CompTIA Project+ · Keep the key ideas within reach.

Quick reference

Project Management Concepts

  • A project is temporary and produces a unique product, service, or result; operations are ongoing and repetitive.

  • Triple constraint: scope, schedule, and cost, with quality at the center - changing one constraint generally requires adjusting at least one other.

  • The project charter authorizes the project and the project manager's authority; it is issued by the sponsor, not written or approved by the project manager alone.

  • Authority spectrum: functional < weak matrix < balanced matrix < strong matrix < projectized.

  • In a functional organization the project manager typically acts as coordinator or expediter with little formal authority over resources.

  • RACI rule: only one person is Accountable per task; multiple people may be Responsible, Consulted, or Informed.

  • Project phases may run sequentially (predictive) or overlap/iterate (adaptive); exiting a phase normally requires a gate or phase-end review.

  • A PMO may be supportive (templates, training, best practice), controlling (compliance required), or directive (project managers report to it).

  • Lessons learned are captured at phase gates and at project close, not only at the end of the project.

Quick reference

Planning and Forecasting

  • WBS rule: decompose deliverables, not activities; the lowest level is the work package, and the 100% rule requires all scope to be represented.

  • PERT weighted estimate = (O + 4M + P) / 6; simple triangular estimate = (O + M + P) / 3.

  • PERT standard deviation = (P − O) / 6; variance = ((P − O) / 6) squared.

  • The critical path is the longest path through the network and sets the shortest project duration; total float on the critical path equals zero.

  • Total float = LS − ES = LF − EF; free float = ES of the successor − EF of the activity.

  • The cost baseline is the approved, time-phased budget that includes contingency reserves but excludes management reserves.

  • Contingency reserve covers known-unknown risks; management reserve covers unknown-unknowns and sits outside the cost baseline.

  • Resource leveling can extend the schedule or change the critical path; resource smoothing uses only float and does not change the finish date.

  • EVM forecasting: CPI = EV / AC, SPI = EV / PV, EAC = BAC / CPI when current cost performance continues, and VAC = BAC − EAC.

Quick reference

Executing and Delivering

  • Tuckman sequence: forming, storming, norming, performing, adjourning; storming is a normal stage and is worked through rather than avoided.

  • Conflict approaches ranked by durable outcome: collaborating, compromising, smoothing or forcing, with avoiding as a last resort.

  • Change flow: submit request, log it, assess impact, obtain CCB decision, update baselines, implement, verify, then communicate.

  • Only approved changes modify baselines; unapproved change requests are not implemented.

  • Quality assurance is process-focused and preventive during execution; quality control is product-focused and detective on deliverables.

  • The issue log records problems that have already occurred; the risk register records uncertain future events.

  • Acceptance criteria belong in the scope statement and WBS dictionary and are defined before the work is performed.

  • A phase gate is a go/no-go decision point, while a kill point is a decision to terminate the project early.

  • Closeout includes formal acceptance, contract closure, resource release, and archival of lessons learned.