Ruankao Information System Project Manager (Senior): Procurement choices, supplied contracts and incentives

Ruankao Information System Project Manager (Senior) · Work through your exam, one topic at a time.

All guide sections

Procurement choices, supplied contracts and incentives

Domain 10 covers make-or-buy analysis, the three contract families and their risk allocation, the source-selection process, and contract control. Calculation items on incentive-fee contracts appear regularly, as do scenario items on which contract type suits an unclear scope.

Planning procurement

  • Make-or-buy analysis compares internal cost and capability against external supply.
  • Fixed-price family: firm-fixed-price (FFP) suits a well-defined scope and puts maximum cost risk on the seller; fixed-price incentive fee (FPIF) shares overruns against a ceiling; fixed-price with economic price adjustment (FP-EPA) protects long-term contracts against inflation.
  • Cost-reimbursable family: cost plus fixed fee (CPFF), cost plus incentive fee (CPIF), cost plus award fee (CPAF). The buyer bears most cost risk and must audit the seller's costs.
  • Time and materials (T&M) is used for small, urgent, or poorly defined work and should carry a ceiling.
  • Procurement documents: RFI, RFP (solution and price), RFQ (price), IFB (bid).

Conduct and control

  • Conduct procurement: bidder conferences, independent cost estimates, proposal evaluation, negotiation, award.
  • Control procurement: contract change control, performance review, inspection and audit, seller payment, claims administration, and procurement audit. Use the actual contract’s authorized change procedure and applicable law. A written approval trail supports control, but no blanket statement about every possible oral agreement is inferred here.

Worked example

FPIF: target cost 100万元, target fee 10万元, target price 110万元, ceiling price 130万元, sharing 70% buyer / 30% seller. Actual cost is 120万元, an overrun of 20万元; the seller bears 6万元, so fee = 10 − 6 = 4万元 and price = 124万元, below the ceiling. If actual cost were 140万元, the computed price would be 138万元, but the ceiling caps the seller at 130万元, so the seller absorbs a 10万元 loss.

Traps that cost marks

  • Choosing cost-reimbursable contracts for a stable, well-defined scope.
  • Forgetting that CPFF requires the buyer to audit seller costs.
  • Ignoring the ceiling when computing FPIF settlements.
  • Accepting an oral contract change.
  • Confusing a procurement audit with a financial statement audit.