BREEAM Assessor (New Construction) flashcards
BREEAM Assessor (New Construction) · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- BREEAM New Construction rating thresholds
- Overall percentage scores map to Pass at 30 or above, Good at 45, Very Good at 55, Excellent at 70 and Outstanding at 85.
- Category weighting
- Each environmental category's percentage score is multiplied by a weighting that varies by building type and scheme version, then combined into the overall score.
- Minimum standards
- Mandatory credits that must be achieved for a given rating level; failing any mandatory credit prevents that rating regardless of overall score.
- Innovation credits
- Additional credits awarded for exemplary performance beyond standard requirements, capped as a proportion of total available score and added to the overall percentage.
- Energy category weighting
- Energy carries the largest weighting of any New Construction category, reflecting its dominant contribution to the overall BREEAM score.
- Scheme version lock-in
- The manual version registered at project registration governs the credits, weightings, thresholds and evidence requirements used throughout that project's assessment.
- Scope of New Construction
- The scheme covers new non-domestic buildings and major refurbishments; fit-out-only projects fall under separate BREEAM schemes with different credit sets.
- Mandatory Energy credit
- A prerequisite credit within the Energy category that must be achieved for any rated outcome; it cannot be offset by strong performance elsewhere.
- Certification route sequence
- Registration, assessor appointment, evidence gathering, internal QA, submission to BRE, query resolution and final certification by BRE Global.
- Registration timing
- Registration must occur before design is complete and before the target rating is fixed, locking the scheme version and building type.
- Design-stage assessment
- An assessment performed after registration using design evidence; it indicates likely performance but is superseded by the final as-built assessment.
- Interim certification
- An optional formal design-stage certificate issued by BRE indicating the rating likely to be achieved, replaced by the final post-construction certificate.
- Final certificate issuer
- BRE Global issues the BREEAM certificate; the assessor compiles and submits evidence but cannot certify or issue certificates.
- BRE technical queries
- Questions raised by BRE during review of a submission; they require evidence or clarification, and unresolved queries can reduce the final rating.
- Post-construction evidence
- Evidence generated after construction, such as commissioning records and as-built drawings, required for credits that depend on actual installed performance.
- Certificate validity scope
- A certificate applies to the building as assessed; changes of use, major alterations or new scheme versions may require a fresh assessment.
- Evidence acceptance criteria
- Evidence must be current, project-specific, dated, traceable to the credit and demonstrate achievement in practice rather than only specification intent.
- Acceptable evidence types
- Drawings, specifications, manufacturer declarations, commissioning records, invoices, photographs, calculations and signed statements are acceptable; generic marketing material is not.
- As-built versus specified
- Post-construction credits require evidence of what was actually installed and commissioned, not design-stage specifications or intentions.
- Evidence referencing
- The assessor records each piece of evidence in the online tool against the relevant credit and retains a copy for audit.
- Handling missing evidence
- Where evidence is absent or ambiguous, the credit is not claimed or further evidence is requested; assessors must not infer or fabricate evidence.
- Internal QA review
- The assessor's organisation checks credit claims, calculations and evidence trails before submission to BRE, and retains records of that review.
- Evidence retention
- Assessment records and evidence must be kept for the period required by the licensing scheme and produced for audit on request.
- Traceability requirement
- Every claimed credit must link to specific dated project documents that a third-party reviewer can locate and verify independently.
- Licensed scope
- An assessor may only practise for scheme versions and building types covered by a current licence; acting outside that scope breaches the licence.
- Assessor core duties
- Advise on scheme and target rating, register the project, compile and validate evidence, submit the assessment and answer BRE queries.
- Independence and integrity
- Assessors must declare conflicts of interest and must not misrepresent project performance or imply that certification is guaranteed.
- Confidentiality obligation
- Client and project information may only be shared with BRE and authorised parties for assessment and audit purposes.
- Licence renewal and CPD
- Assessors must complete continuing professional development and renew their licence; a lapsed licence bars assessor activity until reinstated.
- Online assessment tool record
- The tool holds the project record, credit evidence references, assessor declarations and submission status, and is the authoritative submission to BRE.
- No self-certification rule
- Assessors cannot certify projects or state that certification has been granted; only BRE Global issues certificates, and client misunderstandings must be corrected.
- Audit-ready record-keeping
- Entries in the online tool must reflect evidence actually held, and any retrospective edits must be justified and traceable.