CCRTS cheat sheet
CCRTS · Keep the key ideas within reach.
Cyber Resilience Strategy, Governance, and Risk
Cyber resilience = anticipate + withstand + recover + adapt; measure it as reduced downtime and data loss, not as control counts.
Core governance artifacts: resilience policy, risk appetite statement, RACI across business/IT/security, and board-level reporting cadence.
Risk formula: risk = likelihood × impact; treat residual risk after controls as the number the business formally accepts.
Qualitative scale example: 5×5 matrix where impact 4 = >$1M or regulatory notification, impact 5 = life-safety or insolvency.
Tier systems by criticality: Tier 1 (RTO ≤ 4h, mission-critical), Tier 2 (RTO 4–24h), Tier 3 (RTO > 24h); controls and test frequency scale with tier.
Regulatory mapping: financial sector often cites FFIEC and DORA; healthcare HIPAA Security Rule; payments PCI DSS; EU-wide NIS2.
Resilience maturity model stages: ad hoc → repeatable → defined → managed → optimized; evidence of testing is the usual gating criterion.
Board reporting should include top residual risks, test results, open corrective actions with owners and due dates, and trend over time.
Business Impact Analysis and Recovery Objectives (RTO/RPO)
RTO = maximum tolerable downtime before impact becomes unacceptable; MTD is the outer limit and RTO must be ≤ MTD.
RPO = maximum tolerable data loss measured in time; it drives backup frequency and replication mode (sync vs async).
WRT (work recovery time) = time to verify and resume business processing after systems are restored; RTO = technical recovery + WRT.
BIA inputs: process inventory, upstream/downstream dependencies, peak-period volumes, revenue per hour of outage, regulatory deadlines.
Impact dimensions to score: financial, operational, legal/regulatory, reputational, safety; record the worst credible case per process.
Dependency mapping must include identity providers, DNS, network, and SaaS APIs - outages often come from shared dependencies, not the app.
Tiering rule: a process inheriting a Tier 1 dependency cannot be Tier 2; the strictest upstream RTO governs.
BIA refresh triggers: major architecture change, M&A, new regulation, or a real incident that disproves assumed RTO/RPO.
Backup, Replication, and Immutable Data Protection
3-2-1-1-0 rule: 3 copies, 2 media types, 1 offsite/offline, 1 immutable or air-gapped, 0 errors verified by restore testing.
Backup types: full, incremental (changed since last backup of any type), differential (changed since last full); synthetic full merges incrementals.
Immutability options: object lock in compliance mode (cannot be deleted before retention expires, even by admins) vs governance mode (privileged override).
Air gap = physically or logically disconnected copy; offline tape or a vault with no standing network path defeats ransomware encryption of backups.
Replication is not backup: synchronous replication copies corruption and deletions instantly; async replication bounds data loss to the lag window.
Encryption: encrypt at rest and in transit; keep backup encryption keys outside the backed-up environment so credential theft cannot decrypt archives.
Retention policy must satisfy legal hold and regulatory minimums; verify deletion actually occurs and is logged for audit.
Restore metrics to track: restore success rate, time to restore a single file, time to restore a full tier-1 system, and backup job failure rate.
Incident Response and Crisis Management
NIST SP 800-61 lifecycle: preparation → detection and analysis → containment, eradication, recovery → post-incident activity.
Severity matrix example: SEV1 = confirmed data breach or Tier 1 outage; SEV2 = degraded Tier 1 or Tier 2 outage; SEV3 = contained, limited impact.
Crisis team roles: incident commander, communications lead, legal counsel, technical lead, scribe; the commander does not troubleshoot.
Escalation triggers: ransomware encryption, exfiltration evidence, safety impact, regulatory notification threshold, or media inquiry.
Notification clocks vary: GDPR 72 hours to the supervisory authority; contractual and sector rules may be shorter - pre-map them per jurisdiction.
Communications: pre-approved holding statements, single spokesperson, internal cadence (e.g., every 60 minutes), and a log of every external statement.
Evidence handling: preserve volatile data first, hash evidence, maintain chain of custody, and document every action with timestamps in UTC.
Stand up a separate out-of-band channel (phone bridge, secondary email) because attackers often control the primary collaboration tools.
Disaster Recovery Planning and Alternate Operations
DR plan contents: scope, activation authority, call trees, recovery runbooks by tier, dependency contacts, and return-to-normal criteria.
Recovery site models: cold (space and power only), warm (partial hardware, data restored on demand), hot (mirrored, near-instant failover).
Alternate operations: manual workarounds, paper procedures, alternate site or remote work, and temporary third-party capacity.
Plan must state who can declare a disaster and the objective triggers, e.g., site unavailable > 4 hours or Tier 1 RTO at risk.
Runbooks should be step-by-step with expected outputs and verification checks, not narrative descriptions of architecture.
Maintain a manual contact roster off-network; assume email, SSO, and the intranet are unavailable during activation.
Failover is not complete until business processing resumes; require business-side sign-off, not just IT system availability.
Return-to-normal plan: data reconciliation between sites, reverse replication, and a defined reconciliation window before decommissioning the alternate.
Ransomware and Destructive Attack Resilience
Attack chain: initial access (phishing, exposed VPN/RDP, vulnerable edge device) → credential theft → privilege escalation → lateral movement → staging → exfiltration → encryption.
Double extortion = encryption plus threatened release of stolen data; paying does not guarantee deletion, so assume exfiltrated data is public.
Destructive attacks (wiper malware) target backups, hypervisors, and identity systems first; protect the recovery plane as a Tier 0 asset.
Detection signals: mass file rename or entropy spike, backup deletion or retention-policy changes, disabled security tooling, unusual privileged logons.
Containment decisions: isolate segments, disable compromised accounts, revoke sessions and tokens, and rotate credentials from a clean environment.
Recovery sequencing: rebuild identity and core network first, restore from verified immutable copies, scan before reconnection, then restore business apps by tier.
Decryption tooling is unreliable for modern variants; plan for restore-from-backup as the primary recovery path, not decryption.
Sanction and legal considerations: paying ransom may violate sanctions law in some jurisdictions; involve counsel before any payment decision.
Supply Chain, Third-Party, and Cloud Resilience
Third-party risk tiers by data sensitivity and operational criticality; require evidence such as SOC 2 Type II, ISO 27001, or equivalent attestations.
Contract clauses that matter for resilience: RTO/RPO commitments, notification timelines, audit rights, data return and deletion, subprocessor disclosure.
Concentration risk: identify single providers or shared dependencies (one cloud region, one DNS provider, one identity provider) that could fail simultaneously.
Shared responsibility: cloud provider secures the cloud; the customer secures what runs in it - backups, identity configuration, and data classification remain customer duties.
Cloud resilience controls: multi-AZ by default, cross-region replication for Tier 1, tested restore from provider-native backup vaults.
Fourth-party risk = your vendor's vendors; request subprocessor lists and assess the critical ones, not just the prime contractor.
Exit strategy: documented data export formats, transition assistance obligations, and a tested ability to migrate within the contract term.
Continuous monitoring: track vendor security ratings, breach disclosures, and SLA performance; reassess on renewal or material change.
Testing, Exercising, and Continuous Improvement
Test types in ascending rigor: plan review, tabletop, walkthrough, simulation, parallel test, full failover, and full interruption test.
Tabletop exercise design: scenario, injects, participants with defined roles, stated objectives, and a hot-wash debrief immediately after.
Backup restore testing should be scheduled and sampled: restore random files weekly and a full Tier 1 system at least quarterly.
Test in production with safeguards only under change control; define abort criteria and a rollback path before starting.
Metrics to capture: actual RTO vs target, actual RPO vs target, number of plan gaps found, corrective actions opened and closed.
Corrective action tracking needs an owner, due date, and verification; a finding closed without a re-test is not closed.
Test frequency should scale with tier and change rate; a Tier 1 system with quarterly releases warrants at least annual full failover.
Regulatory and audit drivers may mandate exercise frequency and evidence retention - keep dated after-action reports as proof.
Recovery Validation, Forensics, and Post-Incident Review
Recovery validation criteria: data integrity checks (record counts, checksums), application function tests, and business-process sign-off.
Forensic order of volatility: CPU registers and cache → memory → network state → disk → remote logs → archival media.
Chain of custody: unique evidence ID, collector identity, date/time in UTC, hash (SHA-256) at acquisition and at each transfer.
Forensic soundness: use write blockers and image copies; work from the copy, preserve the original unmodified.
Post-incident review (PIR) is blameless: focus on control gaps and timeline facts, not individual fault; produce a dated report.
PIR content: timeline, root cause and contributing factors, what worked, what failed, metrics vs targets, and prioritized corrective actions.
Lessons learned must feed back into the BIA, DR plan, and control set; otherwise the same failure recurs.
Retain logs and evidence per legal and regulatory retention rules; confirm log integrity (immutable storage, time sync) before an incident occurs.