Value stream mapping and process analysis
Value stream mapping and process analysis examines whether you can see material and information flow end to end, quantify delay, and design a future state with a plan. Questions often ask you to calculate lead time, takt, and value-added ratio, or to select the next kaizen.
Core rules
- A current-state map shows customer demand, information flow, process boxes (cycle time, changeover, uptime, batch), inventory triangles, and the timeline. Walk the actual flow; do not map from memory.
- Lead time is the sum of inventory days plus processing time, not just processing. Value-added ratio = value-added time / total lead time; use consistent time units.
- Mark kaizen bursts only where evidence shows a constraint or delay. The future state should be driven by takt, continuous flow where possible, pull where flow is impossible, and heijunka.
- Process analysis separates value-added, necessary non-value-added, and pure waste. Check capacity against demand before redesigning flow.
- A future-state map without an implementation plan, owners, and dates is a poster, not a plan.
Worked example
Demand is 150 units/day over one 450-minute shift. Three inventory triangles hold 300, 150, and 450 units. Inventory days are 300/150 = 2.0, 150/150 = 1.0, and 450/150 = 3.0, totaling 6.0 days. Processing time across the three processes is 9 minutes. Lead time = 6 days × 450 minutes + 9 minutes = 2,709 minutes. Value-added ratio = 9 / 2,709 = 0.33%. The reasoning matters: inventory dominates lead time, so cutting batch sizes or introducing FIFO/pull between processes will reduce delay more than speeding a 3-minute operation.
Traps
Do not average inventory days when demand differs by product family; calculate per family. Do not use annual demand when takt uses daily available time. Do not omit information flow, changeover, or uptime. Do not set a future state that assumes perfect uptime or zero variation.
Key points
- Map actual material and information flow, not memory.
- Lead time includes inventory wait plus processing; VA ratio uses consistent units.
- Design future state from takt, flow, pull, and heijunka.
- A future-state map needs owners, dates, and kaizen actions.