- Sensible heat formula
- Q_s = 1.08 × CFM × ΔT, where Q_s is sensible BTU/h, CFM is airflow, and ΔT is dry-bulb temperature difference. Used at sea level for air.
- Latent heat formula
- Q_l = 0.68 × CFM × ΔW, where ΔW is humidity ratio difference in grains per pound. Represents moisture removal or addition in BTU/h.
- Total heat formula
- Q_t = 4.5 × CFM × Δh, where Δh is enthalpy difference in BTU/lb. Combines sensible and latent loads for coil capacity.
- Superheat definition
- Suction line temperature minus evaporator saturation temperature at the bulb. Target 8–12°F for fixed orifice, 5–10°F for TXV systems.
- Subcooling definition
- Condenser saturation temperature minus liquid line temperature. Target 8–12°F for TXV, 5–10°F for fixed orifice; indicates charge and condenser performance.
- Heat pump reversing valve
- A four-way valve that swaps evaporator and condenser roles. In heating, outdoor coil becomes evaporator and indoor coil becomes condenser.
- Defrost cycle initiation
- Triggered when outdoor coil temperature falls below about 30°F or a pressure/temperature sensor detects frost. Terminates on time or temperature.
- Manual J load calculation
- ACCA method that calculates room-by-room heating and cooling loads using orientation, insulation, windows, infiltration, and internal gains.
- Sensible heat ratio (SHR)
- Sensible load divided by total load. Equipment SHR should closely match structure SHR to avoid humidity control problems.
- Manual S equipment selection
- ACCA procedure for selecting equipment using manufacturer expanded performance data at design conditions rather than nominal capacity ratings.
- Manual D duct sizing
- Sizes ductwork using friction rate = available static pressure ÷ total effective length. Typical supply friction is 0.08–0.10 in. w.c. per 100 ft.
- Balance point
- Outdoor temperature at which heat pump capacity equals building heat loss. Below this point, auxiliary heat supplements the heat pump.
- ASHRAE 62.2 ventilation
- Requires mechanical ventilation when natural infiltration is below 0.35 ACH. CFM = 0.03 × floor area + 7.5 × (bedrooms + 1).
- Nitrogen purge brazing
- Flow 1–2 psig nitrogen through tubing while brazing to prevent internal oxidation. Use silver-phos or 15% silver alloy depending on joint type.
- Evacuation to 500 microns
- Evacuate system to 500 microns or below and hold for 10 minutes with pump isolated. Rising microns indicate leak or moisture.
- Weigh-in charging
- Charge refrigerant by weight when line set length differs from factory charge. Adjust per manufacturer table, typically 0.6 oz per foot of 3/8-inch liquid line.
- Temperature split check
- Return air dry-bulb minus supply air dry-bulb. Normal cooling split is 18–22°F; low split suggests low airflow or charge issue.
- Condensate trap requirement
- Trap depth must be at least total static pressure; drain slope 1/8 inch per foot. Secondary pan with float switch is required.
- External static pressure
- Measured pressure resistance of duct system and components. Compare to fan performance table; target 350–450 CFM/ton cooling, 400–450 CFM/ton heating.
- High superheat diagnosis
- High superheat with low suction pressure indicates undercharge or restriction. Low superheat with high suction pressure indicates overcharge or overfeed.
- High subcooling diagnosis
- High subcooling with high head pressure indicates overcharge or condenser airflow restriction. Low subcooling with bubbles indicates undercharge.
- Compressor amp draw check
- Measure compressor amps and compare to nameplate RLA. Amps above RLA with high head pressure suggest mechanical or electrical fault.
- Capacitor microfarad test
- Use a multimeter with capacitance function to measure microfarads. Replace capacitor if reading is outside ±10% of rated value.
- Leak detection methods
- Electronic leak detector, UV dye, or nitrogen pressure test at 150–300 psig. Never use oxygen or acetylene for pressure testing.
- Balometer airflow verification
- Measure CFM at each register with a balometer. Total measured airflow should match design within ±10%.
- Thermostat voltage check
- Verify 24 VAC ±10% at R–Y, R–G, and R–W terminals during call. Check anticipator or cycle rate settings for proper operation.
- Lockout/tagout procedure
- Disconnect power at breaker, verify with meter, and apply lock before servicing. Never rely on thermostat off position.
- R-410A pressure safety
- R-410A operates at about 1.6 times R-22 pressure. Use gloves and eye protection; never heat a sealed system or mix refrigerants.
- EPA Section 608 certification
- Technicians must be certified to purchase or handle refrigerant. Recovery is required before opening system; venting is prohibited.
- Electrical safety verification
- Test 24 VAC control voltage and line voltage separately. Treat all conductors as live until tested with a meter.
- Startup documentation
- Record model/serial, refrigerant type and charge, filter sizes, startup readings, and deficiencies on invoice for warranty and reference.
- Fall protection threshold
- Use fall protection on roofs above 6 feet. Wear safety glasses, gloves, and steel-toe boots as personal protective equipment.