CISEC · Put your knowledge to work in context.

The Certified Inspector of Sediment & Erosion Control (CISEC) is a professional credential for people who inspect construction sites for sediment, erosion, and storm water compliance. The certifying body describes its work as "Leading the World in Certifying Construction Site Inspectors of Sediment and Erosion Control and Storm Water Management," and the credential is aimed at environmental professionals who verify that best management practices are installed, maintained, and functioning on active construction projects. The CISEC case studies are 5 cases and about 3,416 words.

1

Building a Six-Hour Module 4 Inspection Course with a Mixed-Experience Crew

You are the training lead for a mid-sized general contractor building a 6-hour Module 4, "Conducting Construction Site Inspections," for field staff who assist CISEC inspectors. You have 18 attendees with mixed experience: 4 have never inspected, 9 inspect occasionally, and 5 inspect weekly.

717 words, about 4 min
2

Forecast Rain with Four Competing BMP Failures on a 14-Acre Grading Site

You are inspecting a 14-acre residential grading project in a region forecast to receive 0.6 inch of rain in 14 hours. You find: a 300-foot silt fence segment along the downslope perimeter with 40 feet of fabric sagging and 6 inches of sediment accumulated at the toe; a stabilized construction entrance with 25 feet of trackout on the public road; a concrete washout pit within 15 feet of a storm drain inlet with no liner; and an 80-cubic-yard stockpile of fill without cover.

699 words, about 3 min
3

Ten Weeks to CISEC Renewal with a Mixed Training Log

A CISEC-certified inspector's credential expires in 10 weeks. The inspector has accumulated 20 hours of training: an 8-hour internal company erosion-control seminar, a 6-hour vendor product demonstration, 4 hours attending a stormwater conference, and a 2-hour webcast on SWPPP implementation.

693 words, about 3 min
4

QSP Confronts a Missing BMP, No Sampling Kit, and an Open Drum Before Rain

You are the Qualified SWPPP Practitioner (QSP) on an 8-acre California construction site covered under the Construction General Permit. The Qualified SWPPP Developer (QSD) prepared the SWPPP.

693 words, about 3 min
5

Repeat Trackout Finding and a Blank Communication Log

You are a third-party inspector on a 3-acre commercial site. You have inspected weekly for six weeks.

614 words, about 3 min