BREEAM Assessor (New Construction) study materials
BREEAM Assessor (New Construction) study resources

BREEAM Assessor (New Construction) flashcards

BREEAM Assessor (New Construction) · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

BREEAM New Construction rating thresholds
Overall percentage scores map to Pass at 30 or above, Good at 45, Very Good at 55, Excellent at 70 and Outstanding at 85.
Category weighting
Each environmental category's percentage score is multiplied by a weighting that varies by building type and scheme version, then combined into the overall score.
Minimum standards
Mandatory credits that must be achieved for a given rating level; failing any mandatory credit prevents that rating regardless of overall score.
Innovation credits
Additional credits awarded for exemplary performance beyond standard requirements, capped as a proportion of total available score and added to the overall percentage.
Energy category weighting
Energy carries the largest weighting of any New Construction category, reflecting its dominant contribution to the overall BREEAM score.
Scheme version lock-in
The manual version registered at project registration governs the credits, weightings, thresholds and evidence requirements used throughout that project's assessment.
Scope of New Construction
The scheme covers new non-domestic buildings and major refurbishments; fit-out-only projects fall under separate BREEAM schemes with different credit sets.
Mandatory Energy credit
A prerequisite credit within the Energy category that must be achieved for any rated outcome; it cannot be offset by strong performance elsewhere.
Certification route sequence
Registration, assessor appointment, evidence gathering, internal QA, submission to BRE, query resolution and final certification by BRE Global.
Registration timing
Registration must occur before design is complete and before the target rating is fixed, locking the scheme version and building type.
Design-stage assessment
An assessment performed after registration using design evidence; it indicates likely performance but is superseded by the final as-built assessment.
Interim certification
An optional formal design-stage certificate issued by BRE indicating the rating likely to be achieved, replaced by the final post-construction certificate.
Final certificate issuer
BRE Global issues the BREEAM certificate; the assessor compiles and submits evidence but cannot certify or issue certificates.
BRE technical queries
Questions raised by BRE during review of a submission; they require evidence or clarification, and unresolved queries can reduce the final rating.
Post-construction evidence
Evidence generated after construction, such as commissioning records and as-built drawings, required for credits that depend on actual installed performance.
Certificate validity scope
A certificate applies to the building as assessed; changes of use, major alterations or new scheme versions may require a fresh assessment.
Evidence acceptance criteria
Evidence must be current, project-specific, dated, traceable to the credit and demonstrate achievement in practice rather than only specification intent.
Acceptable evidence types
Drawings, specifications, manufacturer declarations, commissioning records, invoices, photographs, calculations and signed statements are acceptable; generic marketing material is not.
As-built versus specified
Post-construction credits require evidence of what was actually installed and commissioned, not design-stage specifications or intentions.
Evidence referencing
The assessor records each piece of evidence in the online tool against the relevant credit and retains a copy for audit.
Handling missing evidence
Where evidence is absent or ambiguous, the credit is not claimed or further evidence is requested; assessors must not infer or fabricate evidence.
Internal QA review
The assessor's organisation checks credit claims, calculations and evidence trails before submission to BRE, and retains records of that review.
Evidence retention
Assessment records and evidence must be kept for the period required by the licensing scheme and produced for audit on request.
Traceability requirement
Every claimed credit must link to specific dated project documents that a third-party reviewer can locate and verify independently.
Licensed scope
An assessor may only practise for scheme versions and building types covered by a current licence; acting outside that scope breaches the licence.
Assessor core duties
Advise on scheme and target rating, register the project, compile and validate evidence, submit the assessment and answer BRE queries.
Independence and integrity
Assessors must declare conflicts of interest and must not misrepresent project performance or imply that certification is guaranteed.
Confidentiality obligation
Client and project information may only be shared with BRE and authorised parties for assessment and audit purposes.
Licence renewal and CPD
Assessors must complete continuing professional development and renew their licence; a lapsed licence bars assessor activity until reinstated.
Online assessment tool record
The tool holds the project record, credit evidence references, assessor declarations and submission status, and is the authoritative submission to BRE.
No self-certification rule
Assessors cannot certify projects or state that certification has been granted; only BRE Global issues certificates, and client misunderstandings must be corrected.
Audit-ready record-keeping
Entries in the online tool must reflect evidence actually held, and any retrospective edits must be justified and traceable.