Grade-1 Cost Engineer Examination study materials
Grade-1 Cost Engineer Examination study resources

Grade-1 Cost Engineer Examination cheat sheet

Grade-1 Cost Engineer Examination · Keep the key ideas within reach.

Quick reference

Construction Engineering Cost Management

  • Cost management covers the full process: investment estimate, design estimate, construction drawing budget, bid price, contract price, construction cost, completion settlement, and final accounts.

  • The construction and installation engineering cost consists of labor cost, materials cost, construction machinery use cost, enterprise management fee, profit, and taxes (the 'cost plus fee plus tax' structure).

  • Labor cost is calculated as: quota labor consumption × labor wage unit price; it includes basic wage, wage subsidies, production worker auxiliary wages, employee welfare, and labor protection.

  • Material cost = (material net consumption + loss) × material unit price; loss rate = loss amount / net consumption × 100%.

  • Construction machinery use cost = depreciation + major repair + regular repair + installation and dismantling + field transportation + fuel and power + operator wages + taxes.

  • Enterprise management fee is calculated on a base of labor cost, or labor cost plus machinery cost, depending on the regional rule; profit is typically based on labor cost plus machinery cost.

  • Taxes under general tax method: VAT output tax = pre-tax cost × 9% (current construction VAT rate); under simplified tax method, the rate is 3%.

  • The Bill of Quantities (BOQ) pricing uses comprehensive unit price = labor + materials + machinery + enterprise management + profit + risk; it excludes taxes and fees.

  • Cost control methods include earned value analysis: CV = BCWP − ACWP; SV = BCWP − BCWS; CPI = BCWP / ACWP; SPI = BCWP / BCWS.

Quick reference

Construction Engineering Valuation

  • The investment estimate at the design stage uses the quota method or the index method; the construction drawing budget uses the quota method or the BOQ method.

  • The BOQ pricing method: total cost = Σ (engineering quantity × comprehensive unit price) + fees + taxes.

  • Comprehensive unit price = labor cost + material cost + machinery cost + enterprise management fee + profit + risk fee.

  • Quota pricing method: unit price = labor + materials + machinery; then add enterprise management fee, profit, fees, and taxes according to the quota.

  • The bill of quantities must specify: project code, project name, project feature, unit of measurement, and quantity; it is compiled by the tenderer.

  • Engineering quantity calculation follows the national measurement code (e.g., GB 50854 for building construction); the code is mandatory for state-funded projects.

  • The measure project cost includes: environmental protection, civilized construction, safety construction, temporary facilities, night construction, secondary handling, large machinery, scaffolding, and completion cleaning.

  • Other project costs include: provisional sum, provisional daywork, general contractor service fee, and total contract price service fee.

  • The bid price is composed of: cost, profit, and tax; the bidder may adjust enterprise management fee and profit but not taxes or statutory fees.

Quick reference

Construction Engineering Technology and Measurement

  • Earthwork measurement: excavated volume = (base length + 2 × working face + 2 × slope coefficient × depth) × (base width + 2 × working face + 2 × slope coefficient × depth) × depth + 1/3 × slope coefficient² × depth³.

  • For a foundation pit with slope, the volume formula: V = (a + 2c + kH) × (b + 2c + kH) × H + 1/3 k²H³, where a,b are base dimensions, c working face, k slope coefficient, H depth.

  • Concrete volume for beams: measured in cubic meters, calculated by cross-sectional area × beam length; beam length is taken as clear span plus half the support length at each end.

  • Rebar measurement: weight = length × unit weight; unit weight (kg/m) = 0.00617 × d² (d in mm).

  • Formwork area is measured by contact area with concrete; for beams, the area = beam bottom + both sides; for slabs, the bottom area.

  • Masonry measurement: volume = wall length × wall height × thickness, deducting openings larger than 0.3 m² and embedded concrete components.

  • Roof waterproofing area = roof horizontal projection area × slope coefficient + additional layer area; the slope coefficient depends on the roof gradient.

  • Pile foundation measurement: bored pile volume = design cross-sectional area × design pile length (including pile cap).

  • Scaffolding measurement: for buildings, the area is the building's horizontal projection area; for independent columns, the volume is calculated.

Quick reference

Cost Case Analysis

  • When analyzing a contract price adjustment case, first determine the contract type (fixed price, adjustable price, cost-plus-fee) and the risk-sharing clauses.

  • For engineering quantity deviation, use the BOQ clause: if the actual quantity deviates by more than 15% from the BOQ quantity, the comprehensive unit price may be adjusted.

  • For material price fluctuation, apply the price adjustment formula: ΔP = P0 × [A + B × (Ft/F0) − 1], where A is the non-adjustable portion, B the adjustable portion.

  • For a claim, the critical path method is used to analyze time impact; cost impact is calculated by the actual cost method or the contract rate method.

  • In a settlement case, the completion settlement is based on the contract, design changes, site visas, and claim documents; the final account includes the settlement plus other costs.

  • For a cost overrun analysis, compare the budgeted cost with the actual cost, and use the earned value method to identify whether the overrun is due to schedule or cost.

  • For a bid evaluation case, the evaluated bid price = bid price + adjusted amount for deviations; the lowest evaluated price is not necessarily the lowest bid price.

  • For a progress payment case, the payment = completed project cost − retention money − advance payment deduction − other deductions; retention money is usually 3%-5% of the contract price.

  • For a change order case, the new rate is determined by: (1) the contract rate if applicable; (2) a rate derived from similar work; (3) a new rate agreed by both parties.