LTP10 · Keep the key ideas within reach.

Quick reference

Foundations and Core Concepts

  • LTP10 defines five process groups: Initiating, Planning, Executing, Monitoring & Controlling, and Closing; they are not sequential phases but may overlap.

  • A project is a temporary endeavor with a defined start and end, producing a unique product, service, or result; operations are ongoing and repetitive.

  • Project vs. program vs. portfolio: a program is a group of related projects managed together for synergies; a portfolio is a collection of projects/programs aligned to strategic objectives.

  • The triple constraint (scope, time, cost) is balanced by quality; a change in any one typically affects the others.

  • Stakeholders are individuals or groups who can affect or be affected by the project; their influence and interest vary over the project life cycle.

  • Organizational process assets (OPAs) are internal policies, procedures, and historical data; enterprise environmental factors (EEFs) are external conditions such as market, culture, and regulations.

  • A project management office (PMO) can be supportive (consultative), controlling (compliance), or directive (direct management of projects).

  • The project life cycle consists of phases; phase gates (kill points) review deliverables and authorize the next phase.

  • Project success is measured by meeting scope, schedule, cost, and quality objectives and by stakeholder satisfaction; benefits realization may extend beyond project closure.

Quick reference

Planning and Preparation

  • The project charter authorizes the project, names the project manager, and documents high-level scope, objectives, and constraints; it is issued by the sponsor.

  • The project management plan integrates subsidiary plans (scope, schedule, cost, quality, resource, communications, risk, procurement, stakeholder) and baselines.

  • Scope baseline = scope statement + work breakdown structure (WBS) + WBS dictionary; it is used to control scope.

  • WBS decomposition follows the 100% rule: all work in the project is captured, and no work outside the WBS is performed.

  • Schedule baseline is developed using precedence diagramming method (PDM); critical path is the longest path through the network and determines project duration.

  • Cost baseline is the time-phased budget used to measure cost performance; management reserve is not part of the baseline but is for unknown-unknown risks.

  • Risk management plan defines risk appetite, thresholds, and the risk breakdown structure (RBS); risk identification uses techniques like brainstorming, Delphi, and SWOT.

  • Stakeholder engagement plan classifies stakeholders by power/interest and defines engagement strategies from unaware to leading.

  • Communications management plan specifies who needs what information, when, how, and by whom; it accounts for communication channels = n(n-1)/2.

Quick reference

Execution and Delivery

  • Direct and Manage Project Work involves leading the team, managing stakeholder engagement, and producing deliverables; work performance data is generated here.

  • Quality assurance (manage quality) is a preventive, process-oriented activity; quality control (control quality) is a detective, product-oriented activity.

  • Team development stages: forming, storming, norming, performing, adjourning; the project manager adapts leadership style to the stage.

  • Conflict resolution techniques include collaborating (win-win), compromising, forcing, avoiding, and smoothing; collaborating is generally preferred for important issues.

  • Motivation theories: Maslow's hierarchy, Herzberg's two-factor (hygiene vs. motivators), McGregor's Theory X/Y, and Vroom's expectancy theory.

  • Procurement execution includes selecting sellers, awarding contracts, and managing seller performance; contract types include fixed-price, cost-reimbursable, and time-and-materials.

  • Distribute information (manage communications) ensures stakeholders receive timely and appropriate information per the communications plan.

  • Manage stakeholder engagement involves fostering appropriate stakeholder involvement throughout the project life cycle.

Quick reference

Monitoring, Measurement, and Control

  • Earned value management (EVM) integrates scope, schedule, and cost: PV = planned value, EV = earned value, AC = actual cost.

  • Schedule variance SV = EV - PV; cost variance CV = EV - AC; negative values indicate unfavorable performance.

  • Schedule performance index SPI = EV / PV; cost performance index CPI = EV / AC; values less than 1.0 indicate behind schedule or over budget.

  • Estimate at completion EAC = BAC / CPI (typical variance); EAC = AC + (BAC - EV) (atypical variance); EAC = AC + bottom-up ETC.

  • To-complete performance index TCPI = (BAC - EV) / (BAC - AC) for budget constraint; TCPI = (BAC - EV) / (EAC - AC) for EAC constraint.

  • Variance analysis compares actual performance to the baseline; trend analysis forecasts future performance; earned value graph plots PV, EV, and AC over time.

  • Integrated change control reviews all change requests, assesses impact on baselines, and approves, rejects, or defers them; approved changes update the plan.

  • Control quality uses tools such as cause-and-effect diagrams, control charts, Pareto charts, and statistical sampling to identify defects.

  • Configuration management ensures that versions of deliverables and documents are controlled and that changes are tracked.

Quick reference

Problem Solving and Decision Making

  • Problem-solving steps: define the problem, identify root cause, generate alternatives, select a solution, implement, and verify.

  • Root cause analysis tools: 5 Whys, fishbone (Ishikawa) diagram, and Pareto analysis (80/20 rule) to prioritize the most significant causes.

  • Decision-making techniques include voting, multicriteria decision analysis, and consensus; the Delphi technique gathers expert opinions anonymously.

  • The nominal group technique generates and ranks ideas through silent generation and round-robin sharing.

  • Group decision-making can be affected by groupthink; techniques like devil's advocate and brainstorming with independent idea generation reduce it.

  • Expected monetary value (EMV) = probability × impact; used in decision tree analysis to compare alternatives under uncertainty.

  • Opportunity cost is the value of the next best alternative forgone when making a decision.

  • Escalation is appropriate when a problem exceeds the project manager's authority or requires sponsor or steering committee involvement.

Quick reference

Communication and Stakeholder Management

  • Communication model: sender encodes, message travels through a medium, receiver decodes, and feedback confirms understanding; noise interferes.

  • Communication channels formula: n(n-1)/2, where n is the number of stakeholders; channels grow rapidly with team size.

  • Communication methods: interactive (meetings), push (emails, reports), and pull (intranet, knowledge repositories); choice depends on urgency and audience.

  • Stakeholder analysis classifies by power, interest, influence, and impact; the power/interest grid guides engagement strategy.

  • Stakeholder engagement levels: unaware, resistant, neutral, supportive, leading; the plan aims to move stakeholders toward support.

  • Effective communication is timely, clear, complete, and tailored to the audience; cultural and language differences must be considered.

  • Manage stakeholder engagement involves monitoring stakeholder relationships and adjusting strategies to keep them engaged.

  • Conflict is inevitable; the project manager should address it early and focus on interests, not positions.