The Reserve Fund Study That Was Eight Years Old

BC Strata Management · Put your knowledge to work in context.

All case studies

The Reserve Fund Study That Was Eight Years Old

Lakeview Towers is a 200-unit strata in Burnaby with a replacement cost of about $60 million. Its most recent depreciation report is dated eight years ago. The CRF balance is $1.9 million. The roof (estimated replacement $2.4 million, remaining life 2 years), elevators ($900,000, 6 years) and parkade membrane ($1.1 million, 4 years) are all listed in the old report. Council has just approved a $350,000 lobby cosmetic renovation from the CRF by 3/4 vote, and the treasurer proposes to defer a new depreciation report for two more years to "save the $18,000 fee." An owner asks the manager whether the strata is complying with its reserve fund obligations.

1. Assess compliance with the depreciation report and CRF funding requirements, and identify the consequences of the current course.

Read the worked answer

Depreciation report. The Act requires a strata corporation to obtain a depreciation report on a prescribed cycle (generally every three years, with limited exemptions such as certain bare-land or phased strata, or where owners have resolved by 3/4 vote to defer - but deferral resolutions are time-limited and must be renewed). An eight-year-old report is well outside the cycle. Deferring again to save $18,000 is a false economy and, absent a valid deferral resolution, non-compliant.

CRF adequacy. The CRF must be funded at a level sufficient to meet the anticipated costs in the depreciation report. Here the report itself shows near-term obligations of roughly $4.4 million against a $1.9 million fund - a structural shortfall. Council should be commissioning a current report, not delaying one, because the funding plan (annual CRF contributions) must be tied to real numbers.

The lobby renovation. Spending $350,000 from the CRF on cosmetics while the roof is two years from a $2.4 million replacement is a fiduciary problem even if the 3/4 vote was technically valid. The vote authorizes the expenditure; it does not immunize council from the duty to maintain the reserve fund for its intended purpose.

Consequences. Owners may be exposed to a large special levy at short notice; council faces challenge for failing to fund the CRF; and the manager's advice should be documented so responsibility is clear.

2. The treasurer argues that because owners approved the renovation by 3/4 vote, the CRF use is lawful and the manager should simply process it. How should the manager respond, and what should council do next?

Read the worked answer

The treasurer is half right and wholly incomplete. A 3/4 vote is necessary for a CRF expenditure, but legality of process is not the whole duty. The manager should say:

  • Process: confirm the resolution identified the purpose and amount, that the meeting was properly noticed, and that the vote was recorded correctly. If so, the expenditure is authorized.
  • Substance: the manager must still advise, in writing, that the expenditure worsens an already inadequate reserve position and that the roof, elevators and membrane are unfunded. The manager should not refuse to process a validly authorized expenditure, but should not let the record show unqualified endorsement either.

What council should do next: (1) commission an updated depreciation report immediately; (2) adopt a CRF funding plan with annual contributions calibrated to the report; (3) consider whether the renovation should be phased or deferred until the roof is funded; (4) communicate honestly with owners about the likely need for a special levy. The manager should put this advice in a memo to council and keep a copy on file - the paper trail is the manager's protection and the strata's governance record.