Labor Burden and Overtime on a Crash Schedule

Gold Seal Estimator · Put your knowledge to work in context.

All case studies

Labor Burden and Overtime on a Crash Schedule

A client wants a 16-week schedule compressed to 12 weeks for a 30,000 sq ft office fit-out. Your estimate assumed 5,000 electrician hours at straight time with a loaded rate of $58/hour that already includes 32% burden (payroll taxes, insurance, benefits). To compress, you would run 10-hour days and Saturdays, pushing roughly 1,200 of the hours into overtime at 1.5× base wage. Base wage is $40/hour; burden applies to base wages and generally does not apply to the overtime premium portion in the same way. The client asks for a single accelerated price and expects it to be 'just the labor delta.'

1. Compute the labor cost impact of the crash schedule, being careful about how burden interacts with overtime.

Read the worked answer

Separate base wage, burden, and the overtime premium.

  • Straight-time baseline: 5,000 hours × $58 loaded = $290,000. (Loaded rate = $40 base + 32% burden ≈ $52.80 + other loadings to $58; use the given $58 as the all-in straight rate.)
  • Overtime premium: The 1.5× applies to base wage. The premium portion is 0.5 × $40 = $20/hour on the 1,200 OT hours, i.e., 1,200 × $20 = $24,000. Burden typically attaches to the base wage but not to the premium half, so do not multiply the $24,000 by 1.32 unless your payroll practice says otherwise - confirm with finance.
  • Productivity loss: 10-hour days and six-day weeks reduce productivity. A common planning allowance is 5–10% on the affected hours. On 1,200 hours at $58, a 7% loss is about $4,872.

Total labor delta ≈ $24,000 premium + ~$4,900 productivity = roughly $29,000, before markup. The key judgment is not applying full burden to the premium and not ignoring fatigue-driven productivity loss.

2. The client says the delta looks high and asks you to 'just absorb it into the schedule savings.' How do you respond?

Read the worked answer

The schedule savings accrue to the client, not to you, so absorbing the cost is not justified. Frame it plainly:

  • The acceleration is a client-directed change in performance, and the cost is a direct consequence.
  • The overtime premium is a real payroll cost; the productivity loss is a real field cost. Neither disappears because the schedule is shorter.
  • Absorbing it sets a precedent and erodes margin on a job already compressed.

Offer options: (a) price the full acceleration; (b) accelerate only the critical-path portion to reduce OT hours; (c) keep the 16-week schedule and avoid the premium. Present the trade-off rather than conceding. Document the client's direction and the basis of the delta so any negotiation is transparent.