- Hierarchy of Controls
- Ranking of hazard controls from most to least effective: elimination, substitution, engineering controls, administrative controls, and personal protective equipment, which is considered the last line of defense.
- TRIR Formula
- Total recordable incident rate equals the number of OSHA recordable cases multiplied by 200,000 and divided by total hours worked; 200,000 represents 100 full-time workers at 40 hours for 50 weeks.
- DART Rate
- Days Away, Restricted, or Transferred rate equals DART cases times 200,000 divided by hours worked, measuring recordable cases that caused time away, restricted duty, or job transfer.
- Prevention through Design
- Applying the hierarchy of controls during design of facilities, equipment, processes, and work methods so hazards are eliminated or reduced before construction and operation begin.
- ISO 45001 PDCA Clauses
- Clause structure: 4 context of the organization, 5 leadership and worker participation, 6 planning, 7 support, 8 operation, 9 performance evaluation, and 10 improvement.
- ANSI/ASSP Z10
- A U.S. national consensus standard for occupational health and safety management systems that provides a flexible framework for establishing, implementing, evaluating, and improving an OHSMS.
- OH&S Policy Requirements
- Top management must establish a policy including commitments to provide safe and healthy working conditions, prevent injury and ill health, fulfill legal and other requirements, and pursue continual improvement.
- Management Review Inputs
- Required inputs include audit results, compliance evaluation, incident and nonconformity data, worker consultation, stakeholder issues, and objective progress; outputs include improvement decisions and resource needs.
- Hazard versus Risk
- A hazard is a potential source of harm, while risk is the combination of the likelihood of a hazardous event and the severity of the harm it could cause.
- Risk Matrix Scoring
- A grid combining likelihood and severity ratings to produce a risk score; scores above the defined acceptability threshold require documented controls and reassessment of residual risk.
- HAZOP Guide Words
- Standard terms such as no, more, less, as well as, part of, reverse, and other than applied to process parameters to systematically identify deviations from design intent.
- FMEA Risk Priority Number
- RPN equals severity times occurrence times detection; the value ranks failure modes for corrective action, with higher numbers receiving priority, and is recalculated after controls are applied.
- Lockout/Tagout Standard
- 29 CFR 1910.147 requires energy control procedures, lockout devices, employee training, and verification of a zero energy state before servicing or maintenance where unexpected energization could cause injury.
- Permit-Required Confined Space
- 29 CFR 1910.146 requires evaluation, permits, attendants, entry supervisors, pre-entry atmospheric testing, and rescue capability for spaces with hazardous atmospheres, engulfment, or entrapment potential.
- Fall Protection Trigger Heights
- Construction requires fall protection at 6 feet or more under 29 CFR 1926.501; general industry requires it at 4 feet or more under 29 CFR 1910 Subpart D.
- PPE Hazard Assessment
- 29 CFR 1910.132(d) requires employers to assess workplace hazards, select appropriate PPE, communicate selection decisions to employees, and certify the assessment in writing.
- Leading versus Lagging Indicators
- Leading indicators measure preventive activities such as inspections, near-miss reports, and training completion; lagging indicators measure outcomes such as injuries, TRIR, and DART rates.
- Inspection versus Audit
- An inspection verifies conformance to a defined requirement at a point in time; an audit is a systematic, independent, documented evaluation of the management system against criteria.
- Corrective Action Verification
- A corrective action is closed only after confirming it was implemented as planned and that it actually eliminated or reduced the cause of the nonconformity, verified through follow-up checks.
- PDCA Improvement Cycle
- Plan establishes objectives and controls, Do implements them, Check monitors and measures performance and conducts audits, and Act addresses nonconformities and drives continual improvement.
- Root Cause
- The management system deficiency that, if corrected, prevents recurrence of the incident; it is distinct from the direct cause, such as an unsafe act or condition.
- Five Whys Technique
- An iterative questioning method that repeatedly asks why a condition or event occurred, moving from the observed symptom down to a fundamental system cause.
- OSHA Fatality Reporting
- An employer must report a work-related fatality to OSHA within 8 hours of learning of it, using the telephone or the agency's online reporting system.
- Amputation Reporting Time
- Work-related amputations, in-patient hospitalizations, and losses of an eye must be reported to OSHA within 24 hours of the employer learning of the event.
- Emergency Action Plan Elements
- Minimum elements include reporting procedures, evacuation procedures and routes, employee accounting procedures, rescue and medical duties, and names or titles of contacts.
- EAP Oral Plan Threshold
- Employers with 10 or fewer employees may communicate the emergency action plan orally rather than in writing; employers with 11 or more must maintain a written plan.
- Fire Prevention Plan
- 29 CFR 1910.39 requires a plan covering major fire hazards, handling and storage procedures, potential ignition sources, and maintenance of fire protection equipment.
- Incident Command System
- A standardized, modular response structure using common terminology, unified command, and a span of control of three to seven reporting elements to manage emergency incidents.
- General Duty Clause
- OSH Act Section 5(a)(1) requires employers to furnish a workplace free from recognized hazards likely to cause death or serious physical harm where no specific standard applies.
- OSHA 300 Log Exemption
- Establishments with 10 or fewer employees and employers in designated low-hazard industries are partially exempt from routinely keeping OSHA injury and illness records.
- SDS Sixteen Sections
- Hazard Communication requires safety data sheets in a fixed 16-section format covering identification, hazards, composition, first aid, firefighting, handling, exposure controls, and disposal information.
- State Plan Requirement