percent for coal.
Balanced draft
Balanced draft uses a forced draft fan to supply combustion air and an induced draft fan to remove flue gas, holding furnace pressure slightly below atmospheric.
Inches of water column
Draft is measured in inches of water column; one psi equals about 27.7 inches of water column, and furnace draft normally reads about -0.05 to -0.10.
Safety valve requirement
Every boiler must have a safety valve set at or below its maximum allowable working pressure, with no shutoff valve between the boiler and that valve.
Water column blowdown
Blowing down the water column and gauge glass clears sludge and sediment from the connections so the indicated water level remains accurate.
Economizer function
An economizer transfers heat from leaving flue gas to incoming feedwater, lowering stack temperature and improving overall boiler thermal efficiency.
Steam drum dry pipe
A dry pipe or mechanical separator inside the steam drum removes entrained moisture from steam before it leaves the boiler, improving steam quality.
Zeolite softening
Sodium zeolite softening exchanges calcium and magnesium ions in the water for sodium ions, removing the hardness that would otherwise form boiler scale.
Deaerator purpose
A deaerator heats feedwater to saturation and strips out dissolved oxygen and carbon dioxide, which would otherwise cause pitting corrosion in the boiler.
Scale effect on tubes
Scale is a poor heat conductor; it insulates tube metal, raising metal temperature and causing overheating, bulging, and eventual tube failure.
Continuous blowdown
Continuous surface blowdown removes dissolved solids from the steam drum, controlling conductivity and total dissolved solids so carryover does not occur.
Pneumatic control signal
The standard pneumatic transmission signal in boiler controls is 3 to 15 psi, with 3 psi representing zero percent and 15 psi representing 100 percent.
Flame scanner function
A flame scanner uses ultraviolet, infrared, or flame-rectification sensing to prove the burner flame; loss of the flame signal trips the fuel valves.
Pre-purge requirement
Before each lightoff the burner management system must complete a pre-purge, typically five minutes or a specified number of furnace air changes, to clear unburned fuel.
PID control terms
Proportional action responds to the size of the deviation, integral action eliminates offset over time, and derivative action responds to the rate of change.
Normal drum level
Normal operating water level is at the center of the gauge glass; the level must stay visible at all times because low water requires an immediate fuel trip.
Warm-up rate limit
Boilers are heated slowly, commonly at about 100 F per hour, with drum top-to-bottom temperature difference limited to roughly 50-100 F to avoid thermal stress.
Wet lay-up method
Wet lay-up stores an idle boiler full of treated water, often with a nitrogen blanket or oxygen scavenger, to exclude oxygen and prevent corrosion.
Bottom blowdown purpose
Bottom blowdown removes sludge and sediment settling in the mud drum or lower shell; blows are short and frequent with the boiler under load.
Hydrostatic test pressure
A hydrostatic test is performed at 1.5 times the maximum allowable working pressure for new construction, with the boiler filled and all air vented.
Ultrasonic thickness testing
Ultrasonic thickness testing measures remaining wall thickness of tubes, shell, and headers, detecting metal loss from corrosion and erosion without cutting.
Safety valve pop test
A pop test verifies that the safety valve opens at its set pressure, reseats properly, and does not leak; results are recorded in the boiler log.
Dry lay-up method
Dry lay-up removes all water, dries the interior, and places desiccant inside sealed drums and headers to keep the metal free of moisture.
Low-water emergency action
If water is not visible in the gauge glass, shut off the fuel at once; do not add feedwater until the boiler has cooled enough to rule out overheated metal.
Never gag safety valve
A safety valve must never be gagged, plugged, or have its discharge blocked, because it is the final protection against overpressure of the boiler.
NFPA 85 purpose
NFPA 85 is the standard for boiler and burner management systems, covering pre-purge, ignition sequencing, flame proving, and safety interlocks.
Confined space entry
Entering a boiler drum or furnace requires a confined space permit, atmospheric testing, ventilation, an attendant outside, and lockout of all energy sources.