Mistake 1

Treating the envelope as only the exterior walls, and failing items that ask about the ceiling plane, rim joists, or the boundary between conditioned and unconditioned space.

Candidates carry over a colloquial 'walls and windows' mental model and never map the pressure and thermal boundary as one continuous surface, so they misclassify attic floors, cantilevers, and garage walls.

What to do instead

Before answering any envelope-identification item, sketch the conditioned box and trace one continuous line around it, naming each assembly the line crosses; practice on plans with bonus rooms, kneewalls, and attached garages until the boundary trace is automatic.

Mistake 2

Confusing conduction, convection, and radiation when explaining why a cavity performs poorly, attributing airflow-driven heat loss to conduction or mislabeling radiant transfer.

The three modes are taught together and candidates memorize definitions without linking each mode to a visible building symptom, so they default to 'conduction' for every heat-loss question.

What to do instead

Build a three-column table pairing each mode with a building signature (conduction: cold wall surface; convection: dirty insulation at top plate; radiation: cold window felt on the face) and rehearse identifying the dominant mode from the described symptom.

Mistake 3

Chasing air leakage with a caulk-and-foam blitz without first locating and prioritizing the largest leakage sites by measured impact.

Candidates equate air sealing with effort rather than with targeting, and the exam rewards knowing that top-plate, rim-joist, and penetration leaks dominate over scattered small cracks.

What to do instead

Learn the standard priority stack (attic plane, rim joists, penetrations, doors and windows last) and practice ranking a described list of leaks by estimated contribution before choosing a scope of work.

Mistake 4

Specifying a vapor retarder on the wrong side of the assembly or omitting it entirely because 'the wall needs to dry.'

Candidates memorize 'retarder goes on the warm side' without adjusting for climate zone, and they conflate vapor diffusion control with air leakage control.

What to do instead

Work through one wall assembly per climate zone, stating where the retarder, air barrier, and insulation sit and which direction drying occurs; explicitly separate the vapor retarder's job from the air barrier's job in every answer.

Mistake 5

Installing or approving impermeable interior finishes and foam on the interior of a wall without verifying the assembly can dry, then missing the moisture-accumulation consequence.

Candidates focus on R-value gains and ignore that trapping moisture between two low-permeance layers creates a condensation plane.

What to do instead

For any proposed assembly, identify the condensing surface, the permeance of each layer, and the drying path; practice flagging 'double vapor barrier' configurations and stating the failure mechanism and a corrected design.

Mistake 6

Sizing ventilation to a rule of thumb instead of the applicable standard, and confusing whole-house ventilation with local exhaust.

Candidates blend bath fan, range hood, and whole-house requirements into one number and skip the distinction between intermittent local exhaust and continuous dwelling ventilation.

What to do instead

Memorize which standard governs which function, practice computing a continuous whole-house rate from the published table for a given house size and bedroom count, and state separately the local exhaust requirements for kitchens and baths.

Mistake 7

Treating ventilation as automatically improving indoor air quality without accounting for source control, filtration, or makeup air for combustion and exhaust appliances.

Candidates equate 'more outside air' with 'better air' and overlook backdrafting risk and pollutant sources that ventilation alone does not solve.

What to do instead

Answer IAQ items in the order source control, then ventilation, then filtration, and always check whether added exhaust requires makeup air or combustion-air provisions before endorsing the strategy.

Mistake 8

Judging window performance by U-factor alone or by glazing count, ignoring solar heat gain coefficient, air leakage rating, and the effect of frame and installation details.

Candidates latch onto the most advertised number and forget that a good window in a poorly flashed rough opening still fails, and that SHGC matters differently by climate.

What to do instead

For each window item, state the climate-driven tradeoff between U-factor and SHGC, then name the installation factors (flashing sequence, shim and seal, pan) that determine real performance; practice selecting glazing packages for hot and cold climates side by side.

Mistake 9

Reading a blower door result as a single pass/fail number without normalizing for house volume, conditioned area, or the test conditions.

Candidates memorize a threshold without understanding that CFM50 must be converted to ACH50 or CFM50 per square foot to compare houses of different sizes, and they ignore test setup variables.

What to do instead

Practice the conversions by hand on several house sizes, state units explicitly in every answer, and list the test-precondition checks (exterior openings closed, combustion appliances off or monitored, baseline pressure) before interpreting any reading.

Mistake 10

Interpreting a pressure diagnostic without establishing a baseline or confirming which zone is reference, so a zone reading is inverted or attributed to the wrong cause.

Candidates treat a single manometer number as self-explanatory and skip the step of asking 'relative to what,' which leads to reversed conclusions about driving forces and leakage direction.

What to do instead

Adopt a fixed routine for every pressure question: state the reference zone, the sign convention, the driving force (stack, wind, or fan), and the expected direction; rehearse with zonal pressure and duct leakage scenarios until the reference is always stated first.